HomeMy WebLinkAboutBLD2003-00731 0 Ill
BUILDING PE
RMIT
Jefferson County Department of Community Development
621 Sheridan Street, Port Townsend, WA 98368
(360)379-4450 FAX (360)379-4451
PERMIT #: BLD03-00731 Received Date 11/20/2003
SITE ADDRESS: 33 LEIGHBROOK LN Issue Date 12/11/2003
PORT LUDLOW, 98365
APPLICANT: PORT LUDLOW ASSOCIATES LLC PHONE:
70 BREAKER LN
PORT LUDLOW WA 983659766
SUBDIVISION: TIMBERTON VILLAGE PHASE I Block: Lot: 17
PARCEL NUMBER: 998500017 Section: 17 Township: 28 N Range: 01 E
CONTRACTOR: PORT LUDLOW ASSOCIATES LLC PHONE: (360)437-2101
70 BREAKER LN
PORT LUDLOW WA 98365
Contractor's License: PORTLAL994L8 Expires: 05/02/2004
LOAN LENDER/
BOND HOLDER:
PROJECT DESCRIPTION: NEW SFR W/ATTACHED GARAGE & DECK(S)
REQUIRED INSPECTIONS:
[ ] SETBACKS: ,. k w/end 1 !lr 3/o1� /
[ ] UFFER: eV1/13/0411P // `
[ ] Footing: 2J' ev odit'G„ I r13jG1,
[ ] Foundation: c7< /in./o fl(;!'
[ ] Underground Plumbing:
[ ] Underground Insulation:
[ ] Shear Wall : 71< GJ,/cGndr ir�4s 3/si jo / .
[ ] Framing: k ,Y/,- 3/0c
I1 Plumbing: 23/09
[ ] Propane Tank/Lines: )Ji
y_ y/,2.31b'
[ ] Insulation: 9 ,%6 y
I 1 Sheetrock: k 14): m drtion S.7lofC1
[ ] Septic Sytem Final Approval: —
[ 1 Zoning Final Approval:
[ ] Final/Occupancy Approval: r-- =-/-p y
HEALTH DEPARTMENT APPROVAL REQUIRED PRIOR TO FINAL INSPECTION
THIS PERMIT IS VALID FOR ONE YEAR OR IT MUST BE PROPERLY RENEWED
BUILDING INSPECTION HOT-LINE 379-4455. CALL 24 HOURS IN ADVANCE TO SCHEDULE INSPECTIONS.
Office Hours 9:00 a.m. -4:30 p.m.
HOT LINE AVAILABLE 24 HOURS A DAY
SPECIAL CONDITIONS APPLY -SEE REVERSE
Illt
UILDING PERMIT APPLICA N MReview Ty : I
LLA03 006 25
Jefferson County Department of Community Development
621 Sheridan Street Port Townsend, WA 98368
PERMIT #: BLD03-00731 Received Date: 11/20/2003
SITE ADDRESS: 33 LEIGHBROOK LN
PORT LUDLOW, 98365
OWNER: PORT LUDLOW ASSOCIATES LLC PHONE:
70 BREAKER LN
PORT LUDLOW WA 983659766
SUBDIVISION: TIMBERTON VILLAGE PHASE I Block: Lot: 17
PARCEL NUMBER: 998500017 Section: 17 Township: 28 N Range: 01 E
CONTRACTOR: PORT LUDLOW ASSOCIATES LLC PHONE: (360)437-2101
70 BREAKER LN
PORT LUDLOW WA 98365
Contractor's License PORTLAL994L8 Expires 5/2/2004
REPRESENTATIVE: PHONE:
PROJECT DESCRIPTIOF NEW SFR W/ATTACHED GARAGE & DECK(S)
TYPE OF WORK RES SQUARE FOOTAGE:
TYPE OF IMP NEW MAIN: 1,520
VALUATION 147,564.00 ADD'L: 478 HEAT TYPE: EEE
CODE EDITION: 1997 HEAT BASE: HEAT TYPE: PRO
OCCUPANCY: R-3 UNHEATED: #OF STORIES:
OCCUPANCY: OTHER:
CONST TYPE: 5N SHORELINE:
GARAGE: 604
CONST TYPE: SETBACK:
DECK: 180
BANK HEIGHT:
SEWAGE DISPOSAL: SEW
WATER SYSTEM: LUDLOW PARCEL TAGS: YES NO
BEDROOMS: BATHROOMS: STORMWATER: YES NO AREA
Exist: Exist: Wetland Erosion
Prop: 3 Prop: 3 Seismic Streams
Total: 3 Total: 3 Flood Way Floodplain
Routing Date: F&W Landslide
t11 � /Q`� Shoreline Aquifer
Forest: Commercial Rural
Type Amount Paid Bv: Date: Receipt: ��Oyrtey,ctPermit $1,262.55 KAS 11/20/03 60384
State Building Code $4.50 KAS 11/20/03 60384
Potable Water Application $51.00 KAS 11/20/03 60384 DEC 1 2 2003
Total: $1,318.05 Jefferson County Planning
& Building Department
1 Jefferson Colpartment of Community Development
" ` 621 Sheridan Street,Port Townsend WA 88368[3601310-4450
o
PErmot A c?-'0 0 c o
a�.,::(\s,,
� NOV 2 0 2003 ,�. ,, \ J`J m t
998-500 -o 1
Project Description: J1'OC/C PLR,7 L/Z
}} _
y
Building Type: �;.,, Project Type: Frame Type:
XSingle Family r' � X New X Wood
x Garage Attached/Detached Addition Steel
Modular Alteration/Remodel Concrete
Commercial Repair Masonry
Multi-family/#of Units Demolition Other:
Industrial
Other:
Bathrooms: Bedrooms: Type of Sewage Disposal: Type of Heat:
Choose one:
Existing: D Existing: ( 't( Sewer Community System X Electricity Oil
Proposed: 3 Proposed: 3 Individual System Woodstove Propane
Total: 3 Total: 3If not sewer,fill out the following: Heat Pump
Conventional Alternative Other propane Ft'icp/ote.
Permit# SEP _
Water Supply:
Private well Two Party Well XPublic:Name of water system: 04,5 i
Square Footage: ,; �.i«"' w.. ...
l,. 7 00
Main Floor /5 2 CD 0� -iu
2ND Floor �� i. [7Z- C� �
3rd Floor t. fee 'fcc(C (i'2r2 4/a
Htd Basement $ rch -d arge fee' "I •
Unhtd Basement Subtotal (- (�. QGarage/Carport 601, P2 t Water Review fee [1
Decks /S0 911/Rd Approach fee 1. _1 1
Commercial TOTAL ( ; ,7;•
Industrial Receipt# ''" ;,
Other Cash/Check# I, (C
l
Total Valuation: //Si 000 Initials S`E[. g?.
Or Date � f o
Estimated Cost:
If within 200' of the Shoreline,
Distance to Bank or Ordinary High Water Mark ft.Bank Height ft.
By signing the application form,the applicant/owner attests that the information provided herein is true and correct to the best of their knowledge. Any material falsehood or any
omission of a material fact made by the applicant/owner with respect to this application packet may result in this permit being null and void.
I further agree to save,indemnify and hold harmless Jefferson County against all liabilities,judgments,court costs,reasonable attomey's fees and expenses which may in any way accrue
against Jefferson County as a result of or in consequence of the granting of this permit.
I further agree to provide access and ri ht of e to Jefferson County and it's employees,representatives or agents for the purpose of application review and any required later inspections.
Access and right of entry to .pli 's p o erty or structure shall be requested and shall occur during regular business hours.
Signature: Ake..„:„.7
_ Date: 1 ) 1/ -1 Q 3
OVER ►
ll:I IOME\PLNCNTR\INFOBLDG\FORMS\BLDpermitApplication 11-8-01
08/26/99 05:03 FAX 206+78_Q+2408 MacLearnsberry �.�IT Bi C�O1
•
_3
Novan
20'‘Iikt„\s, , 200.:. •
111111
O r •
..,.., :....
....._ ..:.....„...... .i, y/
// h //
/Ny ,, ,,,-,,. ,.,A
/ {} :,
j:4
-Y ti:}v V_ x:u•Y
./ 1 'y h
i it
rtiF{e>,,....::N,-xx
r / ;}.;n'•:S: ,r•: :...5•:.Six-__S S'v: /
_ '� , r fit:}:'+Y�kvi•}-411 � \•^•i:}'.,. .;..y.,_X%%:.::u -- •13:4%i\,}'
4.
�... I .
.4.\ .:
.'mil - •%" • :'..r:,...:::•:_v,:i:::A=-fi<::fts:`�t,:.:,�:.�'<f,'iii�a _
�� iV }�}�.:6•:` . >ih,:'r\gin _ _ _ :iN•�: tiZ.t_\�L:.Ma;✓n_j
AI �ANi'h` :Y.Win_ 4:~'�h'ti:-: ___ �`_C.:4•}\.4..i._l_++YY�' • CS•0 - ::I
Q`Xix-%�\K:\S.J.-,:., fd:..•.(l._:y>_}J4'.ti�'Z}:5i. i:3.
.� J p Si)CY:•h..3-:.}}*-N.i. .k%^R=_j-Yl'gA:ii:Sf�lf,J..
_t:iiSY'^n-'VR<:lvF�-'i_• }}-4.i:G�J'xi�0.•iti:i:!L-i•Y:K v. :K.y:.Z.
%�,t / ....;;**.a:o-Tie3Xx:3y, +iw,•KYit4 :cia::tti.h.
O _ ih��Si^MX-�'ht:i •AuiM:}>ii n s.. /
":: �iti.XSf•Y•:X-%:4' Y v:..tim.:z.p. -dpffi ' l�i::.v,8?:- 3• .,f-
1 / • -'iN'y�i%u •4'.v''l- v:ey.y.1;Y.:�v' a•'}r' .Ln�,w-i':'t::._:e.:_ __
-S,i-•: • G;:r.V.i9:-\4'((:t: P- W :'._Y:,v-ii••' a ,,,c,• -h X-W V:, -•/
y,S+s,.,4- �s;.;%3::?�Q:,} �•:ti anti»•4h'.n}>�
/ ri'ks}:n�f... .wis.-- .::ti ;.Yh a�x-: .x,-tt•:v,.- _
v.;:loi-.�!-\C Y;•%•;•3};••t:.1C: h:'ti?#::X_�fh:_ ,J•i4}Y[rit}i'}` _ .../
•• �, :Y:P)�---!A?RS}i\iL:iC3kCti?.:Gv\S- 'N•;i:Y:."._-.^ .Y�35}YStiF&H2< _
�P>fy}3•::t•,'•}Y'^.'.'`,'Cs<i:i'0'...•r.,�. f,•,f:`3i 9._`l:i.u�f,,
_. '•h g.a..uac jti'N_0:wn:K:;a,+�:M:,V `h-R,:.v.iNgAtit4. • ''; _
• '•�:•/ ••:ii::6WSfpiaC`ij±o'b`.;:•::{i-',',yyi:�t::::•;t-,�.;..t:•f::•8:1,•:••• }8•
V ie is - _ _*:4,xcx..•4h:2:'h fic...:::5t:Aqc••.C: 4:s5*-.�}}}h•hth.• /
Y-!.:.,3v3<pj::-3:k•:i}j.}: 'ivW.M'.Xd.•i4(f.,t,4,,•:.:C!ri..�: �.
CN:vl(•,Ay6' ,... ▪ ,
Ir% C° - -.
:v:vr:_.•,,Yp:ey:i\�:P:A:p--}ty /
/ •
rtihx`M�4*P4:uSi'
Y•ZtvH-VAS •.
/ �'n}}14'ti'FC /
:Y\
/ •
/
/ /
/ /
/ '
I /
// /APP ' •
lb/
PLAN
/
/ DEC - 1 2003
" � e:ii
,,
JEFFERS CO TY
4.
DEPT.OF CO y B1,OP E 4T
SIGNATURE:
(0)
MACLEARNSBERRY, Inc. Olympic Resource Mgmt.
Land Surveyors c Civil Engineers o Pliers Lot 17 Plan 42L
159 Wyatt Way NE Timberton Village
ainbridge Island,WA 98110
phone: (206)842-5514 feesimil.:(206)780-2408 DRAWN BY CAN r AUGUST 26, 1999 r Na9807
CHECKED Br 6AMP 1" = 20' er 1 Kx 1
PERMIT # BiD
03 - 7 3 4
JEFFERSON COUNTY 71
STORMWATER MANAGEMENT
SMALL PARCEL EROSION AND SEDIMENT CONTROL PLAN
EROSION AND SEDIMENT CONTROL WORKSHEET
Property Owner: Port Ludlow Associates Telephone: 437-2101
Address: 70 Breaker Lane, Port Ludlow, WA 98365
Assessor's Parcel Number: ! 9 g-5-00-O(7
Building Permit or Septic Permit Application Number(if applicable):_
Brief Project Description: New Single Family Residence W/ attached garage.
Site Location: 33 Jei jh brco1 Ian€
Person Responsible for BMP Installation and Maintenance: Jeff Evange r
( Address: Same as above
Telephone:Same as above
1. Describe/check the Best Management Practices (BMPs) that you will implement during land
disturbing activities or construction to control erosion and prevent sediment from entering water
bodies (marine waters, streams, rivers, lakes, or wetlands) or impacting adjacent property or
roads. Please check the measures you plan to implement and show their approximate location on
the site plan. You may also propose measures other than those listed. Attach additional sheets,if
more space is required.
[l Stabilize construction access route. Limit construction vehicles to one route, if feasible.
Provide a stabilized construction access by applying quarry spalls, ballast, or crushed rock
to minimize tracking sediment onto roads. (See attached illustration from Stormwater
Management Manual.) If sediment is transported onto roads, they will be cleaned
thoroughly.
[) Minimize the extent of land disturbing activity and preserve existing vegetation.
Preserve buffers of well-established vegetation between disturbed areas and property
boundaries, roads, water bodies, and designated critical areas (wetlands, fish and wildlife
habitat areas,landslide or erosion hazard area,etc.).
APPROVED
STORMWATER PLAN
SPESC Instructions—Short Form
Revised July 17,2002
3 DEC - 1 2003
JEFFERS° C NTY
DEPT.OF C TY ELOPME
SIGNATUR ' „�
a--,',,, y a.' .c KJ, Ef Pf
ft
NOV 2 0 2003 s
EROSION AND SEDIMENT CONTROL WORKSHEET!
r
.: x of r P i-f`4ri i�EVEIoF''M1
[] Phase clearing so that only areas that are actively being worked are uncovered:a —'-.n.,.`,—
[] Start and complete land disturbing activities and stabilize the site between April 1
and September 30. Stabilization means that disturbed areas will have well-established
plant cover or be landscaped to minimize erosion.
[)1 Stabilize exposed soil Exposed and unworked soil will be covered within 2 days between
October 1 and March 31 and within 7 days between April 1 and September 30.
[ ] Cover exposed soil with a minimum of 2 inches of straw or hay or other material
approved for this purpose.
[ ] Cover soil stockpiles with plastic sheeting and locate away from water bodies, roads,
and property lines.
[] Place gravel base on roads,driveways,and parking areas after clearing and subgrade
preparation.
[f Protect adjacent properties and water bodies from sediment deposition:
[] Place straw or hay bales in ditches and drainage ways down slope from areas
of land disturbing activity to filter runoff before it leaves the project site or enters
water bodies.(See attached illustrations from Stormwater Management Manual.)
[ ] Install a filter fence down slope from areas of land disturbing activity to filter runoff
before it leaves the project site or enters water bodies. (See attached illustration from
Stormwater Management Manual.)
[X Regularly inspect and maintain all BMPs especially after storms events.
[) Describe other erosion and sediment control Best Management Practices. Be specific
as to design and specifications.
Site is very flat with sandy soils . So I helieve the above
measures will be sufficient.
SPESC Instructions—Short Form
Revised July 17,2002
4
•
1 w t� �", W 4t
4i
NOV 2 0 2003
EROSION AND SEDIMENT CONTROL WORKSHEET
2. Describe how disturbed areas will be permanently stabilized(seeded, landscaped,apply gravel base
to roadways,etc.)
Areas that are distrubed will be landscaped with natural
type vegetation and Fawn to property line
3. Describe how runoff from impervious surfaces will be controlled (disperse to vegetated areas to
infiltrate,dry well,infiltration trench,route runoff to existing drainage facilities,etc.).
All impervious surfaces will he run to roof drains and
catch basins as designed into the plat requirements,
SPESC Instructions—Short Form
Revised July 17,2002
5
NOV 202003
EROSION AND SEDIMENT CONTROL WORKSHEET
_ ray .`Y
4. Specify your construction sequence. Describe the timing of all land disturbing activities (clearing
and grading, construction, installation of drainage facilities, landscaping, etc.) and Best
Management Practices.Describe proposed maintenance of BMPs.
After excavation the soil piles will be covered and silt
fence will be installed. Silt fence will be left in
place until we are ready to landscape and all roof drains/
catch basins are in, Landscaping will be installed as
early as possible on the exterior of the building when
all exterior concrete work is completed:,( ,
The Best Mana a nt Practices proposed above will be implemented to control erosion, sediment, and
stormwa of. wi
ll ctify the Jefferson County for inspections as re uire
/ !
Signature of caner/Agent Dater J
SPESC Instructions—Short Form
Revised July 17,2002
6
I
SPECIAL CONDITIONS FOR CASE t BLD03-00731
1.) The application was reviewed by the Jefferson County Department of Community
Development staff on November 28, 2003 for the potential presence of Environmentally
Sensitive Areas (ESAs) under the provisions of the Unified Development Code (UDC).
After an initial Geographic Information Systems mapping review and an investigative site
inspection, the following ESAs were confirmed to be present on the subject property:
landslide 1; Blue Heron.
2.) The applicant is proposing to create or add 2,324 square feet of impervious surface and
4,324 square feet of land disturbing activities.
3.) A Small Parcel Erosion and Sediment Control Plan has been submitted and approved by
the Department of Community Development. Once the subject permit has been issued
the applicant shall fully implement the provisions of the submitted plan and contact the
Jefferson County Department of Community Development to arrange a schedule to
inspect the property for plan compliance. A Certificate of Occupancy will not be issued
until the Department verifies plan compliance. No clearing for roadways or utilities shall
occur on the project site until clearing necessary for the installation of temporary
sedimentation and erosion control measures have been completed.
4.) Jefferson County determined that this proposal is categorically exempt from review under
the State Environmental Policy Act (SEPA)pursuant to WAC 197-11-800(1)(b)(i).
5.) The site plan as submitted with the single family building permit application on November
20, 2003 has been reviewed for consistency under the UDC, and has been approved by
Jefferson County Department of Community Development. Any modifications, changes,
and/or additions to the stamped, approved site plan dated December 1, 2003 shall be
resubmitted for review and approval by Jefferson County Department of Community
Development.
6.) This approval is for a single family residence with attached garage &decks only. Any
future permits on this site are subject to review for consistency with applicable codes and
ordinances and does not preclude review and conditions which may be placed on future
permits.
7.) Outdoor residential storage shall be maintained in an orderly manner and shall create no
fire, safety, health or sanitary hazard.
8.) Maximum lot coverage is not to exceed 45%. Lot coverage is defined as amount of
impervious surface which includes roof tops, driveways, concrete, etc.
9.) The building height is not to exceed 35 feet.
10.) Minimum setback from Leighbrook Lane right-of-way shall be 20 feet. Minimum side and
rear setbacks shall be 5 feet.
11.) The parcel has been designated as MPR SF4:1 under the Jefferson County
Comprehensive Land Use Map effective August 28, 1998.
12.) The lot was created through the Timberton Village Phase I Subdivision on August 7, 1995
under AFN 383713.
13.) The parcel is not located within a landslide hazard area. Hill shade GIS map identifies
elevations as ranging from 186 feet at the southwest corner to 181 feet in at the northeast
corner.
14.) Per email dated December 9, 2003, Jeff Davis (WDFW)the proposal will not have an
impact on the Great Blue Heron.
15.) An address of 33 Leighbrook Lane has been assigned to the parcel. Leighbrook Lane is a
county local access road (C516809).
16.) Per MPR Code Section 3.107, Accessory dwelling units (ADU's)shall not be allowed in
the MPR-SF zone. e,
17.) The lot is subject to Port Ludlow sewer and water.
18.) A minimum of two (2)on-site parking spaces shall be provided for the single family
residence.
19.) Not more than two (2)unlicensed or inoperable vehicles shall be stored on any lot less
than one-half acre unless totally screened from view of neighboring dwellings and
rights-of-way. Such screening shall meet all applicable performance and development
standards specific to the district in which the storage is kept, and shall be in keeping with
the character of the area. Screening shall meet the requirements of Unified Development
Code(UDC)Section 6. Outdoor storage of thirteen (13)or more unlicensed or inoperable
vehicles is prohibited except in those districts where specified as an automobile wrecking
yard or junk (or salvage)yard and allowed as a Permitted Use in Table 3-1 of the UDC,
and such storage shall meet the requirements of UDC Section 4.10. In no case, shall any
such unlicensed or inoperable vehiclesbe stored in an Environmentally Sensitive Area
(ESA).
I:\F_BLD_Permit_Buildng.rpt 10/29/19