Loading...
HomeMy WebLinkAbout40_Phasing Response_2024-0325County Comment: The Project Narrative states, “The project is proposed to include two divisions (phases).” The cover letter included with the preliminary plat application, however, indicates the PHMPR project will not be phased. A phasing plan was agreed upon by PHMPR and approved by the County as an amendment to the Development Agreement on July 22, 2019, following Kitsap County Superior Court’s disapproval of the initial phasing plan in its March 28, 2019, decision in The Brinnon Group v. Jefferson County, et al., No. 18-2-01758-18 (“the Court Order”). The Development Agreement (as amended on July 22, 2019) contemplates but does not necessarily require phasing, stating in Section 10.1 “Future development of the Pleasant Harbor MPR and all associate d infrastructure, including roads and utilities, may be reviewed, permitted and constructed and/or bonded in phases or sub -phases.” Please clarify the proposed approach to phasing, including revising the applicable application materials. This clarification should address, in particular, how PHMPR plans to sequence all preliminary facilities, public amenities, and access listed in Sections 10.1, 10.2, and 10.3 of the Development Agreement to achieve compliance with the Development Agreement (as amended on July 20, 2019) and the Court Order. This clarification should also identify deviations from the requirements in Sections 10.1, 10.2, and 10.3, such as the elimination of the LOSS system. Applicant Response: The refence to “phases” in the Project Narrative was a poor choice of words. The intent of the Project Narrative was to explain general sequencing of development. It was not intended to propose a new “phasing” plan. The attached revised Project Narrative removes the reference to phasing. To be clear, the project is not being phased in the sense that the applicant has not applied for a preliminary subdivision of a portion of the MPR and securing final plat, and developing the final platted property before subdividing other portions of the MPR. Rather, the Applicant has opted to secure preliminary subdivision approval of the entire MPR. The sequencing of development of Preliminary Facilities, Public Amenities and other resort development will , however, continue to comply with the requirements of the Development Agreement, state law, and the Jefferson County Code. Subdivision occurs in two steps: (1) preliminary subdivision and (2) final subdivision. Following preliminary subdivision approval applicants generally have five years to complete the required infrastructure improvements needed to achieve final plat approval. So, from a sequencing standpoint, the applicant will begin constructing the essential infrastructure and the Section 10.2 “Preliminary Facilities” needed to service the lots and tracts first so it can secure final plat approval. This includes constructing roads and utilities like water, sewer and stormwater.1 Additionally, the applicant will begin the grading and construction work for the golf course after preliminary plat approval. 1 The applicant may opt to apply for final plat approval for a portion of the larger preliminary plan of subdivision however any partial request for final plat approval will follow the segregation of planned development in the DA to allow for appropriate sequencing of development of the MPR. Exhibit 40 Following final plat approval, sequencing of construction will generally follow the sequence anticipated in the phasing plan. For example, the applicant will begin construction of the Recreation and Conference Center complex which includes many of the minimum recreational amenities, 220 guest suites, conference rooms and associated parking structure. Construction of this structure will be first because it includes all the minimum recreational amenities required by the DA except for the golf course. Golf course construction will continue as the Recreation Conference Center Complex is under construction. The County inquired specifically about deviations from Section 10.1, 10.2. and 10.3. Deviations to Section 10.1 (Phasing Plan) are described above. As noted in our cover letter, the applicant is preserving Kettle B and is not constructing the LOSS as a temporary treatment facility to service development while the WWTP is constructed. Additionally, some of the units described in 10.1 may be renamed for marketing purposes and units reallocated to other buildings . Changing the building name and unit allocation should be expected and does not generate impacts that have not been assessed. The residential unit cap still applies as does the percentage that must be used for short - term visitor accommodations as described in the DA. Section 10.2 describes preliminary facilities needed for each phase. The preliminary facilities have not changed although we are not pursuing phases. The applicant may seek final plat approval for a portion of the preliminary subdivision. If so, there must be adequate preliminary facilities developed (or bonded) to service that final plat. Section 10.3 lists the minimum recreational amenities that must be provided. The applicant does not propose to change to this list. The phasing issues addressed in the Court Order concern how the residential structures and public amenities in the MPR are developed in relation to each other. The Court’s rational and decision is laid out in Section 16 of the Cover Letter dated November 20, 2023 that was submitted with the application and is not repeated here. The concerns raised by the Court are not applicable to the subdivision of the property because the plan of subdivision merely lays out the lots and tracts for development authorized by future permits. It does not authorize development or address the timing of development. The subdivision reserves adequate land for the required Preliminary Facilities and Amenities in Section 10.2 and 10.3 of the Development Agreement respectively. Exhibit 40