HomeMy WebLinkAbout.FINAL Rathvon Shoreline CUP Appeal Hearing Examiner Decision1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 1 OF 52
OFFICE OF THE HEARING EXAMINER
JEFFERSON COUNTY
IN RE APPEAL OF RATHVON
SHORELINE CONDITIONAL USE
PERMIT
DCD FILE NO. SDP2023-00020
FINDINGS OF FACT, CONCLUSIONS OF
LAW AND FINAL DECISION
OVERVIEW AND SUMMARY OF DECISION
Property owner and applicant Richard and Renee Rathvon (“Applicant”) proposes to
develop a single-family residence, with onsite septic and drilled well, on vacant property within
the Natural shoreline environment designation along Dabob Bay (the “Application”). The
Applicant’s property is addressed as 660 Twana Way, Quilcene, Washington 98376 (the
“Property”). Exs. 01 and 11. The proposed new house will be constructed outside of the 150-foot
shoreline buffer and 10-foot building setback. Ex. 11. A shoreline conditional use permit
(“SCUP”) is required for construction of a single-family home in the Natural shoreline
designation under the Shoreline Master Program (“SMP”) set forth in Chapter 18.25 of the
Jefferson County Code (“JCC”).
There is only one means of access to the Property (other than by barge, which is not
proposed), via a narrow, “primitive” private road, Twana Way. Twana Way may have been a
logging road at one time. It is cut into the hillside, and includes a stretch adjacent to a steep ravine
above property owned by appellants John DiMaggio and Michelle Oliver (“Appellants”). Twana
Way has been in existence since at least the 1970s; the Applicant’s proposed home is likely the
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 2 OF 52
last house that will be constructed along Twana Way. All other homes in the area have been built
with construction vehicles having used the same access road. There is no question that the
Applicant has an easement right to use Twana Way for access to the Property.
On April 10, 2025, the Jefferson County Department of Community Development
(“DCD”) issued a Type II administrative shoreline conditional use permit approving the
Application, File No. SDP2023-00020 (the “SCUP Decision”), subject to eleven (11) conditions
of approval.
Appellants filed a timely appeal of the SCUP Decision on April 23, 2025 (the “Appeal).
Among other things, the Appeal alleges that Jefferson County failed to obtain enough
information from the Applicant to properly analyze and require appropriate mitigation of
potential impacts of the proposed project on the shoreline environment. The main question in this
Appeal is whether the County conducted an appropriate, thorough review of the Application to
ensure that potential impacts to the shoreline of Dabob Bay are addressed and mitigated.
Appellants submit that the County failed to do so and that the Application should be denied.
Appellants’ primary arguments1 focused on whether the County should have, but failed
to adequately analyze: (a) potential shoreline impacts resulting from the Applicant’s use of
Twana Way as a haul route for heavy construction equipment; and (b) whether the Applicant’s
proposal includes widening and potential re-grading of Twana Way, such that Jefferson County
erred in determining that road improvements are “outside the scope of the shoreline application.”
These issues include the following related questions: (1) will the Applicant’s mere use of the
road result in de facto road alterations that will negatively impact the Dabob Bay shoreline
1Appellants’ attorney confirmed on September 30, 2025 (Day 4 of the hearing) that Appellants
are dropping the claims stated in paragraphs 4.8 and 4.9 of the Appeal.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 3 OF 52
environment as a result of erosion and potential landslides carrying harmful sediment and debris
into the bay; (2) are improvements to Twana Way (proposed or contemplated) part of a “full,
unified and integrated physical project,” subject to Shoreline Management Act (“SMA”) and
Shoreline Master Program (“SMP”) review as an integrated and non-severable part of the total
proposed single-family home development; and (3) do conditions of approval adequately protect
the interests of the public using the road, surrounding property owners and the shoreline
environment?
Over the course of a four day hearing, testimony was largely focused on whether
Applicant proposed, or whether he should have proposed, improvements to Twana Way for
purposes of construction vehicle access to the Property. The parties’ expert witnesses provided
competing testimony and written reports analyzing the critical areas in which Twana Way is
located and/or to which it is adjacent, including a landslide hazard area and a stream/stream
buffer. The parties’ experts set forth their conclusions regarding potential impacts from use of
the road – both with and without improvements. The Applicant provided testimony and
photographs of other construction vehicles successfully navigating Twana Way. Several of
Applicant’s witnesses2 testified regarding the ability of construction vehicles to use Twana Way
2Appellants objected to the admissibility of testimony of Larry Dean Reichert and Rob Miller,
stating that Applicant’s attorneys did not comply with Section B of Hearing Examiner’s Pre-
Hearing Order which directed that each party’s witness and rebuttal witness lists include a “brief
2-3 sentence summary of the testimony to be provided.” Applicant asserts that Larry Dean
Richert’s declaration (Ex. CA-9 ¶¶ 1-4), submitted in opposition to Appellants’ summary
judgment motion provided appropriate notice of the subject of his testimony at hearing. Applicant
also asserts that Mr. Miller’s witness disclosure informed Appellants of his intended testimony;
Applicant’s Pre-Hearing Brief also addressed the intended testimony of Messrs. Richert and
Miller. The Hearing Examiner finds that, under these circumstances, there was no undue surprise
as to the subjects of testimony and conclusions offered by these witnesses. Appellants’ attorney
was provided an opportunity to cross-examine each witness. Appellants’ objection is formally
overruled. See Smith v. Sturm, Ruger & Co., 39 Wn. App. 740, 750, 695 P.2d 600, 607 (1985).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 4 OF 52
to access the Property and the variety of construction techniques and hauling options that could
be used to safely construct the proposed home.
Appellants provided testimony and photographs of the road in its existing condition and
following recent use of Twana Way by other construction vehicles. Appellants testified regarding
their concerns of the impacts of Applicant’s contractors’ use of the road and expressed fears
regarding the steep slopes and drop-offs from the road onto their property, the ability of the road
to bear the weight of heavy vehicles, and potential landslides and erosion impacts that may result
in the transfer of debris downstream into Dabob Bay. Appellants expressed a desire to be able to
keep using Twana Way for their personal enjoyment and health, and the health of the dogs that
they foster. They fear that approval of the proposed development will negatively impact them.
To determine whether the Applicant did, in fact, propose improvements to Twana Way,
testimony and evidence was presented concerning statements made by persons other than the
Applicant3 in emails and in a February 25, 2025 report. Among other things, Appellants focused
on correspondence from Terry McHugh, a real estate agent and consultant, to Greg Ballard,
requesting that the County add language to the building permit providing blanket approval for
any future “repairs, maintenance and improvements to Twana Way to allow for safe travel
necessary for construction and inspections.” Ex. A-22. On the other hand, Applicant Richard
Rathvon assured Planner Donna Frostholm on January 30, 2025 that he was not proposing to
3 Appellants’ presentation of their case focused in part on whether Terry McHugh, a real estate
agent and consultant who did not testify at the hearing, acted as an agent for Applicant. The
Hearing Examiner finds that the circumstantial evidence in this regard is not enough to overcome
the direct testimony of Mr. Rathvon (Hearing Day 2 at 00:43-44; Hearing Day 2 at 1:10; and
Hearing Day 4 at 3:13) in which he stated that Mr. McHugh had limited authority to assist on the
project. Mr. Rathvon confirmed that he did not provide him authorization to make decisions on
the project. There is no signed authorization form providing agency authority to Mr. McHugh
from Mr. Rathvon in the record.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 5 OF 52
alter or expand the road, including “cut and fill” activities or removal of trees. Ex. 08, p. 3.
Admittedly, communications received by DCD during its review of the Application regarding
whether the Applicant was, in fact, seeking approval of road improvements were unclear. E.g.
Ex. A-01, p. 53 (February 5, 2025 meeting notes indicating Applicant’s contractor was being
“wishy-washy on whether road improvements” would be required); Testimony Day 1 at 1:13:00
and 1:30:00. And, the Applicant emailed a report entitled “Geologic Hazard Assessment for
Twana Way Improvements,” to Planner Frostholm on March 13, 2025, without comment or
clarification. Ex. 9; Testimony Day 2 at 00:54:29. Still, given the Applicant’s affirmation on
January 30, 2025 that he was not seeking approval of road improvements and the fact that no
specific road improvements were actually proposed (including any proposed locations and any
specific manner of making improvements), the DCD Decision includes condition of approval 7,
which states, “[t]his permit does not authorize any modifications to the existing access road. It is
the responsibility of the permittee to obtain any required permits.” Ex. 11.
Appellants also focused on documents circulated by the Applicant and others regarding
a potential road improvement project in 2023, specifically a “higher cost” proposal for Twana
Way improvements. These discussions did not come to fruition, however. The neighbors did not
agree to any road maintenance or road improvement project. Appellants also argued that
additional studies should have been required by DCD of the Applicant, specifically to address
the location of Twana Way in a landslide hazard area. Appellants’ position is that the reports
prepared by The Stratum Group are not “geotechnical reports” required under the critical areas
code (JCC 18.22.540(4), JCC 18.22.905 and JCC 18.22.945) for “land disturbing activity” or
“activity undertaken on land” within a landslide hazard area. JCC 18.22.200(1). However, such
reports are required when review is triggered under the critical areas code; it was not.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 6 OF 52
As set forth in the findings of fact and conclusions of law below, the Hearing Examiner
determines that Appellants did not meet their burden of proving the SCUP Decision is
unsupported by substantial evidence or constitutes error of law. The Applicant did not submit
any application for, and did not otherwise propose specific road improvements to Twana Way.
The weight of the evidence supports a determination that use of Twana Way, as is, will not result
in any adverse impacts to the shoreline, or to the public health, safety and welfare, provided the
Applicant complies with all conditions of approval set forth in the SCUP Decision and with the
two additional conditions of approval of this Decision. Mere use of Twana Way by construction
vehicles does not trigger critical areas review under JCC 18.22.200(1).
As conditioned herein, the Hearing Examiner finds and concludes that the SCUP Decision
approving the Application will be consistent with the critical areas, shoreline buffers and
ecological protection no net loss and mitigation regulations in JCC 18.25.270(2), critical areas
and shoreline buffer regulations in JCC 18.25.270(4), will not result in cumulative impacts
consistent with JCC 18.25.270(3), and will meet all shoreline conditional use permit criteria in
JCC 18.25.590(2), and criteria applicable to all conditional uses in JCC 18.40.530.
Therefore, the Hearing Examiner DENIES the Appeal and AFFIRMS the SCUP
Decision with MODIFICATIONS.
I. PROCEDURAL FINDINGS AND CHRONOLOGY
1. Jefferson County held a pre-application meeting with the Applicant on October
25, 2022, consistent with JCC 18.25.640. Ex. 02, p. 2; Ex. 03, pp. 71-79.
2. The Applicant submitted an application for an administrative shoreline
conditional use permit, and revisions thereto on May 18, 2023, November 16, 2023 and July 8,
2024 for construction of a single-family home in the Natural environment. Exs. 01-03; Ex. 12,
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 7 OF 52
p.2. The submitted site plan shows the proposed home is approximately 3,800 square feet. Ex. A-
01, p. 67. The Applicant previously submitted applications for Site Development Review,
Buildability Analysis and for Legal Lot of Record on December 2, 2022. Ex. 03, pp. 55-63. The
permit number assigned for the Application is SDP2023-00020. The Application is supported
with copies of recorded Notice to Title of Geotechnical Report dated June 1, 2023 (Ex. 03, pp.
80-83), approved septic permit dated November 20, 2023 (Ex. 03, pp. 84-88), determination of
ordinary high water mark (OHWM) dated November 11, 2022 (Ex. 03, pp. 27-29), and a copy of
a biologist report and survey showing setbacks relating to a Type Ns seasonal stream, emailed
on January 20, 2023 (Ex. 03, pp. 30-54). The Application is also supported by a cumulative
impacts analysis report (Ex. 08, Attachment F), and a Stormwater Management Plan. Ex. 03, pp.
20-26.
3. The County determined the proposed project is exempt from review under the
State Environmental Policy Act (“SEPA”), RCW Chapter 43.21C. Exs. 11-12.
4. The County provided public notice of the Application in accordance with JCC
18.40.150(2) and JCC 18.40.190(2) and (3), and accepted public comment on the Application
per JCC 18.40.220.
5. DCD approved the Application in an SCUP Decision dated April 10, 2025,
subject to eleven (11) conditions of approval. 4 Ex. 11; JCC 18.40.270. A Staff Report, dated
April 10, 2025, prepared by Donna Frostholm, Jefferson County Associate Planner outlines
4 Two recommendations for additional permit conditions were presented by Planner Frostholm
at the open record appeal hearing: A condition that Applicant repair Twana Way Road to any
pre-construction condition; and a condition that Applicant comply with the best management
practices as outlined in the Cumulative Impacts Assessment Report issued January 24, 2025. Ex.
8, Attachment F, page 58. The Applicant agreed to both of these conditions.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 8 OF 52
Findings related to the Jefferson County Comprehensive Plan, Critical Areas (Chapter 18.22
JCC), Stormwater (JCC 18.30.060 and 18.30.070), and the Shoreline Master Program (Chapter
18.25 JCC). Ex. CA-02; Ex. 12.
6. Appellants filed an appeal of the Permit to the Jefferson County Hearing
Examiner on April 23, 2025 in accordance with JCC 18.40.330(2). Ex. CA-01.
7. Appellants filed a timely Motion for Summary Judgment on June 27, 2025 with
supporting declarations and exhibits. The Motion requested the Hearing Examiner to reverse and
remand the Permit to DCD with instructions to evaluate potential impacts to the shoreline
environment caused by the Applicant’s use of Twana Way as a construction haul route, and
resulting from any widening and re-grading work on Twana Way. Exs. CA-03 and CA-11. The
Applicant and Jefferson County submitted briefing and declarations in opposition to the Motion
on July 7, 2025. Exs. CA05 through CA10. Appellants filed a Reply in Support of the Motion and
supporting declaration on July 8, 2025. Exs. CA11-CA12.
8. The Hearing Examiner entered an Order on Appellants’ Motion for Summary
Judgment on July 11, 2025, denying the motion on the grounds that genuine issues of material
fact existed.
9. Consistent with JCC 18.40.230, public notice of the hearing date on the Appeal
was posted on July 7, 2025 and mailed notice was sent on July 3, 2017. Exs. 15-16. The notice
included a link to attend the hearing via Zoom, a link to view the case file, and contact
information for the project planner, Donna Frostholm. Id.
10. The originally scheduled date for the hearing on the appeal was July 17, 2025 at
10:30 a.m. The Hearing Examiner opened the hearing on that date and continued the hearing to
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 9 OF 52
September 8-9, 2025. Additional mailed notice of the continued hearing date was mailed to
property owners within 300 feet of the Property. Ex. 16.
11. The Hearing Examiner conducted a pre-hearing conference with the parties on
July 17, 2025 and entered a Pre-Hearing Order on July 23, 2025.
12. The Hearing Examiner conducted a site visit to the subject Property and to view
conditions of Twana Way on August 23, 2025, followed by a site visit memorandum dated
August 26, 2025.
13. The Hearing Examiner presided over a four-day hearing on the Appeal on
September 8-9, 2025 and September 29-30, 2025. The hearing was held in a hybrid format (in
person and online via Zoom) on September 8-9, 2025, and was held solely online via Zoom on
September 29-30, 2025.
14. Review of the Appeal was conducted pursuant to JCC Chapter 2.30, and the
Jefferson County Hearing Examiner Rules of Procedure (“RoP”) dated October 15, 2019. The
appeal hearing was conducted as an open record hearing as required by JCC 2.30.090. Public
comment and testimony was permitted. However, no members of the public attending the hearing
provided any comment or testimony at the hearing.
15. On day 3 of the 4-day hearing, Appellants narrowed the scope of issues to be
considered, removing their objections to the Applicant’s proposed residential construction, which
includes the septic system, stormwater management, aesthetics and cumulative impacts
associated with the proposed residential construction.
16. All witnesses presented testimony under oath.
17. All exhibits submitted by the parties were entered into the record without
objection and have been considered by the Hearing Examiner in this appeal.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 10 OF 52
18. The appeal hearing closed on September 30, 2025. The record was left open until
October 14, 2025, for submission of written closing arguments by the parties’ attorneys. By
stipulated agreement, the parties requested, and the Examiner approved, an extension of the
deadline for closing arguments to October 20, 2025.
19. The parties submitted final legal arguments on October 20, 2025.
20. The following exhibits comprise the record on the appeal:
00 Exhibit Log
01 Forms (11/07/23) Supplemental Application Shoreline CUP
02 Site Plan and Stormwater (06/25/24)
03 Case Documents (06/26/24)
04 Application Form (06/25/24)
05 Revised Site Plan and Stormwater (08/21/24)
06 Comment Received (10/08/24)
07 Geologist Response (10/11/24)
08 Response to Additional Information (01/30/25)
09 Geologic Assessment for Twana Way (03/13/24)
10 Telegin Law Comments (03/27/25)
11 Permit (Decision appealed) (04/10/25)
12 Staff Report (04/10/24)
13 Notice of Public Hearing (07/03/25)
14 Geotechnical Report (03/27/24)
15 Affidavit of Public Hearing
16 Notice of Public Hearing
17 Affidavit of Posting
Appellant’s Exhibits
A-01 Declaration of Telegin and exhibits thereto
A-02 Miller Report 2008 NW Watershed
A-03 Tarboo Fish Survey NW Watershed
A-04 Twana Way Photographs
A-05 DiMaggio LUPA Petition
A-06 Assignment of Trial or other hearing date
A-07 Notice of Appearance
A-08 Stipulated Order of Dismissal
A-09 RBLD 2024
A-10 Twana Way Emergency Vehicle Access
A-11 Schembs Resume
A-12 Cedzich Resume
A-13 Slope Characteristics Layout
A-14 Slope Characteristics Layout 2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 11 OF 52
A-15 Slope Stability and Landslides Coastal Atlas
A-16 GeoResources Technical memo
A-17 GeoResources Rebuttal Memo
A-18 Appellants’ Revised Witness and Exhibit List
A-19 Road images
A-20 Rathvon emails
A-21 Malick email
A-22 “Please to Phil” email
A-23 Shold Excavation estimate
Jefferson County Exhibits5
CA-01 Appeal Statement
CA-02 Staff Report: Proposed Findings, Conclusions and Recommendations
CA-03 Appellant’s Motion for Summary Judgment
CA-04 Declaration of Bryan Telegin in Support of Appellant’s Motion for
Summary Judgment and exhibits thereto
CA-05 Jefferson County’s Response Brief in Opposition to Appellant’s Motion
for Summary Judgment
CA-06 Declaration of Attorney Ariel Speser in Support of Jefferson County’s
Response Brief in Opposition to Appellant’s Motion for Summary
Judgment and exhibits thereto
CA-07 Applicant’s Response to Appellant’s Motion for Summary Judgment
CA-08 Declaration of Richard Rathvon in Opposition to Appellants’ Motion for
Summary Judgment and exhibits thereto
CA-09 Declaration of Dan McShane, L.E.G. in Opposition to Appellant’s Motion
for Summary Judgment
CA-10 Declaration of Larry Dean Richert in Opposition to Appellants’ Motion
for Summary Judgment
CA-11 Reply in Support of Appellant’s Motion for Summary Judgment
CA-12 Second Declaration of Bryan Telegin and exhibits thereto
CA-13 Notice of Appearance
CA-14 Pre-Hearing Order
CA-15 Final Pre-Hearing Order
CL-17 SDP 2023-00020 Notice of Application
CL-18 197 001 19 Easement
CL-19 Statutory Warranty Deed April 27, 1971
CL-20 Dabob View Tracts Survey 278886
CL-21 Easement 278885
CL-22 357791 192 Deed
CL-23 544674 2009 Deed
5 DCD submitted Exhibits 01 through 17, including the Staff Report issued April 10, 2025, and
“County Legal” documents CL 17 through 26.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 12 OF 52
CL-24 585230 2014 Deed
CL-25 587436 2014 Deed Corrected
CL-26 Email from McHugh 02/17/25 with attached email from Malick 02/12/25
CL-27 Jefferson County Pre-Hearing Brief
Applicant Exhibits
RR-11 PRE2022-00031 Written Narrative
RR-12 PRE2022-00031 EPH Comments
RR-13 Aesthetics
RR-14 Malick Resume
RR-15 Regan McClellan CV
RR-16 Twana Way Road Improvements
RR-17 Considerations for possible Twana Way Road Repair and Maintenance
RR-18 Twana Way Road Repair and Improvements
RR-19 Twana Way
RR-20 Road improvement
RR-21 Introduction
RR-22 Introduction (4)
RR-23 Beach access notes Twana Rd, Quilcene
RR-24 Twana Road beach access
RR-25 Twana Road beach access
RR-26 Twana Road beach access
RR-27 Dabob property offer follow up (redacted)
RR-28 SDP2023-00020 Notice of Application
RR-29 08/14/25 Rathvon Residence Design Analysis w/Exs. A and B
RR-30 Malick Declaration
RR-31 Jefferson Twana Rathvon Road Gradients 08/15/25
RR-32 Rathvon’s Avalon on Twana Way
RR-33 Oliver easement hose
RR-34 Oliver easement
RR-35 Oliver easement rocks
RR-36 Sign dogs
RR-37 Sign grade
RR-38 Von Bargen materials truck August 2025
RR-39 LRFDBDS-10 Table of Contents
RR-40 AASHTO LRFD Bridge Design Specifications – 9th Edition
RR-41 WSDOT Geotech
RR-42 Jefferson Twana Way Geology Map
RR-43 Rathvon Rebuttal Exhibit List
RR-44 Prehearing Brief
RR-45 Construction vehicles accessing Hawley Property (photos)
RR-46 USDA Soil Map Unit Description
RR-47 Map of Quilcene 7.5-Minute Quadrangle, Jefferson County, WA
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 13 OF 52
Also included in the record:
Final Rathvon Order on Summary Judgment Motion
Hearing Examiner Site Visit Memorandum (08/26/25)
Notices of Appearance and Association of Counsel for Applicant
Rathvon Parties of Record (chart)
Notice of Appearance for Jefferson County (07/11/25)
Witness and Exhibit List for Appellant (07/11/25)
Jefferson County Exhibit List (07/11/25)
Jefferson County Witness List (07/11/25)
Exhibit and Witness List Applicant (07/11/25)
Appellant’s Closing Brief (10/20/25)
Jefferson County Closing Brief (10/20/25)
Applicant Post-Hearing Brief (10/20/25)
To view the case file, including application and staff report, go to www.coJefFerson.wa.us —
Services — Laserfiche web portal (username and password is: public) — Board of
Commissioners — Boards and Committees — Hearing Examiner — 2025 — 071725 Rathvon
21. This Decision is the final decision of Jefferson County on the Application and the
Appeal. RoP 6.7. Any party may request reconsideration or clarification of the Decision in
accordance with provisions in the RoP and JCC 2.30.130.
22. This Decision shall be forwarded to the Washington State Department of Ecology
for final action on the Application in accordance with WAC 173-27-130. The Department of
Ecology’s decision will be appealable to the state Shoreline Hearings Board.
II. FINDINGS OF FACT ON MERITS OF APPEAL
After reviewing the record and hearing testimony, the Hearing Examiner makes the
following Findings of Fact:
A. Characteristics of Applicant’s Property and Surrounding Properties
1. Applicant’s Property is within the Natural shoreline designation. The Applicant’s
proposed single-family residence is a conditionally allowed use in the Natural shoreline
environment, requiring issuance of an shoreline conditional use permit. JCC 18.25.500(3)(c).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 14 OF 52
2. Access to the Property is solely via Twana Way, a narrow, unpaved private road,
portions of which are steep and within a mapped landslide hazard area. Ex. 06, p.9; JCC
18.22.510(1)(b). There is only one property on Twana Way beyond the subject Property; Twana
Way dead ends at that location just south of the Property, which is the last developed parcel along
Twana Way.
3. The Applicant’s Property is private land. There are no easements or other
agreements that give the public legal access to the shoreline on the Applicant’s property. Exs. C-
18; C-19; and C-21. The Applicant’s proposed home will be minimally visible from Dabob Bay
4. The subject Property is approximately 5.47 acres in size and is in an area that is
heavily vegetated and forested. Ex. 03. Two parcels adjacent to the subject Property are currently
used as single-family residences.
B. Dabob Bay
5. Dabob Bay is a waterbody known to provide ecologically significant habitat for
Hood Canal summer chum salmon and Puget Sound Chinook, both of which are listed as
threatened under the federal Endangered Species Act. Ex. 06, p. 8. Eelgrass beds, an endangered
plant species, are also common in the offshore areas of Dabob Bay and may occur offshore of
the Rathvon property. Ex. A-03, p. 1; see also Hearing Day 4 at 01:10:212 (Jill Cooper testimony).
6. According to a report entitled “Landslide Hazard and Erosion Susceptibility
Assessment, Tarboo-Dabob Bay, WA” prepared by M2 Environmental Services for Northwest
Watershed Institute by Daniel Miller, dated January 21, 2008,6 “[t]he physical and biologic
6 The purpose of the slope stability study was to aid decision-makers in considering expansion
of existing Natural Area Preserves and creation of new Natural Resource Conservation Areas.
Ex. A-02, p. 1. The report cautions that, “[f]or mapping over this extent (e.g., thousands of acres),
we must rely primarily on information from remotely sensed data and existing maps, i.e., aerial
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 15 OF 52
environment of the bay is finely attuned to the frequency and magnitude [of landslides and
erosion, triggered by high intensity storms during which sediment is delivered to stream channels
that carry the sediment to the bay in accompanying high stream flows]; therefore an important
aspect of assessing risks to the bay is consideration of human activities that alter the frequency
and magnitude of sediment delivery.” Ex. A-02, p. 1.
7. The report states that, “[m]ud and silt are an integral part of floodplain and
estuarine environments, and the organisms that use these environments are well adapted to the
inputs of mud and silt that have been carried by flood flows to the bay throughout the ten thousand
years since the last ice sheet retreated. They are not well adapted, however, to deal with changes
in the frequency and rate at which mud, silt, and associated organic materials are carried to the
bay, with the consequence that actions in the watershed that affect erosional processes alter both
the physical environment and associated ecosystem of the bay.” Id. at 4. “Activities that increase
rates of sediment production and transport within the watershed will increase rates of sediment
delivery to the bay,” with streams predominately carry[ing] fine- grained sediment.” Id. at 22.
8. The Hearing Examiner finds this report (Ex. A-02) to be of limited relevance to
the Appeal for the following reasons: (1) the report was prepared based on high-level (covering
thousands of acres) mapping and does not include any recommendations regarding use of and/or
improvements to roads within the watershed, including Twana Way; (2) while the report states
that “road building” may increase sediment delivery downstream, the report does not include any
photography, and topographic and geologic maps. Two basic approaches have been developed
for slope-stability mapping at this scale: terrain mapping, which seeks to identify potentially
unstable landforms, and computerized analyses using Geographic Information Systems (GIS),
which seek correlations between landslide locations and topographic, geologic, vegetation, and
other attributes for which data may be available.” Ex. A-02, p. 5.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 16 OF 52
relevant conclusions concerning use of existing roads in the watershed7; and (3) the Applicant is
not proposing to construct a new road or to make any improvements to Twana Way.
C. Characteristics of Twana Way
9. No party disputes the fact that Twana Way is more than 200 feet from the
shoreline of Dabob Bay. The majority of Twana Way runs through a mapped moderate landslide
hazard area (a critical area) per JCC 18.22.510(1). Some of these areas exhibit the environmental
attributes defined in JCC 18.22.510(1)(b)(ix) (slopes of 40% or steeper and with a vertical relief
of 10 or more feet); see Exs. A-13; A-14.8 Twana Way winds through a series of steep hillsides
and ravines and is described as a “primitive road,” possibly used previously as a logging road.
The road itself is narrow and steep along several stretches; locals have referred to Twana Way as
the “Goat Trail.” Ex. 06, p. 9; Hearing Day 1 at 4:48:29 (DiMaggio testimony); see also Ex. A-
04 (photographs taken by Mr. DiMaggio); Ex. A-01, p. 8 (Attachment at 3) (Applicant stating
that “[much of the road surface is about ~8’ to 9’ wide … but there are several spots that are more
narrow (~7 to 7-1/2’).
7 The report finds that soils in the area are generally permeable, except for discharge from
impermeable surfaces (roads) and further states that surface runoff is rare, concluding that, “as
long as there is vegetative cover, there is little potential for surface erosion.” Id. p. 7.
8 Testimony was focused in great detail as to whether Twana Way is within an area that includes
environmental attributes of a “landslide hazard area” per JCC 18.22.510(1)(b)(ii) and/or
18.22.510(1)(b)(ix). The Applicant and County asserted that the maps are a screening tool only
and that slopes must be examined and affirmatively demonstrated to be unstable or prone to
sliding. E.g. Hearing Day 1 at 2:13:01-2:30:08; Hearing Day 3 at 1:01:17. Appellants disagreed
with this interpretation. As addressed in the Conclusions of Law below, even after giving
deference to the County’s interpretation of its own code, the Examiner determines that
Appellants’ interpretation is legally correct. However, the Examiner determines that the
Applicant is not proposing any “land disturbing activity, development or activity on land” that is
subject to review under the County’s critical areas code.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 17 OF 52
10. Twana Way is a pre-existing, narrow dirt and gravel road that provides access to
the Property. As far back as 1969, an easement recorded under document number 203763 refers
to “following the general course of an existing road” and states the road easement is permanent
and perpetual. Ex. CL-18. This road existed before the Rathvon family purchased their property.
Ex. A-01 at Ex. I; Ex. 8 at 7-15; Ex. CL-18; Ex. CL-19. There is no dispute regarding Applicant’s
right to use the road for access to the Property. The original easement referenced in the various
deeds to the Applicant’s Property provides access via a 30-foot easement along Twana Way, as
well as an obligation to share in the road’s maintenance. Ex. CL-18; see also Exs. CL-19 and CL-
22-25.
11. The watershed that encompasses Twana Way has been mapped by the Northwest
Watershed Institute (“NWI”) as susceptible to surface erosion. Ex. A-02, p. 34 (Figure 10).
12. Three streams cross Twana Way and then discharge to Dabob Bay further
downhill. Two of those streams have been mapped by the County as depicted at page 114 of Ex.
A-01. See also Ex. A-01, p. 5 (Attachment at 1; copy of Jefferson County critical areas map sent
by Greg Ballard); Hearing Day 1 at 05:12:22 (testimony by John DiMaggio that he is personally
familiar with streams mapped by the County). A third type Ns stream runs just south of the
Applicant’s Property and under Twana Way in a culvert. Ex. 03, p. 54. Twana Way is outside the
stream and stream buffer.
13. Twana Way has been consistently used and maintained for ingress and egress to
the properties along the road for decades. No evidence of landslides above or below Twana Way
was introduced. Both the Applicant and Appellants have been accessing their properties and
using the pre-existing road without issue. Appellants installed landscaping and rocks on and near
that portion of Twana Way that crosses his property. The purpose of the rocks is to demarcate
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 18 OF 52
the edge of the road to prevent vehicles from inadvertently exiting the road into a ravine. An
unnamed/unknown property owner has installed and/or maintained “water bars” across Twana
Way in a number of locations, presumably for the purpose of moving stormwater across the road
to the downhill slope and ravines. Testimony Day 2 at 5:29:34 and 5:50:35.
14. Applicant introduced evidence during the hearing that several neighbors have
undergone some level of construction using Twana Way “as is” for construction vehicle access
(Ex. RR-38 and RR-45). Appellants introduced photographs showing the current condition of
Twana Way and its “shoulder” following recent use by the Von Bargen and Hawley construction
vehicles. Ex. A-18, pp. 2, 5, 14, 15, 18, 19 and 24. These images show tire tracks outside the
gravel road surface, dirt banks on the uphill side of the road having been ground down, and
dislodged chunks of earthen material from the uphill slope. Id. They also show crushed vegetation
on the downhill side of the road. Id. Appellants asserted that Twana Way “[h]as been widened
because of that traffic,” and that the road “absolutely” needed to be widened to accommodate the
trucks. Testimony Day 4 at 3:13:05 and 3:39:20.
15. Appellants assert that construction vehicles are causing sections of the road to be
covered in fine dust which they believe may wash downhill during rain events. Ex. A-18, pp. 1,
2, 3, 8, 10, 23; Testimony Day 4 at 2:55:53 and 3:15:42. Appellants argue, but did not present
any evidence to support their assertion, that dust and sediment will ultimately make its way
downhill to Dabob Bay, harming the sensitive aquatic environment. Ex. 06, p. 18. Appellants
also argue that the recent alteration to some “water bars” across Twana Way by other construction
vehicles may exacerbate the risk of erosion and sediment transport to Dabob Bay. Appellants did
not present any competent evidence to support this argument.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 19 OF 52
16. Appellants assert that use of Twana Way by construction vehicles meets the
definition of a “land disturbing activity” under JCC 18.10.120 and, thus, that regardless of
whether road improvements are proposed by the Applicant, mere use of Twana Way by the
Applicant’s construction vehicles is subject to review under the County’s critical areas code.
Appellants’ previous expert, David Parks of Crescent Environmental, opined that DCD erred by
failing to require the Applicant to assess Twana Way to determine if it can bear the heavy loads
anticipated during truck use without failing and delivering sediment to downstream waters. Ex.
06, p. 18; Hearing Day 2 at 1:43:41 (Mr. Cedzich agreeing with Mr. Parks’ assessment).9 In the
conclusions of law below, the Hearing Examiner concludes that mere use of the road, even by
heavy vehicles, is not subject to critical areas review.
17. Appellants argue that damage to Twana Way has already been caused by other
construction vehicles for other projects (unrelated to the Applicant or the subject Property), and
that such damage threatens to interfere with pedestrian use of Twana Way to reach the waters of
Dabob Bay for recreational purposes. They state that the dust and rock covering Twana Way has
made it more difficult to walk on the road. See, e.g., Hearing Day 3 at 2:05:56; see also Hearing
Day 3 at 1:47:00, 3:27:54 and 5:19:29. Therefore, Appellants assert that when the Applicant
undertakes his construction project, problems related to pedestrian use of Twana Way will only
increase. The Hearing Examiner finds that this speculation is not competent evidence.
9 Appellants did not provide their own geologic hazard assessment of the slope stability of Twana
Way. On the other hand, Applicant’s experts opined, based on their in person inspections and
analysis of the road and slopes, that neither the home site nor Twana Way pose landslide risks.
Appellants’ expert witness Mr. Cedzich based his conclusions on mapping only. Exs. A-16 and
A-17.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 20 OF 52
18. To address Appellants’ concerns regarding impacts to Twana Way by Applicant’s
neighbors’ construction, which arose with specificity for the first time during the appeal hearing,
a new condition of approval to which the Applicant agreed is included with this Decision,
requiring the Applicant to restore Twana Way to its pre-construction condition following
completion of the Applicant’s single-family home construction. Testimony Day 4 at 00:19:46;
see also Ex. RR-2 and Ex. 08, p. 58. The burden is on the Applicant to demonstrate compliance
with this condition of approval. Testimony Day 4 at 00:20:44. Per JCC 18.25.720, “[w]hen permit
or permit exemption approval is based on conditions, such conditions shall be satisfied prior to
occupancy or use of a structure or prior to commencement of a nonstructural activity.”
D. Single-Family Home Application
19. The Applicant proposes construction of a single-family home and garage, to be
situated approximately 160 feet from the ordinary high water mark (OHWM), outside of the 150-
foot shoreline buffer, with a 10-foot building setback. Ex. 12, p. 3. The home will be situated
within the existing mature forest, resulting in a barely visible footprint. Ex. 01.
20. The Applicant’s Property is the last piece of land that has not yet been developed
into a single-family residence or set aside for conservation. Adjacent properties contain single-
family homes, and the Applicant’s home has been designed to fit in with its surroundings. Exs.
RR-3; RR-29. The Applicant’s architect designed the home to reduce disturbance to the site by
nestl[ing the home] in the slope of the site using the topography to enter the home on the upper
level and reduce the home’ s apparent size from the road.” Ex. RR-29, p. 2.
21. The home has been designed so that a minimum of the home is exposed on both
the landward and waterward side of the home. Ex. RR-29, p. 2. The home will be placed at the
maximum shoreline setback, and the Applicant has not requested any exceptions from the
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 21 OF 52
shoreline setback requirements. Id. In retaining as many existing trees as possible on the property,
using dark colors for the home’ s exterior, and employing a roof with a low slope, the architect
has designed a home that will blend into the forested surroundings. Id
22. The submitted site plan depicts all components of the Applicant’s proposal and
the affected site. Ex. 05. Stormwater will be naturally dispersed into the native forest, with no
change or increased impact. Id. Stormwater resulting from impervious surfaces will disperse
naturally. Id.
23. The Staff Report analyzed how the project will “avoid impacts to the shoreline
environment to the extent possible” and concludes that “no adverse impacts to the shoreline are
expected,” provided the Applicant follow best management practices for erosion control. Ex. 12
pp. 6-7. Conditions of approval are included in the SCUP Decision to ensure no sediment or
pollutants will reach Dabob Bay. Ex. 11, p. 8.
24. Because the Applicant’s proposal is to construct a private, single-family residence
on his private Property, there will not be a substantial detriment to the public interest. Ex. 11, p.
1; Ex. 12, p. 7.
E. Did the Applicant Propose Improvements to Twana Way?
25. Significant testimony was provided and exhibits were referenced regarding the
question of whether Applicant proposed to alter or make improvements to Twana Way for the
purpose of facilitating construction of a single-family home on the Property. E.g. Ex. A-01
(Exhibits E, J, K, M, N and P), and Exs. 7-8.
26. One of the primary bases for Appellants’ objections to the DCD Decision, and for
their belief that road improvements were proposed and not analyzed by the County, is found in a
document Mr. Rathvon created in October 2023 to facilitate a neighborhood discussion about a
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 22 OF 52
possible formal road maintenance program for Twana Way. Ex. RR-16 (illustrative examples of
a “possible range of possible road repairs and improvements”); Ex. RR-17 (invitation to “a
neighborhood gathering to discuss possible repair and maintenance of our road”). Appellants
assert that the Applicant’s home construction project includes extensive road improvements to
Twana Way based on the “Higher Cost Option” that Mr. Rathvon presented at the October 2023
neighborhood meeting. Hearing Day 1 at 4:50-4:53, Hearing Day 3 at 1:45-1:46, 2:00
(DiMaggio); Hearing Day 3 at 4:58-5:02, 5:20-5:21 (Oliver); Ex. RR-16 at 5, 9-11; Ex. RR-17.
27. Appellants submitted a comment letter on the Application, which letter included
a figure of the Higher Cost Option from Mr. Rathvon’s October 2023 presentation. Ex. 6, p. 9.
Appellants alleged that Mr. Rathvon intended to significantly improve[]” Twana Way and
commented that “[i]f this is still the applicant’s plan, then that should be included and evaluated
as part of the project application, which may in turn trigger SEPA review.” Id., p. 10.
28. Appellants object to the Higher Cost Option because they are concerned that if it
was implemented, new rock and gravel on Twana Way would make the road unwalkable. Hearing
Day 1 at 4:57 (“we’re concerned that [Mr. Rathvon] will start a process [that]’s going to
jeopardize our personal use of the road and our personal ability to get to the shoreline), Hearing
Day 3 at 2:49-2:50 (DiMaggio); Hearing Day 3 at 5:08-5:09; 5:27-5:30 (“[I]f, in fact, that rock
was laid down, it's not walkable anymore.”) (Oliver). This walkability objection dates back to
October 2023. See Ex. A-20, p. 5.
29. Appellants believe that the Applicant only put forward the neighborhood road
maintenance proposal to further construction of their single-family home. Hearing Day 3 at 5:09
(Oliver); Hearing Day 3 at 1:57-1:58, 2:50-2:51 (DiMaggio). Appellants criticize what they
perceive to be untruthful statements and the Applicant’s lack of being forthright as to the purpose
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 23 OF 52
of bringing neighbors together to discuss improvements to Twana Way – his intent to develop
the Property with a single-family home and desire to improve access for construction vehicles.
30. The neighbors did not agree on a neighborhood road maintenance proposal and
the proposal never went forward. Ms. Oliver admitted that the road proposal went “nowhere.”
Hearing Day 3 at 5:15, 5:25 (Oliver testimony); see also Hearing Day 4 at 1:28 (VonBargen
testimony).
31. None of the permit applications or documents submitted by the Applicant
described any specific work on Twana Way and the Applicant did not file a permit application
for any road work on Twana Way. Ex. 3, pp. 9-16, 55-63, 67-70; Ex. 4. Applicant confirmed to
that they “are not proposing to alter or expand the road, including cut and fill activities or removal
of trees.” Ex. 8, p. 3. Applicant did not submit any document that indicated the location(s) of any
future road improvements or the manner in which such improvements would be made. Applicant
stated that he and his experts “have not determined that there is a need to alter Twana Way.”
32. DCD Planner Donna Frostholm testified that the County never received any
formal application from the Applicant for road improvements on Twana Way. Hearing Day 1 at
1:35. Ms. Frostholm stated that it was “very clear to [her], [that Mr. Rathvon was] expecting to
maintain [Twana Way] in its current condition.” Hearing Day 1 at 1:02. Appellant John
DiMaggio also testified that they are “not aware of any formal proposal at the County” for the
Applicant to improve Twana Way. Hearing Day 3 at 2:00.
33. When questioned on this matter, Mr. Rathvon repeated his prior written statement
to the County that he has no intention of making road improvements to Twana Way. Hearing
Day 4 at 3:13-3:14, 4:50- 4:53; Ex. 08, p. 3 (“We are not proposing to alter or expand the road,
including “cut and fill” activities or the removal of trees”). Mr. Rathvon testified that he did not
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 24 OF 52
include improvements to Twana Way in any of his permit applications and that he was not and
is not contemplating road improvements on Twana Way. Hearing Day 4 at 3:13-3:14, 4:50-4:53.
34. Appellants believe the Applicant is not being truthful about his intent to construct
road improvements to Twana Way based in part on the Applicant’s submission of a February 25,
2025 Stratum Group report entitled, “Geologic Hazard Assessment for Twana Way
Improvements” Ex. 9.
35. Jefferson County Code Administrator Greg Ballard testified about his personal
involvement in this matter. In large part, it involved consulting with Applicant’s team regarding
a possible critical area exemption, which was separate from the SCUP application. Code
Administrator Ballard testified that, in an abundance of caution, he had asked for additional
information regarding slope stability for this limited purpose (Hearing Day 1 at 4:03:10), hence
receiving the Stratum Letter dated February 25, 2025. Ex. 9; see also Hearing Day 1 at
04:06:48.000.
36. To the extent the Stratum Group Letter dated February 25, 2025 created confusion
regarding any possible “road widening,” this assertion was refuted by the author’ s own testimony.
Geoff Malick testified he had misunderstood what was actually being proposed – he assumed
road modifications. Regardless, he personally observed the road and testified that he has no
concerns for its overall stability in its current condition.
37. Based on the weight of the evidence, the Hearing Examiner finds that the February
25, 2025 Stratum Group report does not constitute a proposal by the Applicant to widen and/or
re-grade Twana Way. This report was submitted to DCD in response to the County’s request for
a “brief statement [from the Applicant’s geotechnical engineer] regarding the stability of the
Twana Way roadway.” Ex. RR-30.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 25 OF 52
38. In what appears to have been a “telephone game” series of conversations, real
estate agent and consultant Terry McHugh passed along the County’s request to the Applicant’s
principal geologist, Dan McShane at the Stratum Group, who then tasked Geoff Malick with
conducting the review because Mr. Malick was within the area and could investigate in person.
Hearing Day 2 at 5:19-5:20; Hearing Day 3 at 00:17-00:18. Mr. Malick testified that his sole
understanding of the Applicant’s project was Mr. McHugh’s email (Ex. RR-30 at 6), and a brief
conversation with Mr. McShane. Hearing Day 3 at 3:57-4:01, 4:08-4:09, 4:13. Mr. Malick never
had a conversation with Mr. Rathvon before writing his report, and had no direct knowledge of
the Applicant’s proposed residential construction project. Id.
39. In his geologic hazard assessment for Twana Way, Mr. Malick wrote: “It is our
understanding that you are proposing to improve Twana Way to allow construction vehicle
access to your property at 660 Twana Way.” Ex. 09 at 2. In his declaration (Ex. RR-30), and in
his hearing testimony (Hearing Day 4 at 4:17, 4:21), Mr. Malik explained that he did not conduct
any analysis of construction vehicle sizes or turning radii and that his assumption regarding
potential road-widening was made in an effort to be over-inclusive in his geotechnical analysis.
He stated that he has “no reason to believe that road improvements would be required for
construction access to the Applicant’s property.” Ex. RR-30, ¶8.
40. The weight of the evidence demonstrates that, while the Applicant and/or their
agents and consultants explored the possibility of proposing road improvements to Twana Way,
and Terry McHugh requested that a note be added to the building permit to generally allow road
improvements (Ex. A-22), no specific proposal for the County’s review, including location of
road improvements or how such road improvements would be constructed, ever was submitted.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 26 OF 52
41. The weight of the evidence supports a determination that the Applicant’s
construction of their single-family residence is neither dependent on, nor intertwined with, any
improvements on Twana Way.
42. If the Applicant had, in fact, proposed road work on Twana Way, and such work
was required for access to the Property as an integrated and non-severable element of the
proposed single-family development and a necessary part of the plan to construct a residence or
for the proposed home to function, DCD would have been required to review such work as part
of its review of the SCUP Application. As addressed in more detail in the findings and
conclusions below, the Applicant did not propose road work on Twana Way and the DCD
Decision specifically does not authorize any road work on Twana Way. Ex. 11.
F. Will Use of Twana Way As-Is Impact the Shoreline?
43. Appellants’ geotechnical experts opined on their preferred means of geotechnical
analysis for new road improvements that were not proposed. Ex. 6 at 16; Exs. A-16 and A-17. Mr.
Cedzich presented testimony concerning potential impacts of road improvements to Twana Way.
Ex. A-16 (purpose of memorandum is to present our professional review and findings “for the
proposed roadway improvements along Twana Way”). Mr. Cedzich not performed a geologic
hazard assessment in Jefferson County (Testimony Day 2 at 2:10), he made no independent
evaluation of Twana Way’s geotechnical stability (Testimony Day 2 at 2:27-2:30), and he did
not visit the site (Testimony Day 2 at 2:27-2:30).
44. Mr. Cedzich presented opinion testimony on the studies he believed should be
conducted prior to approval of road improvement construction (Testimony Day 4 at 5:14-5:16).
Neither Mr. Cedzich nor Crescent Environmental opined that road improvements were required
for the Applicant to construct a single-family home on the Property.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 27 OF 52
45. Geologist Dan McShane, who has personal knowledge and experience working
in Jefferson County, testified that he does not have any concerns about the road stability.
46. The weight of the evidence shows that Twana Way is geotechnically stable and
may be used safely, in its current condition, for construction access to the Applicant’s Property.
Hearing Day 4 at 00:24:07 (Frostholm). If necessary, minor maintenance to Twana Way will be
governed by the County’s critical areas regulations and may fall within an exemption under JCC
18.22.230(4)(c)).
47. Mr. Rathvon testified that he is willing to incur higher construction costs to ensure
that no work on Twana Way is necessary for his project. Hearing Day 4 at 4:53.
48. To refute Appellants’ argument that road improvements are, in fact, required to
access the Property for construction vehicles, Mr. Richert and Mr. Miller testified that there are
a variety of construction means and methods that can be used to minimize impacts on the road,
such that road modifications or improvements are not necessary. Mr. Richert testified that while
“Twana Way has its challenges,” many types of construction vehicles “are well within the realm
of being able to get up and down that road.” Hearing Day 4 at 1:56- 2:03. Mr. Miller testified
that he has driven Twana Way himself and that he can “get various vehicles down there [Twana
Way] in its current condition.” Hearing Day 4 at 2:21. Mr. Miller testified he could use a smaller
cement mixer to deliver concrete to the Applicant’s property. Hearing Day 4 at 2:23. Concrete
could also be pumped to the construction site or even mixed on site. Id. Mr. Miller explained that
dump trucks ranged in capacity from 2 yards to 12 yards and that an appropriate size would be
selected to safely perform the work. Hearing Day 4 at 2:23-2:24.
49. No compelling evidence supports a determination that the Applicant needs to
modify Twana Way to build their home or that the Applicant’ s project will inevitably require
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 28 OF 52
improvements to Twana Way. The Applicant can complete construction of the home without
necessitating road improvements. The evidence does not support a determination that DCD erred
by improperly deferring review of a necessary element of the proposed construction project.
50. No persuasive evidence was presented that use of Twana Way by construction
vehicles has caused, or will cause slope stability issues. No evidence was presented that
Applicant’s construction-related vehicles will be unable to navigate Twana Way in its current
condition to access the Property. In fact, the weight of the evidence shows that construction
vehicles have successfully used Twana Way to build and expand at least eight homes, as recently
as September 2025. Exs. RR- 31, RR- 38, and RR-43 (photographs of construction vehicles on
Twana Way); Hearing Day 4 at 1:18-1:23 (VonBargen), 2:20-2:24 (Miller), 2:00-2:03 (Richert);
see also Exs. CA-08; RR- 38; RR-45. No persuasive evidence was offered that improvements to
Twana Way are necessary for the Applicant to build their single-family home or that construction
traffic will undermine the road’s stability.
51. Appellants did not present compelling evidence to show that impacts to the
shoreline environment will result from the Project, or that road improvements are necessary to
construct the Applicant’s single-family home. The County properly excluded Twana Way from
its Decision because the Applicant did not propose any improvements to Twana Way and no road
improvements are necessary to build the Applicant’s home.
52. Applicant’s witnesses, Mr. Malick and Mr. McShane, testified that Twana Way
was not at risk of landslide, was geologically stable, and could be used for construction access.
Hearing Day 2 at 5:00-5:01, 5:26-5:28, 5:51 (McShane); Hearing Day 3 at 4:17-4:19 (Malick);
see also Exs. 9, RR-30. Based on his personal evaluation of Twana Way, Mr. McShane confirmed
that Twana Way is wide at the culvert near the Applicant’s property, and there is no evidence of
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 29 OF 52
runoff or sediment transport to the shoreline environment or Dabob Bay. Hearing Day 2 at 5:08-
5:11.
53. DCD determined that Appellants’ allegations regarding potential discharge of
material into stream(s), which may then flow into Dabob Bay, were speculative and not relevant
because the Applicant did not submit a proposal to alter Twana Way. DCD properly evaluated
potential impacts of the Applicant’s use of Twana Way (if not improved or otherwise modified)
for construction equipment access. Potential impacts of use of Twana Way, expressed by
Appellants, are hypothetical and speculative.
54. Substantial evidence supports DCD’s determination that the Rathvon single-
family residence SCUP will have no significant impacts on the shoreline environment.
55. As addressed in more detail in the findings and conclusions below, the Applicant’s
mere use of Twana Way for construction-related traffic does not constitute a “land disturbing
activity” under JCC 18.10.130. DCD did not err in failing to require additional studies and
documentation from the Applicant and was not required to perform critical area review of mere
use of a road that has existed and been used for decades without incident, including for the
construction of all other existing homes in the area. DCD properly interpreted and applied its
SMP and critical areas code and did not err in not requiring the Applicant to submit an analysis
of whether Twana Way “can bear the heavy loads anticipated during truck use without failing.”
G. DCD’s Review of the Application
56. DCD reviewed the Application and required additional submittals and
information over a nearly three-year period before issuing the SCUP Decision. Ex. 3 at 9-16, 55-
63, 67-70; Ex. 4. The County put the Application out for public comment, reviewed those
comments, and acted upon them by requesting additional information from the Applicant. Id.;
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 30 OF 52
Exs. 6 and 8. DCD’s review involved an iterative process, requiring the submission and
consideration of multiple technical reports, through which the County ensured it had sufficient
information to confirm the Application met all required criteria.
57. DCD required, and the Applicant submitted, complete responses to SCUP
application questions. The Applicant provided the County with numerous technical analyses
from qualified experts in their field, such as analyses of the septic system, multiple geotechnical
reports, stormwater analyses, a stream report, and a cumulative impacts report. Ex. 3 at 9-16, 55-
63, 67-70; Ex. 8; Ex. 12 at 1. Some of these analyses were prepared at the request of the County
in response to public comments on the Application.
58. During its review of the Application, DCD requested and obtained additional
information from the Applicant on multiple occasions. DCD requested even more information
from the Applicant in November 2024 regarding road improvements, construction staging,
additional geotechnical analyses, and cumulative impacts in response to comments made by
Appellants. Ex. A-01 at Ex. D. Planner Donna Frostholm met and corresponded via email with
Mr. Rathvon to obtain clarification as to the scope of the proposal and whether it included
improvements to Twana Way. Ex. A-01 (Ex. D). DCD staff considered Appellants’ comments,
requested additional geotechnical information on the stability of Twana Way (Ex. A-01 at Ex. D,
at 1), which was provided (Ex. 9), and concluded that Twana Way could be used in its current
condition for construction of the proposed home (Ex. A-01 at Ex. I, at 1).10 DCD staff also
conducted a site visit on January 17, 2025 to examine Twana Way itself. Ex. A-01 at Ex. I.
10 The County presented testimony to clarify why additional information was requested for both
the shoreline permit regarding the residence, and, separately, for a critical areas code consultation
on road maintenance.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 31 OF 52
59. The classification of The Stratum Group reports was debated at the hearing.
Appellants questioned whether those reports were considered geotechnical reports under JCC
18.22.540. DCD considered the reports provided by Stratum (Geological Hazard Assessment for
Proposed Septic System dated February 15, 2022 (Ex. 14), Comments in response to public
comments from Telegin Law and Crescent Environmental dated October 11, 2024 (Ex. 7),
Geological Hazard Assessment Update dated November 14, 2024 (Ex. 8, Attachment E), and
Geological Hazard Assessment for Twana Way Improvements dated February 25, 2025 (Ex. 9))
to be sufficient to support the findings in the Staff Report (Ex. 12). Ms. Frostholm testified that
she did not request a geotechnical report because the Applicant is proposing a single-family home,
not a road improvement project. Hearing Day 1 at 1:41-1:43.
60. Substantial evidence supports the determination that DCD completed its due
diligence in reviewing the professional reports provided to satisfy the SCUP review. Planner
Frostholm testified that having reviewed the updated report prepared by The Stratum Group (Ex.
8, Attachment E), DCD relied on JCC 18.22.540(5) to determine the updated report should be
accepted. Geologist Dan McShane and partner Geoff Malick both personally visited the property,
assessed slope stability, and walked Twana Way. In contrast, Mr. Cedzich had not visited the site
location, has less experience working in Jefferson County, and does not have the local expertise
or familiarity with the local geological landscape. Most of Mr. Cedzich’s experience is in Canada
or the southern United States. Hearing Day 2 at 1:14, 3:12-3:15; Ex. A12
61. DCD visited the site to examine Twana Way (Ex. A-01 at Ex. I, asked the
Applicant if they intended to improve Twana Way as part of their project (Ex. 8 at 3), and
requested additional information on the road’s geotechnical stability based on comments received
from Appellants’ consultant, Crescent Environmental (Ex. 8 at 4). That information was provided
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 32 OF 52
to DCD and supplemented at the hearing. (Es. 7 at 13; Ex. 8 at 19; Ex. 9 at 2; Exs. RR-31, RR-
42, RR- 44, and RR- 45; McShane: Hearing Day 2 at 4:14-6:17, Hearing Day 3 at 00:09-1:34;
Malick: Hearing Day 3 at 3:55-4:52.
62. The Stratum Group submitted five geotechnical reports on behalf of the
Applicant—three during the permitting process and two as part of the hearing. Mr. McShane’s
first geologic hazard assessment for the Applicant’s single-family home project was conducted
in February 2022. Ex. 14. As part of this assessment, Mr. McShane reviewed County geological
hazard mapping; shoreline stability maps and historical documents; conducted a field visit; and
conducted a slope stability analysis. This slope stability analysis assessed the shoreline bluff
slope and slopes on the eastern portion of the site, including the two valley slopes above Twana
Way and the ridge in between those valleys. Id. at 9-10. Mr. McShane also assessed the erosional
potential of the slope above the beach on the property. Id. at 11-12. He concluded:
Based on our geologic hazard assessment, it is our opinion that construction of a single-
family house and associated septic system on the lower upland on the subject property
will not be at risk from landslides or erosion within the expected life of the structure as
long as the building and septic systems are located at least 30 feet from the top of the
steep shoreline bluff slope. Furthermore, development within the area [ designated for
homesite construction] will not increase the risk of landslides or erosion on or off the site
as long as the recommendations of this report are followed. Id. at 13.
63. Mr. McShane determined that the “unstable recent slide” indicated on the
shoreline stability map does not appear in any aerial images dating back to 1951 or within the
lidar bare earth imagery. There was an area of bare ground on a slope area to the north visible in
the 1976 aerial photograph, but it appears to be associated with land grading and/or mining
associated with road construction, and Mr. McShane suspects that the designation was mis-
mapped. Id. at 10.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 33 OF 52
64. Appellants did not make any of the Crescent Environmental reports authors
available to testify during the hearing. Mr. Cedzich testified that he did not speak to anyone at
Crescent Environmental when he prepared his report. Hearing Day 2 at 2:27-2:30.
65. Mr. Cedzich first testified that he had no particular project in mind when he
completed his analysis. Hearing Day 2 at 2:19- 2:20. On rebuttal, Mr. Cedzich then testified that
his analysis was based on the Higher Cost Option that Mr. Rathvon had discussed in his October
2023 presentation to neighbors. Hearing Day 4 at 5:14-5:15. Mr. Cedzich analyzed the idea of
future road work that was neither proposed by the Applicant, nor discussed with any specificity.
The basis for Mr. Cedzich’ s opinion is that The Stratum Group’ s report failed to comply with
JCC 18.22.530(4)(b)11 and 18.22.945(2)(d), the WSDOT Geotechnical Design Manual (GDM)
Section 7.2 and 7.6.4, and AASHTO LRFD Bridge Design Specifications Section 11.6. Ex. A16
at 1. The AASHTO standard referenced applies to bridges and retaining walls constructed for
bridges. See Ex. RR- 31.
66. Appellants’ experts did not provide their own geologic hazard assessment of the
slope stability of Twana Way, and did not controvert with evidence (other than mere mapping)
the conclusions of Mr. McShane or Mr. Malick that neither the home site nor Twana Way pose
landslide risks. Appellants’ experts did not complete their own site analysis.
67. DCD weighed three geotechnical reports from The Stratum Group, based on on-
the-ground analysis from geotechnical engineers with experience in Western Washington, and
11 JCC 18.22.530(4)(b) does not exist in the County code, and Mr. Cedzich did not provide the
correct citation. Hearing Day 2 at 3:16-3:20. Section 7.6.4 of the WSDOT GDM also does not
exist. See Ex. RR-30.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 34 OF 52
one report from Crescent Environmental that provided a critique of The Stratum Group’s work.
DCD afforded The Stratum Group’s reports more weight.
68. Planner Frostholm proposed that the Hearing Examiner add a new condition to
the SCUP Decision to address the road issue: requiring the applicant to restore the road to its
existing condition post-construction. Hearing Day 4, 00:11-00:12. The Applicant agreed to this
proposed condition. Hearing Day 4 at 32-33. Mr. DiMaggio testified whether this condition
would address his concerns. Hearing Day 4 at 2:57-2:58. Appellants’ initial public comment
letter on the SCUP application also requested similar mitigation. Ex. 6 at 11.
69. In their closing brief, Appellants requested that the proposed condition be clarified
to require the Applicant to document the complete, unaltered, undamaged condition of the road
(both surface and subsurface) prior to the start of construction so that compliance can be
accurately and meaningfully assessed when he is done. The Hearing Examiner finds that surface
documentation is possible and shall be required via photographic evidence. However, it is unclear
what Appellants are requesting with respect to documentation of subsurface conditions of the
road, particularly given the primitive condition of the road. It is further unclear what subsurface
damage Appellants are requesting to ensure will be repaired. Therefore, documentation of
subsurface conditions is not required.
70. Based on the mitigation proposed in Ms. Cooper’ s Cumulative Impact Analysis,
Planner Frostholm recommended the following also be added as a permit condition to address
concerns about potential construction impacts to the shoreline environment.
General Best Management Practices for Small Construction Sites
• Hand-tools should be used whenever practicable, consistent with standard
building practices.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 35 OF 52
• Marking the critical root zone (CRZ) of trees with paint, flagging, or other to
avoid running equipment and stockpiling materials in CRZ, therefore limiting
soil disturbance and compaction. Additionally, any necessary heavy
equipment and/or truck access should entail a layer of clean woodchips, or
sufficiently wide and thick steel plates in the vehicle wheel path to avoid
rutting and damaging the vegetation.
• Construction should not be conducted during heavy precipitation events,
regardless of the protection of vegetation. If vegetation is damaged, or rutting
occurs, it is recommended that those areas be re-planted with native vegetation.
If planting is necessary, a layer of clean woodchips should also be installed
around plants at a minimum depth of 3 inches.
• Limit the extent of clearing operations and phase construction operations.
• The duff layer, native topsoil, and natural vegetation should be retained in an
undisturbed state to the maximum extent practicable.
Ex. 8 at 58; Hearing Day 4 at 00:12-00:14. The Applicant agreed to this condition, as well.
71. DCD exercised its authority under JCC 18.25.270(3)(b) and required the Applicant
to submit a cumulative impacts analysis that addressed aesthetic impacts and an analysis of the
geologic conditions of Twana Way. Ex.. A-01 at Ex. D; Ex. 9. The Applicant also submitted
renderings of their proposed home. Ex. A-01 at Ex. Q, p. 1; Exs. RR-3; RR-29.
72. Ms. Jill Cooper, from Marine Surveys and Assessments, reviewed the Applicant’s
proposal and conducted a cumulative impacts analysis that was submitted to DCD for review.
Hearing Day 4 at 1:05; Ex. 8 at 59. Ms. Cooper, a senior ecologist with 15 years of experience,
testified that the Applicant’s project will not have negative impacts to sensitive species or critical
habitat areas, if all regulations are followed. Hearing Day 4 at 00:49. She concluded that the
Applicant’s project would not have any significant adverse cumulative impacts.
73. Ms. Cooper testified that the Applicant’s project was similar to all of the
surrounding parcels, which had been developed as single- family homes since the 1970s. Hearing
Day 4 at 00:54-00:55; Ex. 8 at 52 (Fig. 2). The remaining undeveloped properties in the area have
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 36 OF 52
been protected from development by the Washington Department of Natural Resources or
Northwest Watershed Institute. Ex. 8 at 55. Ms. Cooper testified that “ it’s unlikely that there’s
going to be a whole bunch more future development, because there’s not really any space left.”
Id. at 00:56. Ms. Cooper concluded that there would be no significant cumulative impacts on the
shoreline environment because of the low potential for future development in the area and
because the Applicant’s project would not have impacts on sensitive species or critical habitat
areas. Hearing Day 4 at 1:04-1:05
74. Ms. Cooper reviewed the proposed project footprint in relation to relevant buffers
for critical habitat, streams, and shorelines. Hearing Day 4 at 48:00; Ex. RR- 8. Ms. Cooper
concluded that because the project was located outside of the critical habitat, stream, shoreline
buffers, and the project is following the relevant code provisions, there would be no significant
negative impacts to sensitive species or critical habitat areas and there would be no net loss of
ecological functions and values. Hearing Day 4 at 00:48-00:50; Ex. 8 at 59. Ms. Cooper also
testified that Twana Way is too far away from critical habitat, stream, and shoreline buffers to
have significant negative impacts on endangered or listed animal and plant species within Dabob
Bay or their habitats. Hearing Day 4 at 1:09-1:11. Appellants did not provide any evidence to the
contrary to rebut this testimony.
75. DCD’s review was thorough and was completed pursuant to typical permit review
and processes. Substantial evidence in the record supports a determination that DCD satisfied its
permitting obligations by conducting a detailed review of the Application and by requesting,
reviewing and considering additional information where needed in order to complete review.
DCD had ample and sufficient information to make an informed decision on the Application and
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 37 OF 52
to find that the Project, as conditioned, will comply with SMP criteria in JCC 18.25.630(12) and
(16) and the SMA, RCW 90.58.050 and RCW 90.58.140. Ex. 12
76. Approval of the SCUP Decision, as conditioned, will ensure that construction of
the Applicant’s single-family home will not result in adverse shoreline impacts. Conditions 4, 5,
8, and 9 of the SCUP Decision require the Applicant to install a silt fence between 150 and 160
feet from the OHWM to prevent sediment from the uplands construction from entering the bay,
to refrain from construction activities within the 50-foot buffer for the off-site stream, to ensure
that all construction activities are conducted at least 150 or 160 feet from the OHWM, and to
follow the Department of Ecology’s 2019 Stormwater Manual and the stormwater management
best practices identified therein. Ex. 11 at 1-2.
77. DCD analyzed Twana Way’s geotechnical stability and its ability to be used
safely, in its current condition, for construction access to the Applicant’s Property. Testimony
Day 4 at 00:24:07 (Frostholm). Conditions of approval, as amended in this Decision, are
appropriate to mitigate any impacts from use of Twana Way. DCD staff weighed the evidence
before them when they issued the DCD Decision; DCD staff believe the Applicant has been
truthful in his representations and will fulfill his legal obligations. DCD relied on what it
determined to be credible analyses, rather than conjecture, to support its SCUP Decision.
78. Appellants offered no technical studies, scientific evidence, or any evidence that
that contradicts DCD’s findings that the Applicant’s project is consistent with the SMA and SMP.
Appellants believe that DCD did not analyze the Project enough. However, the County
considered the Appellants’ comments and required additional information in response to these
comments, including two more geotechnical analysis and a cumulative impacts analysis. Ex. 3 at
9-16, 55-63, 67-70; Ex. 4; Ex. 8. Appellants’ concerns about geological hazardous areas and use
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 38 OF 52
of construction vehicles on Twana Way are sufficiently addressed in the conditions of approval,
as amended in this Decision.
III. CONCLUSIONS OF LAW
1. The Jefferson County Hearing Examiner has jurisdiction over this Type II land
use appeal. JCC 18.40.330 and JCC 18.40.280(3). The procedures governing Hearing Examiner
hearings are set forth in the Hearing Examiner Code, JCC Chapter 2.30, and the Hearing
Examiner RoP. The Appeal has been reviewed by the Examiner in accordance with applicable
Code and RoP provisions, including but not limited to JCC 18.25.690(2) and JCC 18.40.330.
2. Per JCC 18.25.610(2), the Hearing Examiner is vested with the authority and
responsibility in this Appeal as follows:
(a) Approve, condition, or deny shoreline substantial development permits, variance
permits and conditional use permits after considering the findings and recommendations
of the administrator;
(b) Decide local administrative appeals of the administrator’s actions and interpretations,
as provided in this program and the county Unified Development Code;
(c) Consider shoreline substantial development permit, variance permit and conditional
use permit applications and administrative appeals of the administrator’s actions on
regular meeting days or public hearings;
(d) Review the findings and recommendations for permit applications or appeals of the
administrator’s actions and interpretations;
(e) Approve, approve with conditions, or deny substantial development permits, variance
permits and conditional use permits;
(f) Conduct public hearings on appeals of the administrator’s actions, interpretations and
decisions;
(g) Base all decisions on shoreline permits or administrative appeals on the criteria
established in this master program; and
(h) At his or her sole discretion, require any project proponent granted a shoreline permit
to post a bond or other acceptable security with the county, conditioned to assure that the
project proponent and/or his or her successors adhere to the approved plans and all
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 39 OF 52
conditions attached to the shoreline permit. Such bonds or securities shall have a face
value of at least 150 percent of the estimated development cost including attached
conditions.
3. Appellants have standing to appeal the Decision as a party of record. JCC
18.40.280. Appellants submitted the Appeal in accordance with JCC 18.40.330(2)(b).
4. Public notice of the Appeal was provided in compliance with JCC 18.40.280(4)
and JCC 18.40.230. Members of the public were provided an opportunity to comment on the
Appeal and to participate in the public hearing consistent with state and local requirements.
5. Chapter 18.25 JCC constitutes the County’s Shoreline Master Program (“SMP”),
compliance with which is intended to ensure consistency with the state Shoreline Management
Act, RCW Ch. 90.58 (“SMA”), and Washington Department of Ecology shoreline regulations in
WAC Chapter 173-27.
6. JCC 18.25.590 sets forth conditional use permit criteria for shoreline conditional
use permit applications. It states:
(1) The purpose of a conditional use permit is to allow greater flexibility in administering
the use regulations of this program in a manner consistent with the policies of RCW
90.58.020. In authorizing a conditional use, special conditions may be attached to the
permit by the county or the Department of Ecology to control any undesirable effects of
the proposed use. Final authority for conditional use permit decisions rests with the
Department of Ecology.
(2) Uses specifically classified or set forth in this program as conditional uses and unlisted
uses may be authorized, provided the applicant/proponent can demonstrate all of the
following:
(a) That the proposed use will be consistent with the policies of RCW 90.58.020
and this program.
(b) That the proposed use will not interfere with normal public use of public
shorelines.
(c) That the proposed use of the site and design of the project will be compatible
with other permitted uses within the area.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 40 OF 52
(d) That the proposed use will not cause adverse effects to the shoreline
environment in which it is to be located.
(e) That the public interest suffers no substantial detrimental effect.
(3) In the granting of all conditional use permits, consideration shall be given to the
cumulative environmental impact of additional requests for like actions in the area. For
example, if conditional use permits were granted for other developments in the area where
similar circumstances exist, the sum of the conditional uses and their impacts should also
remain consistent with the policies of RCW 90.58.020 and should not produce a
significant adverse effect to the shoreline ecological functions and processes or other
users.
A. Standard of Review and Burden of Proof
7. Appellants have the burden of proof in this Appeal.12 As to the material factual
issues in this Appeal, the burden of proof is by a preponderance of the evidence. RoP 5.14(j)(iii).
Issues of law are subject to a de novo standard of review. Id.
8. To prevail on an error of law, Appellants must establish that the County’s SCUP
Decision is “an erroneous interpretation of law.” RoP 5.14(j)(iii); Phoenix Dev., Inc. v. City of
Woodinville, 171 Wn.2d 820, 837-38, 256 P.3d 1150 (2011). The County’s interpretation of its
own code is entitled to deference, and should be accorded “great weight where the statute is
within the agency’s special expertise.” E.g. Cornelius v. Wash. Dep’t of Ecology, 182 Wn.2d 574,
585, 344 P.3d 199 (2015). Jefferson County DCD’s legal interpretations of the County’s SMP is
given substantial weight because the interpretations falls within the department’s specialized
expertise. See Ackerson v. King County, SHB No. 95-026 at 8-9, 1996 WL 226594 (Findings of
Fact, Conclusions of Law and Order) (March 19, 1996). In addition, DCD’s administration of
12 While Appellants are correct that the initial burden of proof with respect to DCD’s review of
the Application was on the Applicant (JCC 18.25.670), Appellants carry the burden in this
Appeal to prove the SCUP Decision is not supported by substantial evidence and/or is based on
error of law.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 41 OF 52
the SMA through the SMP, may be afforded deference. Solid Waste Alternative Proponents v.
Okanogan County, 66 Wn. App. 439, 442, 832 P.2d 503 (1992).
9. The “substantial evidence” standard requires that the Examiner view the evidence,
and reasonable inferences therefrom, in the light most favorable to the DCD, as the fact-finding
entity. RoP 1.1(q). The Examiner does not weigh the evidence and substitute her judgment for
that of the administrative official. RoP 1.1(q); Phoenix Dev., Inc. v. City of Woodinville, 171
Wn.2d 820, 832, 256 P.3d 1150 (2011). The substantial evidence standard is met if there is a
“sufficient quantum of evidence in the record to persuade a reasonable person that the declared
premise is true.” Wenatchee Sportsmen Ass'n v. Chelan Cnty., 141 Wn.2d 169, 176, 4 P.3d 123
(2000). RoP 1.1(l) defines “Preponderance of the evidence” as, “after considering all the evidence
on the record and/or at the hearing that the proposition on which that party has the burden of
proof is more probably true than not true.” The Hearing Examiner may consider new evidence
to address the issues raised on Appeal to determine whether there is additional legal and factual
support for the County’s SCUP Decision. RCW 36.70B.020(3).
10. Speculation is not substantial evidence, and conflicting testimony is not sufficient
to warrant reversal. Henderson v. Kittitas County, 124 Wn. App. 747, 100 P.3d 842 ( 2004);
Miller v. City of Sammamish, 9 Wn. App. 2d 861, 881, 447 P.3d 593 (2019) (substantial evidence
supported examiner’s conclusion as to the presence of regulated wetlands despite competing
expert testimony); see also City of Fed. Way v. Town & Country Real Est., LLC, 161 Wn. App.
17, 42-43, 252 P.3d 382 (2011) (hearing examiner conclusion of “absence of data” supported by
substantial evidence). A “technical error” is not sufficient to reverse or remand a decision. Jones
v. Town of Hunts Point, 166 Wn. App. 452, 462-63, 272 P.3d 853 2011).
///
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 42 OF 52
B. Shoreline Management Act and Shoreline Master Program
11. The Shoreline Management Act, RCW 90.58.010, et seq., regulates development
within 200 feet landward of most lakes, rivers and marine waters of the State of Washington. In
general, only those developments within the 200-foot shoreline jurisdiction are subject to
regulation under the SMA, and the local Shoreline Master Program. E.g. Weyerhaeuser Co. .
King County, 91 Wn.2d 721, 736 (1979).
12. The SMA provides that the Act is to be “liberally construed to give full effect to
the objectives and purposes for which it was enacted,” including protection of the shoreline
environment. RCW 90.85.900; Merkel v. Port of Brownsville, 8 Wn. App. 844, 848-49 (1973).
13. Under the Jefferson County SMP, JCC Chapter 18.25, construction of a single-
family residence in the Natural shoreline environmental designation requires the issuance of a
shoreline conditional use permit. JCC 18.25.220; JCC 18.25.500(3)(c). The SMP requires “[a]ll
shoreline use and development to be carried out in a manner that avoids and minimizes adverse
impacts on the shoreline environment.” JCC 18.25.270(1)(a).
14. JCC 18.25.500(1) sets forth policies for residential development in the shoreline
environment. Of note, although residential use is not water-dependent, it is a preferred use of the
shorelines when such development is planned and carried out in a manner that protects shoreline
functions and processes to be consistent with the no net loss provisions of the SMP. JCC
18.25.500(1)(a).
1) Twana Way Road Work is Not Part of a Full, Unified and Integrated Project
15. Review under the SMA may extend to elements outside of the SMA’s 200-foot
jurisdictional limit where there is some integral linkage between the outside elements and other
project elements that are within the SMA’s jurisdictional boundary. When a proposal includes
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 43 OF 52
physical elements both within and outside of the 200-foot shoreline jurisdiction, the local
government should review the “full, unified, and integrated physical project” in order “to
determine to what extent those portions of the project outside the [shoreline] may adversely
impact the shoreline of the state.” Citizens to Stop the SR 169 Asphalt Plant v. King County, SHB
No. 22-007 at 88, 2023 WL 2977069 (Findings of Fact and Conclusions of Law and Order, Apr.
12, 2023). A physical element outside of the shoreline jurisdiction is part of the “full, unified and
integrated physical project” when the element is an “ integrated and non-severable part[] of the
total development.” Bahia v. Dep’t of Ecology, SHB No. 95-34, 1996 WL 538822 (Final Findings
of Fact Conclusions of Law and Order, Jan. 9, 1996).
16. The purpose of such extended review is to guard against piecemeal environmental
review so that local government may determine whether off-site components of such “full,
unified and integrated project” will adversely impact the shoreline. Hearing Examiner’s Order
on Appellants’ Motion for Summary Judgment (Order on Summary Judgment) at 4. Such review
does not “enlarge” the SMA’s jurisdictional reach beyond 200 feet, but instead ensures that all
aspects of a project – where portions are inside and outside the shoreline jurisdiction - are
reviewed together in a cohesive fashion. Id.
17. For residential development, a project element is integrated and non-severable if
the element is a necessary part of the plan to construct a residence or is necessary for the home
to function. See Manza v. Shorelines Hearings Board, 128 Wn. App. 1023, 2005 WL 1540942
at *8 (June 28, 2005); Bahia v. Dep’t of Ecology, SHB No. 95-34, 1996 WL 538822 (Final
Findings of Fact Conclusions of Law and Order, Jan. 9, 1996).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 44 OF 52
18. As a matter of law and as supported by substantial evidence in the record, the
Applicant did not propose new development or improvements to the pre-existing Twana Way as
a “unified part” of the single-family home development project.
19. Appellants did not carry their burden of proving that the Appellant did, in fact,
propose road work on Twana Way, or that road work on Twana Way is required for access to the
Property as an integrated and non-severable “element,” and a necessary part of the plan to
construct a residence or for the proposed home to function.
20. The Examiner concludes that road work on Twana Way is neither required for
construction of the single-family home nor integrated with and non-severable from the project.
As a matter of law, DCD did not err in reviewing the Application as proposed, or in its decision
to condition approval of the SCUP Decision with statement that road work on Twana Way is not
approved. Ex. 11, condition 7. DCD did not err as a matter of law in concluding that, because no
road work on Twana Way was proposed, analysis of potential impacts of road work on the
shoreline is not required. The Examiner upholds DCD’s interpretation of the scope of the
Applicant’s proposal.
21. DCD did not err in concluding that the Applicant’s compliance with conditions of
approval will ensure that the shoreline environment will not be adversely affected by unpermitted
road improvements. Per JCC 18.25.720, “[w]hen permit or permit exemption approval is based
on conditions, such conditions shall be satisfied prior to occupancy or use of a structure or prior
to commencement of a nonstructural activity.” The SCUP Decision, as modified by the two (2)
additional conditions of approval in this Decision, requires the Applicant to comply with the
critical areas ordinance by stating that and by requiring that the Applicant obtains additional
permits for any future modifications to Twana Way. Ex. 11, Condition 7.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 45 OF 52
2) Applicant’s Use of Twana Way is Consistent with the SMA and SMP
22. Substantial evidence supports DCD’s determination that Twana Way is
geotechnically stable and may be used safely, in its current condition, for construction access to
the Applicant’s Property.
23. The Hearing Examiner concludes that DCD properly exercised its authority as the
arbiter of the weight to be placed on conflicting expert opinions. See City of Des Moines v. Puget
Sound Reg’l Council, 98 Wn. App. 23, 37, 108 Wn. App. 836 (1999) (“When an agency is
presented with conflicting expert opinion on an issue, it is the agency’s job, and not the job of
the reviewing appellate body, to resolve those differences”); Gerla v. City of Tacoma, 12 Wn.
App. 883, 894, 533 P.2d 416 1975) (“At the very least, the decision was debatable and made
upon conflicting evidence. As such, it is not subject to judicial interference”).
3) Type of Report Submitted by Applicant
24. Appellants allege that the County erred by failing to require the Applicant to
submit a geotechnical report per JCC 18.22.540(4)(c). Appellants’ assertions are based on the
presumption that he Applicant is proposing to construct improvements on Twana Way; therefore,
Appellants assert, a geotechnical report should have been required because road construction
requires design engineering recommendations.
25. JCC 18.22.540(5) requires DCD to determine what report(s) the County accepts
and which one(s) the County rejects. Because no road improvements were proposed by the
Applicant, DCD did not err as a matter of law in relying on the reports submitted by The Stratum
Group in issuing the SCUP Decision.
26. Substantial evidence supports the conclusion that DCD properly completed its due
diligence in reviewing the professional reports provided to satisfy SCUP review requirements.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 46 OF 52
DCD’s reliance on the information provided by The Stratum Group was factually and legally
sound. DCD’s reliance on the information provided by the Applicant’s experts at The Stratum
Group does not constitute error of law. Substantial evidence supports the County’ s reliance on
the information provided by the Applicant
4) Consistency of Application with SMA and SMP
27. Substantial evidence supports the conclusion that the Application was properly
submitted, reviewed for completeness and supported by all required and requested reports in
accordance with JCC 18.40.530 (approval criteria for all conditional uses) and JCC 18.22.590
(shoreline conditional use permit criteria). The SCUP Application was correctly reviewed by
DCD as a Type II permit, consistent with JCC 18.25.620(3). DCD followed all applicable County
code requirements for processing a SCUP application.
28. Substantial evidence supports the conclusion that DCD considered, and
adequately addressed through conditions of approval in the SCUP Decision potential adverse
environmental effects that the Applicant’s proposed single-family home may have on the
shoreline environment, as required by JCC 18.25.590(2).
29. Substantial evidence supports the conclusion that the Applicant’s proposed
development and compliance with conditions of approval of the SCUP Decision, as modified in
this Decision, will result in no net loss of ecological functions and processes, as required by JCC
18.25.590(a)-(b).
30. Substantial evidence supports the following conclusions: (a) DCD included
conditions of approval in the SCUP Decision which were “deemed necessary to assure that the
development will be consistent with the policy and provisions of the [SMA] and this program as
well as the supplemental authority provided in Chapter 43.21 RCW as applicable, consistent with
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 47 OF 52
JCC 18.25.690; (b) the SCUP Decision includes measures to mitigate adverse impacts on
shoreline functions and processes; such mitigation will not have a significant adverse impact on
other shoreline uses fostered by the policies of the SMA. JCC 18.25.270(2)(c), (e); and (c) DCD
engaged in mitigation sequencing review of the Application consistent with JCC 18.25.270(2)(d).
31. Substantial evidence supports the conclusion that the Applicant’s project, as
approved and conditioned in the SCUP Permit, will not cause adverse effects to the Natural
shoreline environment in which it is located and is consistent with shoreline conditional use
criteria. JCC 18.25.220; JCC 18.25.590; RCW 90.58.020; see also JCC 18.40.530 (approval
criteria for all conditional uses).
32. Substantial evidence supports the conclusion that the Applicant’s proposed
single-family home is consistent with the policies of RCW 90.58.020 and the SMP.
33. Substantial evidence supports the conclusion that the Applicant’s proposed
single-family home will not interfere with normal public use of the shoreline. JCC
18.25.590(2)(b).
34. Substantial evidence supports a conclusion that DCD properly and appropriately
analyzed incremental and cumulative impacts in accordance with JCC 18.25.270(3)(b).
35. Substantial evidence supports the conclusion that the Applicant’s proposed
single-family home will be compatible with other permitted uses in the area. JCC 18.25.590(2)(c).
36. Substantial evidence supports the conclusion that DCD properly analyzed the
potential for adverse environmental effects of the proposed development on the shoreline
environment in which the proposed home will be located. JCC 18.25.590(2)(d). Appellants did
not meet their burden of proving that DCD erred in its determination that the Applicant’s project
is not likely to cause significant impacts to the shoreline environment.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 48 OF 52
37. Substantial evidence supports the conclusion that the public interest will not suffer
any detrimental effect as a result of construction or use of the proposed single-family home. JCC
18.25.590(2)(e).
C. Critical Areas Regulations
38. Critical areas are regulated in Jefferson County pursuant to JCC Chapter 18.22.
According to the purpose statement in JCC 18.22.500:
The purpose of this article is to reduce risks to human life and safety and reduce the risk
of damage to structures and property from geologic hazards, to allow for natural geologic
processes supportive of forming and maintaining fish and wildlife habitat, and to regulate
and inform land use and planning decisions. It is recognized that the elimination of all
risk from geologic hazards is not feasible to achieve but the purpose of this article is to
reduce the risk to acceptable levels
39. Twana Way is within a mapped geologically hazardous area per JCC 18.22.510
and subject to the standards of Article V of the County’s critical areas code, Chapter 18.22
because it is mapped as a high or moderate geologically hazardous area as a landslide hazard
area.13 JCC 18.22.510(2)(b) further refines the definition of landslide hazard areas to “include
any areas susceptible to landslide because of any combination of bedrock, soil, slope (gradient),
slope aspect, structure, hydrology, or other factors,” including:
(ii) Areas where all three of the following conditions occur:
(A) Slopes are steeper than 15 percent;
(B) Hillsides intersecting geologic contacts with a relatively permeable sediment
overlying a relatively impermeable sediment or bedrock; and
(C) Spring or groundwater seepage.
and
13 Per JCC 18.10.120, “Landslide hazard areas” has the same meaning as in WAC 365-190-
030(10).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 49 OF 52
(ix) Areas with a slope of 40 percent or steeper and with a vertical relief of 10 or more
feet, except areas composed of bedrock.
40. Nothing more than a demonstration that the factors listed in JCC 18.22.510(1)(b)
are present needs be established to reach a conclusion that an area is within a landslide hazard
area. While on-site inspection of actual conditions may be made, there is no provision in the
critical areas code that allows a mapped landslide hazard area to be “removed” from a portion of
the area mapped so as to exclude review of “land disturbing activity, development or activity on
land” that is subject to review under the County’s critical areas code (JCC 18.22.200(1)) or to
excuse the requirement for submission of a geotechnical report pursuant to JCC 18.22.540(4) and
JCC 18.22.905 for purposes of critical areas review. Even after providing deference to DCD’s
interpretation of its own code, the Examiner disagrees with its interpretation of JCC
18.22.510(1)(b) as a mere “screening tool.”
41. Per JCC 18.22.520, activities within a landslide hazard area that are regulated
include any development activity or action requiring a project permit. Because the Applicant is
not proposing any road improvements to Twana Way, the Applicant is not proposing any
development activity or action requiring a project permit within a landslide hazard area.
Therefore, protection standards set forth in JCC 18.22.530 do not apply. The SCUP Decision
does not authorize alteration of a critical area or critical area buffer. JCC 18.22.200(2). The
Applicant was not required to submit a geotechnical report, per JCC 18.22.540(4)(c), to support
the SCUP Application for a proposed single-family home. DCD did not err in relying on the
conclusions in The Stratum Group reports, weighed against the competing evidence presented
by Appellants. JCC 18.22.540(4)(c); see also JCC 18.22.905 (when special reports are required).
42. The Hearing Examiner concludes that, even under a liberal construction of the
County’s critical areas code (JCC 18.22.110 and .120), Appellants’ argument that mere
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 50 OF 52
construction vehicle use of Twana Way should be considered to be “land disturbing activities,”
defined in JCC 18.10.120 as, “any activity that results in movement of earth, or a change in the
existing soil cover (both vegetative and nonvegetative) and/or the existing soil topography. Land
disturbing activities include, but are not limited to, clearing, grading, filling, and excavation.
Compaction that is associated with stabilization of structures and road construction shall also be
considered a land disturbing activity. Vegetation maintenance practices are not considered land-
disturbing activity,” is not legally supportable.
43. The SCUP Decision is supported by substantial evidence and does not constitute
error of law with regard to compliance with the County’s critical areas code, Chapter 18.22 JCC.
44. In preparing and issuing this Decision, the Hearing Examiner reviewed both the
record as it existed before DCD and information presented at the hearing. See North Park
Neighbors v. City of Long Beach, SHB No. 05-030 at V, 2006 WL 2848721 (Findings of Fact,
Conclusions of Law, and Order, Sept. 28, 2006) (a shoreline application consists of the entire
record developed on review).
45. The Hearing Examiner has authority to affirm the SCUP Decision, grant the
Appeal or modify the Decision. RoP 6.1(c)(4) and (6). The Hearing Examiner also may remand
the SCUP Decision to DCD for further fact-finding and decision-making consistent with the
Examiner’s Decision. RoP 6.1. The Hearing Examiner determines there is no basis on which to
remand the SCUP Decision.
46. The Hearing Examiner finds and concludes that Appellants have not met their
burden of proving that the SCUP Decision was issued contrary to substantial evidence in the
record and/or constitutes error of law.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 51 OF 52
47. With the additional conditions of approval set forth in this Decision, the
Application will be consistent with the critical areas, shoreline buffers and ecological protection
no net loss and mitigation regulations in JCC 18.25.270(2), critical areas and shoreline buffer
regulations in JCC 18.25.270(4), will not result in cumulative impacts consistent with JCC
18.25.270(3), and meets all shoreline conditional use permit criteria in JCC 18.25.590(2), and
criteria applicable to all conditional uses in JCC 18.40.530.
DECISION
Based on the foregoing Findings of Fact and Conclusions of Law, the Jefferson County
Hearing Examiner DENIES the Appeal and AFFIRMS the SCUP Decision, File No. SDP2023-
00020, with MODIFICATIONS, subject to the following additional conditions of approval:
1. Upon completion of the approved single-family home development, Applicant
shall repair Twana Way to its pre-construction condition, including but not limited to replanting
damaged vegetation along the side of the road and repairing any damaged and/or filled “water
bars” to their previously functioning condition. To ensure compliance with this condition of
approval, the Applicant shall submit photographs to DCD to document the complete, unaltered,
undamaged condition of Twana Way prior to the commencement of construction activities on
the Property.
2. Applicant shall comply with the best management practices outlined in the
Cumulative Impacts Assessment Report issued January 24, 2025:
General Best Management Practices for Small Construction Sites
• Hand-tools should be used whenever practicable, consistent with standard
building practices.
• Marking the critical root zone (CRZ) of trees with paint, flagging, or other to
avoid running equipment and stockpiling materials in CRZ, therefore limiting
soil disturbance and compaction. Additionally, any necessary heavy
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
FINDINGS OF FACT, CONCLUSIONS OF LAW AND FINAL DECISION - PAGE 52 OF 52
equipment and/or truck access should entail a layer of clean woodchips, or
sufficiently wide and thick steel plates in the vehicle wheel path to avoid
rutting and damaging the vegetation.
• Construction should not be conducted during heavy precipitation events,
regardless of the protection of vegetation. If vegetation is damaged, or rutting
occurs, it is recommended that those areas be re-planted with native vegetation.
If planting is necessary, a layer of clean woodchips should also be installed
around plants at a minimum depth of 3 inches.
• Limit the extent of clearing operations and phase construction operations.
• The duff layer, native topsoil, and natural vegetation should be retained in an
undisturbed state to the maximum extent practicable.
SO ORDERED this 3rd day of November, 2025.
STEPHANIE MARSHALL
Jefferson County Hearing Examiner