Hi Donna,
Can you tell me where the permitting is for the project? I am trying to get an accurate budget for time moving forward
and I am unsure how much time I will need to spend on County Permitting because I'm not sure where we are in the
process. Are we slated to have a hearing? Are there other hurdles you would anticipate?
Thanks and take care,
Chris Gourley
Cell: 360-790-3118
She/Her/Hers
From: Gourley, Chris L (DFW)
Sent: Tuesday, May 2, 2023 10:16 AM
To: 'Donna Frostholm' <DFrostholm@co.jefferson.wa.us>
Subject: RE: MLA21-00007
Hello Donna,
The mitigation area on site will be allowed to continue as a natural process area, though we are not planning on blocking
it off to public access. No fences or similar will be put up, but the area is still part of the site. Did I clear up the question
for you?
Thank you and take care,
Chris Gourley
Cell: 360-790-3118
She/Her/Hers
From: Donna Frostholm <DFrostholm@co.Lefferson.wa.us>
Sent: Tuesday, May 2, 2023 10:03 AM
1
To: Gourley, Chris L (DFW) <Chris.Gourley@dfw.wa.gov>
Subject: FW: MLA21-00007
External Email
Hi Chris,
I want to apologize for the delay in getting back to you about your shoreline application at Pt Whitney.
I made a site visit after receiving the most recent information from you, but was not able to follow up. As I recall, I think
I may have only one question for you following the site visit. The mitigation area waterward of the parking lot and picnic
table graded down to a high-energy marine shoreline environment. My question is: will natural shoreline processes be
allowed to continue in the mitigation area (e.g., erosion, natural vegetation establishment) or will this area be
maintained as a park amenity (i.e., provide public access to the beach)?
I hope to take another look at the application case file later this month, and will follow up with you then.
Regards,
Donna frosthoCm, P'WS
Associate Aanner-.Cead/WetCandSpeciaCist
Jefferson County Department of Community DeveCopment
62i Sheridan Street, Port Tawnsen[4 'Washington 98368
36o-379-4466 clrYoslhrrCrri?co. a ersgn.jY ff:
DCD IS OPEN MONDAY — THURSDAY FROM 9:00 —12:00 and 1:00 - 4:30; CLOSED FRIDAY.
All emails sent to and from this address will automatically be archived by Jefferson County and emails may be subject to Public Disclosure under Chapter 42.56 RCW.
From: Gourley, Chris L (DFW) <Chris.Gourley@dfw.wa.gov>
Sent: Thursday, February 16, 2023 1:06 PM
To: DCD Front Staff <dcd@co.iefferson.wa.us>
Subject: MLA21-00007
ALERT: BE CAUTIOUS This email originated outside the organization. Do not open attachments or click on links if you
are not expecting them.
Hello,
Can you please provide a status on this application and permit? A sign was placed on site in November of 2021 and I did
not hear from Donna Frostholm after. Please provide next steps to move forward on the project.
Thank you,
Ch4l(lk(�otwLey