JEFFERSON COUNTY
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
Board of County Commissioners
Janet Silvus, Director of Jeff Com 9-1-1
December 6, 2010
JEFFCOM 9-1-1 Radio System Improvements Change Order Request No. 16
STATEMENT OF ISSUE: Approval and execution of Change Order Request (COR) No. 16 in the amount
of $377,796.00 for Buchanan General Contracting Company (Contractor).
ANALYSIS: On January 25, 2010, the Board of County Commissioners approved and executed a contract
with Buchanan General Contracting Company, P.O. Box 40069, Bellevue, W A 98015 for the construction of
the JeffCom 9-1-1 Radio System Improvement Project. The original contract work at Green Mountain, South
(Coyle) and Maynard Peak sites has been completed.
We have been keeping the contract open for construction ofthe Port Townsend Water Tank Site, an entire
new radio tower site. We are currently in the conditional use process and anticipate building permits in latc
December or January. Change Order Request No. 16 is for construction of that sitc and is attached for your
approval and execution. The Board of Commissioners has already approved the purchase of an equipment
building and emergency generator for the City site and we will soon be bringing a request for purchase of the
tower itself. These will all be installed by the Contractor under COR No. 16.
We did include the intention to construct the City site within the original Invitation to Bid and contract
documents so the JeffCom Administrative Board and Board of County Commissioners would have the ability
to approve the additional construction by change order without having to go back out to bid. And it states, "In
the event JEFFCOM 9-1-1 and the contractor are unable to reach agreement on the additional cost associated
with this additional site, JEFFCOM 9-1-1 reserves the right to seek bids from other companies for this work."
Change Order No. 16 was approved by the JeffCom Administrative Board on November 4, 2010.
FISCAL IMPACT: Funds will be provided by the JeffCom Enhancement Fund 121 which was funded by a
2007 bond issue. The total amount ofthe original contract with sales tax is $364,728.08. Change Order
Requests No.1 through 15 increased the current approved costto $461,909.08. The addition of COR No. 16 in
the amount of$377,796.00 brings the new total to $839,705.08. The total ofCORs 1 through 16 is
$474,977.00 or 130.29% of the original contract. The total projected costs of this project have exceeded the
original 2007 bond issue and will require an additional bond issue to cover the costs. A bond issue is being
prepared separately by the County Treasurer for this project.
RECOMMENDATION: Move to approve and execute Change Order Request No. 16 to the JeffCom 911
Radio System Improvement Contract with Buchanan General Contracting Company.
!
II tiCfto
Date
JEFFCOM 9-1-1 Radio System Improvements
CHANGE ORDER REQUEST No. 16
On January 25,2010, Jefferson County executed a Contract with Buchanan General Contracting Company
(Contractor) for the public works construction ofJeffCom 911 Radio System Improvements in the amount of
$364,728.08 including local and state sales tax. Previously approved Change Order Requests (COR) No.1
through 15 bring the approved project total to $461,909.08 to date. Proposed COR No. 16 in the amount of
$377,796.00 would bring that total to $839,705.08 (a total of 130.23% increase).
The intention to construct the City site was included within the original Invitation to Bid and contract documents
so the JeffCom Administrative Board and Board of County Commissioners would have the ability to approve the
additional construction by change order without having to go back out to bid. And it states, "In the event
JEFFCOM 9-1-1 and the contractor are unable to reach agreement on the additional cost associated with this
additional site, JEFFCOM 9.1.1 reserves the right to seek bids from other companies for this work."
The scope of work for the project is described in the Contract, Amendments to Standard Specifications and on the
Plans that are included in the original Contract. That scope of work is hereby amended as follows:
Provide labor, equipment, materials and supervision to construct the Port Townsend Water Tank Site including
clearing & grading; rock retaining walls; foundations for 180' tower, equipment shelter and emergency generator;
erection of] 80' tower; installation of equipment shelter and emergency generator; all related electrical and
grounding; fencing; landscaping and related site work, all per the provided plans and specifications.
The Contract amount is hereby amended as follows:
On November 19, 2010, the Contractor provided a price quote of $377,796.00 for COR No. 16 (copy attached)
for the extra costs related to the construction of the Port Townsend Water Tank Site as described above. The total
Contract amount is hereby amended to $839,705.08.
The Contract is also hereby amended to add 65 working days for this work bring the total to ] 55 working days.
There are no changes to any other provisions of the Contract than stated herein.
Executed by the Contractor November 18,2010
\51A<:fo/I\NAN 6E'Nejl..,qL ~tJ1". ~.
.. , f.'~_
! I <;
Contractor
By: \~
~
~~~
,'t: q
.-:,,'"
.
v-, .'
l
MMAc..,cs-f/""
SEAL:
COUNTY OF JEFFERSON
BOARD OF COMMISSIONERS
David W. Sullivan, Chair
Phil Johnson, Member
John Austin, Member
ATTEST:
Erin Lundgren,
Deputy Clerk ofthe Board
.,
BUCHANAN
GENERAL CONTRACTING COMPANY
..... ' .....
November 19, 2010
Little Little Construction
2009 4th Street
Port Townsend, W A 98368
Attention:
Alex Little
Reference:
JEFF COM 911 Communications
CE16 - Port Tovmscnd Water Tank
We are pleased to submit a lump sum quotation of $377,796.00 to provide all of the labor, material, equipment, subcontract
work and supervision necessary to complete the Port TmVIlsend \Vater Tank project per the drawings provided, CD
REVIEW SET - 10/4/1 O.
Also, this additional work \vill require an extension of the current contract by 65 working days (three months).
Clarifications and Assumotions:
1. We have included pricing for lower foundation based on three (3) S' diameter by 24' deep caissons;
2. We have included vinyl slats in the existing fence from the NE to SE comers of the new compound;
3. Wc have included a credit for th work not required in CE-13 - Access for Gcteoch at Pt. Townsend Site;
4. V\'e have included a Payment and Performance Bonds;
5. Wc have included Washington State Sales Taxes.
Items snecificallv excluded from ProDosal:
1. Purchase and shipping of generator, shelter and lattice tower;
2. Cable and antenna install;
3. Power company fees and equipment;
4. Architectural or Structural design fees;
5. Ruilding Permit and Plan-Check fees;
6. All other permits that may be required;
7. Removal of hazardous materials;
8. Special Inspections.
Please issue a change order with this additional work. Thank you.
Vcry Truly Yours.
~~~
Terry Buchanan
Project Manager
PO Box 40069 Bellevue, W A 98015
phone 425 462-1326 fax 425 462-9468 www.buchanangc.com
BUCHAGC 159CF
Buchanan General Contracting Co.
Jeffcom 911 Comrnunicatons
CE16 - Port Townsend Water Tower
Proposal Date: 11/512010
Revision Date:
BGC 1 Labor Material Subcontractor Total Notes
_n -..-- -----.-- ----- --
Code i Description Quantity Unit Total Unit Total Unit Total Cost
General Conditions 1
SUPERINTENDENT
Superintendent 306 hr 49.60 15,178 0.00 0 0.00 0 15,178
Meetin s & Re rtin 20 hr 49.60 992 0.00 0 0.00 0 992
g po g
Site Walks
PROJECT MANAGEMENT
: Building permit and license
As built drawings
Additional blueprints
Project manager travel
Estimating Prevailing wages
Project Managing
TELEPHONE
Telephone
FAX equipment
TEMPORARY CONSTRUCTION
Subsistance Superintendent
Subsistance Craft
Subsistance Craft Duncan
Toles, Fuel & Ferry
:Travel trucks
'Job office
Sanitary convenience
Temp power hook up
Temp power
Temp weather protection
Wrnter Protection & Impacts
Temp water hook up
I Temp water
Local yard (composite rate)
Disposal
Mobilize & Demobilize
Final cleanup
Temp fence
,CONCRETE PLACING EQUIP.
Safety
Construction equipment
Pick up truck
Tool sharpening
! Job photos
Small tools
FUEL OIL & GREASE
4 hr 0.00 01 0.00 0 0.00 0 0
1 Is 0.00 0 0.00 0 125.00 125, 125
1 Is 0.00 0 0.00 0 475.00 475' 475
1 Is 0.00 0 200.00 200 0.00 0 200
,
1 Is 0.00 0 0.00 0 0.00 0 01
1 Is 0.00 01 225.00 225' 0.00 0 225
1 Is 0.00 0 0.00 0 0.00 0 0
2.25 mo 0.00 0 225.00 506 0.00 0 506
2.25 mo 0.00 0 125.00 281 000 0 281 mise
50 da 0.00 0 45.00 2,250, 0.00 0 2,250
162 da 0.00 01 35.00 5,670 0.00 0 5,670
25 da 0.00 01 45.00 1,125 0.00 0 1,125
60 da 000 0 65.00 3,900 0.00 0 3,900
800 0.00 0 125.00 1,000 0.00 01 1,000
I
2.25 mo 0.00 0 325.00 731 0.00 0 731
2.25 me; 0.00 0 135.00 304; 0.00 0 304
2.25 mo 0.00 0 425.00 956, 0.00 0 956
2.25 mo 0.00 0 275.00 619 000 0 619
1 Is 0.00 ,
0.00 0 0.00 0 0 0
1 Is 0.00 0 800.00 800 0.00 0' 800
2.25 mo, 0.00 0 125.00 281 0.00 0 281,
2.25 mo' 0.00 0 90.00 203 0.00 0 203.
20 hr 40.03 801.~ 35.00 700i 0.00 0 1,501
3 ea 120.09 360: 70.00 210 115.00 345 915
20 hr 40.03 801 35.00 700 0.00 0 1,501
1 Is 0.00 0 325.00 325 0.00 01 325
1 Is 0.00 0 0.00 0 0.00 0' 0
10 hr 49.60 496 37.50 3751 0.00 0 871
2.25 mo 0.00 0 460.00 1,035 0.00 0 1,035
2.25 mo 0.00 0 675.00 1,519 0.00 0 1,519
1 Is 0.00 0 80.00 80 0.00 0 80
1 Is 0.00 0 200.00 200 0.00 0 2001
2.25 mo! 0.00 0 460.00 1,035 0.00 0 1,035'
Fuel and maintenance 2.25 mo 0.00 0 1050.00 2,363 0.00 0 2,363
Fuel adjustment 2.25 mo 0.00 0 375.00 844 0.00 01 844
BUILDING LAYOUT I SURVEY
Locates 8 hr 0.00 0 0.00 0 125.00 1,000 1,000
Foreman (carpenter) 48 hr 48.63 2,334 20.00 960 0.00 0 3,294
,
Survey and Engineer Site 2.25 mo' 0.00 01 375.00 844 0.00 0 844
STRUCTURAL CONSULTANT !
Testing and inspection 1 Is 0.00 0 000 0 600.00 600 600
SUBTOTAL GENERAL CONDITIONS 20961 30240 2545 53746
,
EQUIPMENT ! 1 sic 0.00 0 0.00 0, 0.00 0 0
1 Is 0.00 0 0.00 Oi 1070.00 1070 1,070
1 sic 0.00 0 0.00 0 0.00 0 0
,
none
MobJdemob equipment
SITEWORK EXTRA OVER
WinterAccess & Work Pad- 31oo5f 1 sic I
580 Backhoe lexcavator 24 hr
10cy Dump 0 hr
filter fabric 3419 sf
12/0 import & place quarry spalls @ 12" 154 cy
12/0 ,rought grade 344 sy
eE16 - Port Townsend Water Tower, 11-19-10
0.00 0
0.00 0
0.00 0,
0.09 291
1.10 169
0.49 168
Page 1
winter access
0.00
0.00
0.00
0.15
32.00
0.00
0 0.00 0
01 130.00 3120
0 105.00 0
513 0.00 0
4928 0.00 0
0 0.00 A'
I
01
3,120'
o
803
5,097
168
BGC __"Labor Material Subcontractor Total Notes
Totai1- -
Code Description Quantity Unit Unit Total Unit Total Cost
plate compactor - clean-up 1 da 30"00 30 115m 115 0"00 0 145
miscellaneous eroision control 1 Is om 0 0"00 0 120000 1200 1,200
,
i
SITEWORK 1 sic 0"00 0 0"00 0 0"00 0' 0
Access Road - irregular 4150sf 1 sic 0"00 0 om 0 om 0 0
580 Backhoe ! 46 hr 0"00 0 0"00 0 130m 5980 5,980
i 10cy Dump 12 hr 0"00 0 0"00 0 105"00 1260 1,260
1610 clear & rub 462 s 0"52 240 0"00 01 000 0 240
Buchanan General Contracting Co.
Jeffcom 911 Communicatons
CE16 - Port Townsend Water Tower
5/12 jload, ha~1 & dispose
6/a cut to fill
6/0 rough grade & compact
compactor
filter fabric
13/0 import & place gravel @ 6"
finish grade
plate compactor - clean-up
Y
100 cy
60cy
462 sy
2 da
4565 sf
100 cy i
462 BY ,
1 da
Compound - 58'x58' 1 sic
580 Backhoe 106 hr
10cy Dump 70 hr
install silt fence 240 If
4/0 gravel @ sitt fence 18 cy
12/0 I tree removal - 4" or bigger 34 eo
6/12 load & dispose trees & stumps 60 cy
34/0 excavate dirt 390 cY ,
20/48 'load, haul & dirt 390 cy I
12/0 clear & grub 374 sy
4/10 load & dispose 81 cy
4/0 rough grade & compact 374 sy
I compactor 2 da
filter fabric 3703 sf
11/0 : buy & place rock - 6" 81 cy
finish grade 374 sy j
compactor 2 da
IKeystone Retaining Walls 1 sic
4.69'x 168'
1580 Backhoe 20 hr
10cy Dump 3 hr
6/0 excavate toe of wall . 168'x2'x2' 25 cy
1/3 load & dispose 13 cy
410 'import & place gravel foundation 13 cy
I deliver keystone 1 Is
buy & place keystone wall 168x4.69' 788 sf
4" perforated footing drain w/sox 180 If
filter fabric behind wall 867 sf
6/0 buy & place drain rock 168'x4.69'x1,5' 49 cy
3/0 finish grade 112 sy
EXCAV" & BJF FOR UTILITIES 1 sic
Grounding - 332' 1 sic
580 Backhoe 17 hr
8"5 grounding machine excavavation 55 cy
R5 backfill & compact native material 55 cy
; compactor 1 da I
Proposal Date: 11/5/2010
Revision Date:
751 I
0"75 2"00 200' 0"00 0 2751
1"80 108i om 0 0"00 0 108
0"45 208 0"00 0 0"00 0 208
15"00 30 115"00 230 0"00 0 2601
0"09 388 0"'3 593 om 0' 981
1"95 195 2R5O 2950 om 0 3,145
OA5 208 0"00 0 om 0 208
30"00 30 115"00 115! 0"00 0 145
0"00 0 0"00 0' 0"00 0 13,7~ I
0"00 0, 0"00 0 130"00 13780
om 0 0"00 0 105"00 7350 7'3501
3m 720 2"00 480 0"00 0 1,200
3A5 62 36"50 657 0"00 0; 7W
7"06 240 0"00 0 0"00 0 240
1"50 90 14.00 840 0"00 0 930
U1 511 0"00 01 0"00 0 511
0"77 300 2"00 760 0"00 0 1,080
0"48 180: 0,00 0 0"00 0 180
0.74 60 om 0 0"00 0 60
0"45 168 0"00 0 0"00 0 168
15"00 30 115"00 230 0"00 01 260
0"09 333 0"13 481 om 0' 815
2"04 165 2R50 2390 om 0 2,555
OA5 168 0"00 0 0"00 0 168
15"00 30 115"00 230 0"00 0 260
0"00 0' 000 0 000 0 0
I
om 0 0"00 0 130"00 26001 2,600
0"00 0 0"00 0 105"00 315' 315
3"65 91 0"00 0 0"00 0 91
1,13 15 6"00 78! 0"00 0 93'
925 120 29"50 364 0"00 0 504
0"00 0; 500"00 500' 0"00 0 500 jacob @ mm
1"65 1300 5"09 4011 0"00 0 5,311 425-452-2311
0"75 135 150 270 000 0' 405
0"12 104 0"12 104 om 0 208
3"67 180 3650 1789 om ~I 1,968
OA3 48 0"00 0 000 48,
0"00 0' 0"00 0' 0"00 ~I 0
0"00 0; om 0 0"00 0
0"00 0 0"00 0 130"00 2210 2,210
2"32 128 0"00 0 om 0 128
2.32 128 0"00 0 000 , 1281
0
15"00 15 115"00 115 0"00 0 130
Power Telco onloff site - 200'
580 Backhoe 15 hr 0"00 0 0"00 0 130"00 1950 1,950
10cy Dump 3 hr om 0 0"00 0 105"00 315 315
5 grounding machine excavavation 35 cy 220 77 0"00 0 0.00 0' 77
213 load & dispose 15 cy U3 17 6.00 90 om ~I 107
5 'backfill & compact native material 35 cy 220 77 0"00 0, 000 77
2/0 I import & place bedding sand 16 cy i 3"80 61. n50 280 0"00 3411
CE16 - Port Townsend Water Tower, 11-19-10 Page 2
Buchanan General Contracting Co.
Jeffcom 911 Communicatons
CE16 Port Townsend Water Tower
Proposal Date: 11/512010
Revision Date:
-
BGC Labor Material Subcontractor Total , Notes
Code Description Quantity Unit Total Unit Total Unit---" lota-I-- Cost
compactor 1.5 da 15.00 23 115.00 173 0.00 0 195
2" PVC powerltelco conduit 200 If 0.00 0 0.00 0 0.00 0 0 electrical
2" PVC sweeps 4 ea 0.00 0 0.00 0 0.00 0 0 electrical
1/0 17x30 pull box 2 ea 000 0 0.00 0 0.00 0 0 electrical
pickup materials I 4 hr 0.00 0 0.00 0 0.00 0 0 electrical
LANDSCAPING 1 sic 0.00 0 0.00 0 541B.oo 5418 5,418 cathcart
small digger 20 hr 0.00 0 0.00 0 0.00 01 0
; labor i 48 hr 0.00 0 0.00 0 0.00 0 0
,
doug firs ~ 10' min height 16 ea ! 0.00 0 000 0 0.00 0 0,
,
evergreen huckleberry - 30" min hgt 18 ea 0.00 0' 0.00 0 0.00 0 oj
soil & improvement 12 cy 0.00 0' 0.00 0 0.00 0 0
i
TOWER FOUNDA nON 1 sic 0.00 0 0.00 0 0.00 0 0
,
CAISSON 60' x 24 In clayey sand wino water
580 Backhoe
10cy Dump
Layout & mobilize
Master Template by Buchanan
Weld bolts & assembly
! Set anchor bolts
Inspection by contractor
load, haul & dispose
Rebar - furnish
Rebar - place
Concrete @ caisson 6000 psi
'Driller - 60''x24' caissons 3 each
vac truck & mud disposal
Pumping mob
Pumping hourly
Pumping cy
Grout & drain
Form 5'x5' pier at one leg xJo
Form 5'x5' caisson cap
Drill day labor
,Pick up bolts & template
12 hr
12 hr
1 Is
1 Is
3 00
3 00
12 hrs'
68 cy
2.60 t
2.60 t
68 cy
1 Is
1 Is I
1 Is i
6 hr
68 cy
3 ea
2 ea
3 ea
48 hrs
1 Is
CHAIN LINK FENCE - 6'CLF
8' chain link fence wi vinyl slats
vinyl slats on existing fence
18' dbl gate
1 sic
297 If i
1,481 sf
1 ea
6" PIPE BOLLARDS - none
6' pipe bollard (3' embed)
excavate
concrete
1 sic
200
1 cy
1 cy
2/0
1/2
I' SHELTER SLAB & STOOP 112'x22')+ 2x14'x4')
580 Backhoe I 4 hr
10cy Dump 2 hr
I excavate thickened edge I 11 cy
: load, haul & dispose of debris 9 cy ,
fine grade & compact , 296 sf
compactor 0.5 da
I' 24" edge forms 68 If I
2x8 edge forms @ stoop 24 If
L extra forming @ stoop 2 ea
I buy & place rebar 950 #
3/4" champher strip 92 If
screeds 296 sf
buy & place concrete 9" 15 cy ,
I finish concrete 'I 296 sf I
cure & protect 296 sf
CE16 - Port Townsend Waler Tower, 11-19-10
0.00 0 0.00 0 130.00 1560i 1,560
0.00 0 0.00 0 105.00 1260' 1,260
120.00 120 60.00 60 0.00 0' 180
120.00 120 650.00 650 0.00 0 770
45.00 135 185.00 5551 0.00 0 690'
60.00 180 25.00 75! 0.00 0 255
0.00 0 0.00 0 100.00 1,200 1,2001
0.00 0 4.00 272 0.00 0 272
0.00 0' 0.00 0 1156.92 3,008 3,008 ct sales
0.00 0 0.00 0 579.00 1,505 1,505 cruncher
0.00 0 110.00 7,480 0.00 0' 7,480
0.00 0 0.00 0 21350.00 21,350i 21,350, versatile
0.00 0 0.00 0 1800.00 1,800 1,800'
0.00 0 75,00 75 135.00 135 210
15.00 90 0.00 01 135.00 810 900
0.00 0 0.75 51 3.75 255 306
30.00 90, 60.00 180i 0.00 0 270
90.00 180 275.00 550 0.00 0 730
0.00 0' 65.00 195 0.00 0, 195
15.00 720 0.00 0 0.00 0 720
60.00 60 75.00 75 0.00 OJ 135,
I
000 0 000 0 10953.00 10953 10,953 viking
0.00 a: 0.00 0, 000 0 0
0.00 0 0.00 0' 000 0 0
0.00 0' 0.00 0 0.00 0 0 existing
0.00 0 0.00 0 0.00 0 0
30.00 60 180.00 360 0.00 0; 420,
40.00 40 90.00 90 0.00 0 130
60.00 60 90.00 90. 0.00 0 150
i
0.00 OJ 0.00 0 130.00 520 520
0.00 0 0.00 0 105.00 210! 210
5.45 60 0.00 0 0.00 0 60
3.75 34 2.00 18 0.00 0 52
0.20 59 0.00 0 000 0 59,
30.00 15 115.00 58 0.00 0 73
3.50 238! 2.75 187; 0.00 0 425
2.50 60 1.75 42 0.00 0 102
60.00 120 90.00 180 0.00 0' 300
0.25 238 0.03 29 0.58 551 817
0.45 41 0.35 32 0.00 , 74,
0
0.12 36 010 30, 0.00 0 65;
15.00 225 96.00 1,440 0.00 0 1,665
0.45 133 0.00 2~1 0.00 0 133
0.10 30 0.08 0.00 0 53
Page 3
BGC Quantity r--IJ~it labor Material Subcontractor Total Notes
-. Total' Cost
Code Description Total Unit Total Unit
1/0 backfill 1 1 hr 45.00 45 25.00 25 0.00 0 70'
GENERA TOR SLAB - 6' x 10'
580 Backhoe 1 hr 0.00 0 0.00 0 130.00 130 130
10cy Dump 1 hr 0.00 0 0.00 0 105.00 105 105
1/0 excav thickened edge 4 cy 5.00 20 0.00 0 0.00 0' 20
0/1 : load, haul & dispose of debris 3 cy 3.75 11 2.00 6 0.00 0 17 w/above
fine grade & compact 60 sf 0.25 15 0.00 0 0.00 0, 15
Buchanan General Contracting Co.
Jeffcom 911 Communicatons
CE16 - Port Townsend Water Tower
compactor
24" edge forms 32'
buy & place rebar 600'X,#4
3/4" champher strip
screeds
I buy & place concrete o'
finish concrete
cure & protect
condenser pad 4'x2'x6"
INSTALL 25 KW GENERATOR
mobe forklift
forklift rental
; load & transport generator
set generator
; attach generator to pad
initial fuel fill
INSTALL OFCI SHELTER
mobeJdemobe 35 ton crane
rig, hoist & set shelter@site
transport shelter to site
'mobe/demobe 70 ton crane
rig, hoist & set shelter @site
attach shelter to pad
layout & cut-in wave guide entry port
F&I 3x4 WGEPs
ICE BRIDGE 20'
labor all ice bridge
auger bridge posts 54"x18"
buy & set 3 1/2" post & cap
buy, tie & set rebar @20#ea
concrete @ posts
arm over brackets
; 24" grip strut
1/2" all thread
unistrut
nuts & washers
MU, taxes & freight
, delivery
FURNISHINGS
combination locks
signage
FURNISH 180' TOWER (nle)
, Purchase 180' tower
WA State engineers stamp
foundation design
delivery from Salem, OR
ship anchor bolts separately
0.5 da !
62 sf
330 #
32 If
60 sf
5 cy
60 sf
60 sf
8 sf
1 Is
1 Is
1dy
4 hr
2 hr
4 ea
200 ga
1 Is
3 hr
3 hr
5 hr
2 hr
2 hr
4 ea
1ea
1ea
1 Is
40 hr
5 ea
5 ea
100 #
4 cy
5 ea
36 If
36 If
36 If
250 ea
15 %
8 hr
1 sic
2 ea
5ea
1 sic
1 Is
1 Is
1 Is
1 Is
1 Is
I INSTALL 180' SST 1 sic I
CE16 - Port Townsend Water Tower, 11-19-10
30.00
3.50
0.35
0.45
0.12
15.00
0.65
0.10
5.63
0.00
000
30.00
30.00
30.00
3.75
0.00
0.00
0.00
40.00
0.00
0.00
60.00
3.75
30.00
15.00
0.00
15.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0,00
0.00
0.00
15.00
000
3.75
6.00
0.00
000
000
0.00
0.00
000
000 0
Page 4
15 115.00
2171 2.25
116 0.Q3
14 0.35
7 0,12
75 96.00
39 0,00
6 0.08
45 5.00
o 0.00
o 38045
30 459,15
120 0.00
60 0.00
15, 3.50
0' 3.75
o 0.00
o 201.10
120 201.10
o 145.00
o 330,62
,
120' 330,62
151 3.50
30 20.00
15 225.00
o 0.00
600, 0.00
o 80.00
o 75.00
o 0.03
o 96.00
o 8500
OJ 28.00
o 2.00
o 4.00
o 0.75
o 29.99
120 35.00
o 0.00
8 22.00
30 70.00
o 0.00
0' 0,00
0, 0.00
o 0.00
o 0.00
o 0.00
0.00
Proposal Date: 11/512010
Revision Date:
58 0.00 0 73!
140 0.00 0 357
10: 0.58 191 317
11 0.00 0 26
7 0.00 0 14
450 0.00 0 555
0 0,00 0, 39
5 0.00 0 11
,
1
40: 0.00 0 85
1
0 0.00 0 0 1,000#
380 0.00 01 380 350+wsst
459 0.00 0' 519 450+wsst
0 35.00 140 260
a: 35.00 70 130
14 0,00 0 29'
750 000 0 750
0 0.00 0 0
603 0.00 0' 603
603 0.00 0: 723,
725 0.00 0 7251
661 0,00 0 661 using mick's
6611 0.00 0 781
14 0.00 0 29
20 0.00 0 50
225 0.00 0: 240
O! 0.00 01 0
01 0.00 ~I 600
400 0.00 400
375 0.00 0' 375
3 1,00 100 103
,
384 34.00 136 520 ,short road
425 0.00 0 4251
1008 000 0 1,008
72 0.00 0 72
144 0.00 0 144
188 0.00 0, 188,
450 0.00 0 450 w/discount
280 0,00 0 400
0 0.00 0 0
44 0,00 0' 52
350 0,00 0 380
0 0.00 0 0' Valmont
0, 0.00 0 0 72745.00
~I 0.00 0 0 1250.00
0,00 01 0 600.00
~I 0.00 oi 0 1200.00
0.00 0 0
O! 32030.00 32030 32,0301 Mick
Buchanan General Contracting Co. Proposal Date: 11/512010
Jeffcom 911 Communicatons Revision Date:
CE16 - Port Townsend Water Tower
BGC Labor Material Subcontractor Total Notes
Code ; Description Quantity Unit Total Unit Total Unit Total Cost
i mobilize forklift for assembly 1 Is 0.00 0 0.00 0; 0.00 0 0
forklift rental to assemble tower 2 wk 0.00 0, 0.00 0 0.00 0 0
I assemble tower sections
4 men x 10 hrs x 85/hr 9 ea 0.00 0 0.00 0 0.00 0 0
I mobe 70 ton crane for tower set 2 hr 0.00 0 0,00 0 000 0 0
; 70 ton crane on site for tower set 10 hr 0,00 0 0,00 0, 0.00 0 0
stack tower 40 hr 0.00 0 000 0 0.00 0 0;
! 01
CABLE & ANTENNA INSTALL 1 sic 0.00 a' 0.00 0 0,00 0
none 1 Is 0,00 0 0.00 0 0.00 0' 01
1 sic! , 0'
UPGRADE PSE TRANSFORMER 0.00 0 0,00 0 0.00 0
upgrade PSE transformer 1 Is 0,00 0 0.00 Oi 0.00 0 0 nic
MISC, ELECTRICAL 1 sic 0.00 0 0.00 0 21576.00 21576 21,576 seahurst
mobilize electrical 8 hr 0.00 0 0,00 0 0.00 01 0
F&I H Frame 1 ea 0.00 0 0,00 0 0.00 0 0
temp power to temp shelter 4 hr 0,00 0 0.00 0 0.00 0 0
Ifurnish & install meter socket 4 hr 0,00 0, 0.00 0: 0.00 0 0
UG conductors all 220 If 0.00 0 000 0 0,00 0 0
furnish & install disconnect 1 ea 000 0 0,00 0 0.00 0' 0
Install OFCI ATS lea 0,00 0 0.00 0 0.00 0 0
Install OFCl generator lea 0.00 0 0.00 0, 0.00 0 0
tie into shelter panel 1 eo 0.00 0 0,00 0' 0.00 0 ~I
I demo existing mise electrical 8 hr 0.00 0' 0,00 0 0.00 0
G roundina 1 sic 0,00 0 0,00 0 8451.00 8451 8,45~1 seahurst
0.00 grounding labor complete 48 hr 0,00 0 0,00 0 0.00 0 110,00
18.00!ground rods 23 ea ! 0.00 0 0.00 0 0,00 0 0' 18.00
1.00igroUnd wire 400 If 0.00 0' 0.00 0, 000 0 ~I 1.00
7.50 cadwelds 36 ea 0,00 0; 0.00 0 0.00 0 7.50
15.00 mechanical connections 18 ea 0.00 0 000 0 0,00 0 0 15.00
350.00 test wells 2 eo 0.00 0 0,00 0 0,00 0 0 350.00
0.00 misc grounding @ interior hr 000 0 0,00 0 0,00 0 0 0.00
300.00 install OFCI RF entry port grounding 1 Is 0,00 0 0,00 0 0.00 0 0 300.00
0_00. electrician MU on materials 30% 0,00 0' 0.00 0 0.00 0 0 0.00
33,727 76,611 157,160 267,498
Labor Adjustment 194.62% 24,844 0 0 24,844
Labor Taxes 32.71% 19,159 0 0 19,159
Total Labor, Material, & Sub 77,730 76,611 157,160 311,501
Overhead & Fee 13.50% 42,053
Sub Total 353,554
B&O, & Insurance 2.59% 9,157
Sub Total 362,711
Credit for Work Not Required in CE13 -14,190
Change Estimate 348,521
WSST 8.40% 29,276
Total With WSST $377,796