HomeMy WebLinkAboutCONSENT Hadlock Wastewater Change Order 6 Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Josh Peters, County Administrator
From: Eric Kuzma, Public Works Director
Agenda Date: Febraruay 2, 2026
Subject: Change Order No. 6, Ovivo USA, LLC
Port Hadlock Wastewater Project
Statement of Issue: Execution of Change Order No. 6 to the contract with Ovivo USA,
LLC for supply of the Membrane Bioreactor (MBR) wastewater treatment plant
equipment for Port Hadlock.
Analysis/Strategic Goals/Pro's Et Con's: Change Order No. 6 is a $24,530.00 (plus
9.2% WSST) increase to the Ovivo contract. The proposed change to the contract
includes 1) Ovivo engineering and drafting time for changes made to Change Order
No. 2; and 2) additional materials which were not included in Change Order No. 2.
Change Order No. 2, was executed on 10/16/2023 and added a new master control
panel to incorporate the Ovivo system and the non-Ovivo system controls.
Programming and integrating controls for non-Ovivo equipment were not included in
the original design.
Fiscal Impact/Cost Benefit Analysis: Change Order No. 6 adds $24,530.00 (plus 9.2%
WSST) to the total contract price. The contract increases from $1,790,805.35 (plus
WSST) to $1,815,335.35 (plus WSST). The project is funded at 100% by the
Department of Commerce through the American Rescue Plan Act, State and Local
Fiscal Reovery Funds.
Recommendation: Public Works recommends that the Board sign Change Order No. 6
where indicated and return signed change order to Public Works for further
processing.
Department Contact: Samantha Harper, P.E., (360) 385-9175.
Reviewed By:
f
; 7
Peters, County Administrator Date
CHANGE ORDER NO.:6
Owner: Jefferson County Owner's Project No.: 405-21140
Engineer: Tetra Tech Engineer's Project No.:N/A
Contractor: Ovivo USA,LLC Contractor's Project No.:
Project: Port Hadlock Wastewater
Contract Name: Port Hadlock Wastewater
Effective Date of Change Order: Upon Execution
Date Issued: 01/16/2026 by all parties
The Contract is modified as follows upon execution of this Change Order:
Description:
Ovivo added scope to the changes made in Change Order 02, executed 10/16/2023 which included
changes to the main plant control panel and additional marshaling panels. This change incorporates
additional changes to the scope of Change Order 02 and also includes engineering and draft time for
Ovivo staff.
Attachments:
Ovivo Change Proposal ECN 12 for Plant Control Panel Design Changes to Port Hadlock.
Change in Contract Price Change In Contract Times
Original Contract Price: Original Contract Times:
Substantial Completion. Per Article 2.02(Original
Contract)
$ 1,395,158.00(plus WSST) Ready for final payment: Per Article 2.02(Original
Contract)
Increase from previously approved Change Orders Nos. Increase from previously approved Change Orders
1-5: No.l to No.1:
Substantial Completion: N/A
$ 395,647.35(plus WSST) Ready for final payment: N/A
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: N/A
$ 1,790,805.35(plus WSST) Ready for final payment: Per Payment Schedule in
Change Order 2
Proposal,pp.5-6.
Increase this Change Order: [Increase][Decrease]this Change Order:
Substantial Completion: N/A
$ 24,530.00(plus 9.2%WSST) Ready for final payment:
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial Completion: Per Article 2.02(Original
Contract)
$ 1,815,335.35(plus WSST) Ready for final payment: Per Payment Schedule In
Proposal,p.2.
EJCDC'C-941,Change Order EJCDC•C-941,Change Order,Rev.1.
Copyright°2018 National Society of Professional Engineers,American Council of Engineering Companies
and American Society of Civil Engineers.All rights reserved.
Page 1 of 2
Recommend d.b Engineer(if required) Accepted by Contractor
- :'0%�2 1/26/26 0
Monte Reinders, P.E. Date Eric Schaefer Date
County Engineer Ovivo Project Manager
Authorized by
Greg Brotherton Date
Chair,Jefferson County Board of Commissioners
EJCDC°C-941,Change Order EJCDC°C-941,Change Order,Rev.1.
Copyright°2018 National Society of Professional Engineers,American Council of Engineering Companies
and American Society of Civil Engineers.All rights reserved.
Page 2 of 2
Ovivo SiC Systems ovivo
2300 Greenhill Dr.#100 Worldwide Expert"In Water Treatment
Round Rock,TX 78664
Plant Control Panel Design Changes Port Hadlock
Date Prepared By Services Performed For:
Port Hadlock
Port Hadlock
December 1st, 2025
Proposal Overview
I,,ut{;c orti,,t (I,,(,,,f c(I
inform loon liH 111110c1 ill
,, I II u` ,),%Ivo in(um (I ic1c11tiIm.a1 IM.1, f( rh,uir ,
,)cl(lis.on II cir IWirIf'. 1111 k,,rc III tint (IIVti iiI), II.
1
a
t, ,,
. Ilr.. .
e. .
'40i .1., ,
• 4
"jmrSsI .
`` �•
- —
• ec
s rrw.
-
Project Change Notice(ECN 12)for Port Hadlock
1
Purchase Price
r,:,:10'I ui
1 Material Costs $13,979.16
2 Drafting $2,907.71
3 Electrical Engineering $7,643.13
Total: $24,530.00
Payment Schedule
Pricing and Commercial Terms
k •'iir
•
drib 404 bk..
I
F
+
•'
h' '1.f
•
Project Change Notice(ECN 12)for Port Hadlock
2
Warranty
General Notes
Proprietary and Confidential Information
part in olhe,
";ot to copy in wholi‘
;re purpo.c sttterl hr,!ciu,
foregoing dpplic,,Without fimitatr
subrnis�ir�i! and the !ecipient dclolow!
Vinci a!! dn;ipn, rrrunuf,!cl In ing, I i1pror'''
i ;,
o.
!1
• - ii
.ca :� e
! r"
ry _
t.
sue. «• .
Project Change Notice(ECN 12) for Port Hadlock
3
Approval and Acceptance
Port Hadlock Ovivo Project Manager
c1117..-er— CtIl.G. a142464.2
( (2:4 (2-'(10
4 R
.1 •
A
tb-
ry
4 R i•.0 , .. m
f.
S
11 'lc
a
Project Change Notice(ECN 12)for Port Hadlock
4