Jefferson County
Board of Commissioners
Agenda Request
From:
Board of Commissioners
Philip Morley, County Administrator
Frank Gifford, Public Works Director ::1.RJ
To:
Agenda Date:
February 7, 2011
Subject:
Local Agency Agreement Supplement with the Washington State
Department of Transportation (WSDOT), Upper Hoh Road
Emergency Repair, M.P. 4.0, X01736, Federal Aid Project No. ER-
0701 (051)
Statement of Issue: The attached Local Agency Agreement Supplement with
(WSDOT) is necessary in order to proceed with completion of the Upper Hoh Road,
M.P. 4.0 emergency repair project.
Analysis/Strategic GoalslPro's El: Con's: Emergency repairs were completed at Upper
Hoh Road MP 4.0 in March, 2007, with construction of 400 lineal feet of armored bank
protection. Remaining work consists of mitigation as required by the Washington
State Dept. of Fish El: Wildlife (WDFW). Mitigation will be satisfied by replacing the
fish-passage barrier culvert at Dismal Creek, Upper Hoh Road MP 9.19, with a 3-sided
concrete box culvert. A Local Agency Agreement Supplement is necessary in order to
fund the construction and construction inspection.
Fiscal Impact/Cost Benefit Analysis: This supplement is for $828,000 for construction
and construction inspection. The total estimated cost of the mitigation work is
$998,000. This will be funded at 86.5% by the Federal Highway Administration, and
13.5% by County road funds.
Recommendation: The Board is requested to sign the Local Agency Agreement, and
return to Public Works.
Department Contact: Monte Reinders, County Engineer, 385-9242.