STATE OF WASHINGTON
COUNTY OF JEFFERSON
In the Matter of:
x
Resolution No. 05-11
Updating Right-of-Way Acquisition Procedures x
and appointing staff responsible for x
the various elements of the right-of-way x
acquisition process, replacing x
Jefferson County Resolution No. 84-99. x
WHEREAS, Jefferson County, desires to acquire real property in accordance with the State
Uniform Relocation Assistance and Real Property Acquisition Act (Ch. 8.26 RCW) and State
Regulations (Ch. 468-100 WAC) and applicable Federal Regulations, and
WHEREAS, the Jefferson County Department of Public Works is responsible for the real
property acquisition and relocation activities on projects involving County Road rights-of-way
and other County projects, administered by Jefferson County, and
WHEREAS. to fulfill the above requirements, the Jefferson County Department of Public
Works will acquire rights-of-way and real property in accordance with the policies set forth in
the Washington State Department of Transportation (WSDOT) Right of Way Manual (M26-
01) and Local Agency Guidelines Manual (M 36-63.08), and
WHEREAS, the following Right-of-Way Acquisition Procedures and the appointment of
personnel responsible for the various elements of the right of way acquisition process
replaces Jefferson County Resolution No.27-79 & No.84-99,
NOW, THEREFORE BE IT RESOLVED by the Board of Jefferson County Commissioners
that the County adopt the following Right-of-Way Acquisition Procedures, for the acquisition
of real property:
1. Jefferson County has the following expertise and personnel capable to accomplish
these functions:
A. Proaram Administration -
Public Works Director/County Engineer
Project Managers
B. Appraisal-
Contract Fee Appraiser or qualified agency selected in consultation
with, and approved by WSDOT
C. Aopraisal Review-
Contract Fee Appraiser or qualified agency selected in consultation
with, and approved by WSDOT
D. Acauisition Neaotiator-
Project Managers
Right of Way Representative
Page 1 of4
E. Relocation-
Contract with WSDOT or other qualified Consultant selected in
consultation with and approved by WSDOT
F. Prooertv Manaaement-
Public Works Director/County Engineer
Project Managers
Right of Way Representative
2. Jefferson County desiring to acquire Real Property according to 23 CFR, Part
635, Subpart C and State directives and desiring to take advantage of the
$25,000.00 appraisal waiver process approved by the Federal Highway
Administration for Washington State, hereby agrees to follow the procedure approved
for the Washington State Department of Transportation as follows:
RULES
A. The Jefferson County Department of Public Works (Agency) may elect to
waive the requirement for an appraisal if the acquisition is simple and the
compensation estimate indicated on the Project Funding Estimate (PFE) is
$25,000.00 or less including cost-to cure items.
B. The Agency must make the property owner(s) aware that an appraisal has not
been done on the property and that one will be completed if they desire.
C. Special care should be taken in the preparation of the waiver. As no review is
mandated, the preparer needs to assure that the compensation is fair and
that all the calculations are correct.
PROCEDURES
A. An Administrative Offer Summary (AOS) is prepared using data from the
PFE.
B. The AOS is submitted to the Director of Public Works or their designated
representative for approval.
C. The Director signs the AOS authorizing a first offer to the property owner(s).
3. Just Compensation includes amounts for the value of the lands and improvements
acquired for the project, uneconomic remnants, damages, and deductions for special
benefIts as established through the Authorization and Concurrence by the Board of
County Commissioners.
4. Administrative Settlements may be required, in addition to Just Compensation in
order to acquire needed rights-of-way. Administrative Settlements can help mitigate
or eliminate costly condemnation litigation and project construction schedule delays.
The Project Parcel Negotiation Diary shall contain rationale, justification and/or
documentation for the Settlement Offer. The authority granted to County officials to
provide Administrative Settlement Offers is as follows:
A. Acauisitlon Neaotiator
A counter-offer of Just Compensation plus an Administrative
Settlement not to exceed 20% of the Just Compensation value.
Page 2 of4
B. Proiect Manaaer
A counter-offer of Just Compensation plus an Administrative
Settlement not to exceed 30% of the Just Compensation value.
C. Public Works Director/County Enaineer
A counter-offer of Just Compensation plus an Administrative
Settlement not to exceed 50% of the Just Compensation value.
D. Jefferson County Board of County Commissioners
A counter-offer of Just Compensation plus an Administrative
Settlement exceeding 50% of the Just Compensation value.
5. All projects shall be available for review by the Federal Highway Administration
. and the state of Washington at any time. All project documents shall be retained
and available for Inspection during the plan development, right of way acquisition and
construction stages and for a. three (3) year period following acceptance of the
projects by WSDOT.
6. WSDOT approval of Jefferson County's procedures, contained herein, may be
rescinded at any time should Jefferson County be found to no longer have qualified
staff or is found to be in non-compllance with applicable Washington State
Department of Transportation regulations. The rescission may be applied to all or
part of the functions approved.
Page 3 of4
. ~ ~
~?~~VEDthis~claYOf . ~i~~,"---,2011.
. . . JEFFERSON COUNTY
BOARD 0 .OMMISSJONERS
,
$
,
./
Lorna Delaney
Clerk oUhe Boarc:I
JEFFERSON COUNTY
DE~... 'TM.' .. ..F BLI.C WORKS
. d~~ (; VC
FrankGlffo.rcl
PubDcWorks D
..,/ia/lI
Date
, ..,
. . APPROVED AS TO FORM:
Jefferson CountY .
...~4~~Attome~
... . ... ...... ........a .. .i
1-/ g...2PU
. Date ..
Acknowledged by:
Washington State Department of
Tram;portatlon Representative
Date
Plige4of4 ..