HomeMy WebLinkAboutBLD2008-00099 Mitigation • •
JUL 21 2009
Wei Zhou
Mitigation and Monitoring Plan
Addendum to Mitigation Plan (Jan 09)
Parcel # 961 500 101
MLA#0800123
June 2009
Prepared for:
Wei Zhou
200 Kincaid
Port Hadlock, WA 98339
v✓
' 0 ymplc am ' esources, Inc.
M1 w 856 50th Street
Port Townsend, Washington 98368
360 385-6432
dixiellewellin@yahoo.com
•
Wei Zhou
Mitigation And Monitoring Plan
Addendum to Mitigation Plan (Jan 09)
Parcel # 961 500 101
June 2009
Table of Contents
Introduction
Project Goals and Objectives
Best Management Practices
Revegetation
Installation
Maintenance and Weed Control
Irrigation
Monitoring Plan
Monitoring Methodology
Monitoring and Maintenance Schedule
Determining Survival Rates
Performance Standards
Contingency Plans
Summary
Appendices
Sheet #1 Site Plan and Buffer Impacts
Sheet #2 Mitigation Plan
•
Wei Zhou
Mitigation and Monitoring Plan
Parcel# 961 500 101
MLA# 0800123
June 2009
RE: Addendum to Mitigation Plan
Introduction
This addendum to the original Wei Zhou Mitigation Plan (submitted in January 2009) addresses the
redesigns of the home site which will now have permanent buffer impacts. The building site is defined
by installed septic, a redesigned septic reserve, and is between two wetland buffers. The high quality
wetland (Wetland A) and buffer will not be impacted. The smaller wetland(Wetland B) will need to
have a buffer reduction from 50 feet to 35 feet since there are NO available alternatives. The 20' by
28' two story home will permanently impact 900 sq. ft. of buffer(-15' X 60'). To mitigate for this
buffer loss over 900 sq.ft. replanted with appropriate native trees and shrubs. The driveway will be
adjacent and outside the buffer of Wetland B and therefore will have minimal impacts.
As defined in the original mitigation plan the project will meet the standards outlined in the
Department of Ecology,Guidance on Wetland Mitigation in the State of Washington State (March
2006). A required maintenance and monitoring component has been added to this project.
A map in the Appendix shows the proposed building envelope,trees that need to be removed, and the
impacted buffer area(Sheet#1, Site Impacts). The Mitigation Plan(Sheet#2) includes home site
location, and replanting zones which will be planted when all grading is complete. The updated plant
and landscape specifications are also included in the Appendix.
Project Goals and Objectives
• to avoid any impacts to Wetland A and;
• to reduced buffer of Wetland B by from 50 feet to 35 feet from the back property
boundary for 70 feet (approximately 900 sq. ft. reduction, see Sheet#1);
• to fence the new buffer boundary prior to site clearing and with permanent fencing when
home is complete;
• to maintain original contours and revegetate buffer impacts with a dense planting of
native species (Sheet#2), and;
• to control the small populations of non native species which include reed canarygrass
and thistle, and;
• to provide protective measures during the construction process to minimize impacts to
wetlands or buffers (BMP's during and after construction, outlined below), and ;
• to guarantee the success of the project through maintenance and monitoring for a period
of 5 (five) years.
Wei Zhou Mitigation and Monitoring Plan 1 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 June 2009
• • •
Best Management Practices (BMP's)
Prior to any clearing or excavating the construction boundaries should be clearly marked with silt
fencing to prevent sediment passage or impacts to additional portions the wetland buffer. Excavated
soils will be stockpiled outside of all wetlands or wetland buffers.
BMP's are those practices as defined by the Jefferson County, State of Washington Department of
Agriculture, State of Washington Department of Ecology, State of Washington Department of Fish and
Wildlife, conservation district, and other professional organizations.
These Conservation Practices will be implemented at all times during and after construction.
1. Avoid or control soil loss and protect water quality from degradation caused by nutrients,
animal waste, toxins, and sediment; and
2. Avoid or minimize adverse impacts to surface water and ground water flow, and circulation
patterns; and
3. Avoid or control the movement of sediment and erosion control caused by land alteration
activities. It is recommended that the project to be conducted during dry weather to
minimize runoff. All soils should be stabilized with straw and re-seeded; and;
4. Avoid or minimize adverse impacts to the chemical, physical, and biological characteristics
of critical areas; and
5. No fertilizers, pesticides, or other lawn chemicals will be applied to the yard or adjacent
buffer vegetation.
6. A silt fence should be installed to guarantee that no sediments enter the wetland during
construction.
Revegetation
Final location of recommended plant species should be determined after final grading and construction
is complete. It should be noted that a mature cedar and fir(26"dbh and 24"dbh) are adjacent to the
building site and should be retained. These trees should be clearly marked as DO NOT CUT prior to
clearing for the home site. Several mature trees will need to be removed during clearing as indicated
on the Site Impact Map.
The Mitigation Plan includes planting zones and Landscape Specifications. The Landscape
Specifications includes size, quantity, and spacing for each species recommended for this project.
These native trees and shrubs should thrive at this site since soils have had minimal disturbance and
will be shaded and protected by the adjacent forest. Soils may need to be amended additional compost
for the success of planted species. Since deer frequently graze this area plants may require either
planting tubes or fencing. A total of 15 trees and 20 shrubs are included in this enhancement plan
which includes red cedar, Douglas fir, aspen, red osier dogwood, ninebark, and hazelnut.
Installation
All plant material should come from plants grown in containers as specified. It is desirable to
obtain plants that are adapted to this region and propagated in local nurseries. If bare root
plants are substituted the total number should be at least 25%higher than in the Landscape
Plan due to lower survival rate.
Wei Zhou Mitigation and Monitoring Plan 2 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 June 2009
. •
Nursery specimens should be planted in dense groupings. In general, trees should be planted
8 to 10 feet apart and shrubs 3 to 5 feet apart. Native plant design encourages grouping of
species in clusters to mimic the natural surroundings, however for easy maintenance species
could be planted in rows or grids. Installing mulch circles (bark,wood chips, compost) to 3"
deep and a minimum of 3 feet in diameter around each tree and shrub is highly recommended.
Mulch circles help woody specimens become established by preserving moisture and reducing
competition for nutrients from weeds and grasses. Success rates of a restoration project are
greatly improved when commercial tree protectors are used on newly planted trees and shrubs.
With this added protection mortality is reduced during weeding and deer grazing.
Maintenance and Weed Control
The use of appropriate native species ensures that ongoing maintenance is minimized over
time. All new plantings must become established to successfully out-compete weeds. This
will require at least 3 years of maintenance and weeding. In the years following the initial
planting adding layering additional mulch around the plants will minimize weeds as well as
enrich the soils.
Irrigation
Irrigation may be required for the success of planted species through the dry summer months. In
the low-lying areas of the site hydrology may be present year-round. If the planted species
appear to be stressed in the summer months they must be irrigated. Trees and shrubs require a
minimum of 1 inch of water per week or 2 inches every two weeks from July thorough
September.
Monitoring Plan
Monitoring Methodology
As required by Jefferson County monitoring is required when wetland or wetland buffers are
permanently impacted. Ongoing annual monitoring will be conducted for 5 years by a professional
biologist. All years will require a report submitted to Jefferson County Department of Community
Development. After the report is submitted, the site may be inspected by the wetland specialist of
Jefferson County Department of Community Development.
This monitoring will occur during the growing season in late June or early July and will contain a
general description of the site and condition of the planted areas. Photopoints will be established to
evaluate ongoing success of the re-vegetation project. The report will include the number of species
planted, mortality, and undesirable weed infestations. Unhealthy or dead plants that should be replaced
and invasive weeds removed.
The monitoring should begin as soon as the home has been built and the re-vegetation project is
complete. The report will include the final location of tree and shrub species, and photopoint locations
with photographs.
Wei Zhou Mitigation and Monitoring Plan 3 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 June 2009
• • ,
Monitoring and Maintenance Schedule
Finished project Year 1 Year 2 Year 3 Year 4 Year 5
Maintenance
Planting
Maintenance
Irrigation
Replace plants as needed
Monitoring
Vegetation and Habitat
Photopoint
Annual Report
Determining Survival Rates
A monitoring form will be used to determine plant survivorship, species density, and general condition
of planted species. This information will determine whether plant survivorship and percent cover
provided are sufficient to meet the performance standards.
Performance Standards
Monitoring will determine whether the performance standards outlined below are met. The proposed
length of time for mitigation compliance is five years. This time period will allow for the planted and
volunteer species to become established. Enhancement will be considered successful if the buffer
plantings meet the following criteria:
• Survivorship of installed tree and shrub species is expected to be 100%after the first growing
season. All plants that do not survive the first year should be replanted.
• Survivorship of installed tree and shrub species is expected to be 80% from year 2 through year
5. Species will be replanted until the monitoring period is complete.
• The wetland buffer mitigation is considered successful if 80% or greater of desirable cover is
achieved and the plants are healthy and vigorous during the fifth year of monitoring. Desirable
species include volunteer native trees and shrubs.
• No more than 10% invasive species should be present at any time during the monitoring
process. Non-desirable species include Scots' broom, reed canarygrass, poison hemlock,
thistle, (both Canadian and bull), and Himalayan blackberry.
Contingency Plans
The purpose of the contingency plan is to evaluate available alternatives if monitoring indicates that the
project goal and objectives have not been achieved. Contingency plans will vary depending upon
which goals have not been met and will apply to each specific mitigation activity. Appropriate
corrective action will be recommended after the first year of the monitoring process and will include
the following:
• replanting of any dead vegetation in the first year and additional replanting if density goals are
not met over the following four years;
Wei Zhou Mitigation and Monitoring Plan 4 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 June 2009
• •
• increased maintenance, which may include additional watering and/or weeding;
Summary
The Zhou single family residence will fall within a wetland buffer and will require a permanent buffer
reduction from 50 feet to 35 feet(approximately 900 sq.ft.). This Mitigation and Monitoring Plan
addresses construction impacts and buffer losses by re-vegetating the buffer with native trees and
shrubs after the final grading and construction are complete. Native trees and shrubs will be planted
within specific zones according to wetland tolerance. A short fence will be built to define the new
buffer edge. If the plan is followed as outlined the functions and values of wetland buffers will be
enhanced over time.
A final building inspection to verify compliance of this mitigation plan should be required prior to an
occupancy permit. The final authority over this Mitigation and Monitoring Plan rests with the
Jefferson County Department of Community Development. If there are further planning requirements
or adjustment do not hesitate to call.
I
Dixie Llewellin
Principal Biologist, Olympic Wetland Resources
Certified for Wetland Delineation, 1987 Manual WTI, June 1995
DOE Rating Certified 2007, Mitigation Manual Certified 2008
Wei Zhou Mitigation and Monitoring Plan 5 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 June 2009
• • � ! •
0
0
1
U 2cT
� �y •� ,
i. ✓ F+-1
r •
ii
a~°'.
i
O
M
O o o
00
hi as OO
— v aCti
s.- i
= v (I.)
En
a)
oo
x = p;
W
oo
M
Q\ M
.
Gj r Q `— .
Q I
E . 0 = clCA
—
. tiH Nix
00
o •�,, 0 ►�'(►D
I—
Q g Q [� � j$( W W
2 o .....
cc
N co
tua o E Igtgyp( .
V ,
N O
•
V O _
I
S3 C N �' ______---9----- -----
.[ �._
CA a� 1CD'CT CO
L-.-rr �
.,. LA, cz,Lc> ,I., . ........ s-. 1 ,..±-....( -0
l
0 •
0 � x .0ia
N Ca. ' U ei a
a.;
� � as
° b
O rx ✓a
ti
y
I
III •
O i._ r. N r. N .. r.
Q
O
-,.--Z ,SIP. .--I Yl h Yl ^ \O s•D 00 ry tin
�1
cT 1
s
•
h
U 4•.4 N Q
` - I. C
•
'vl 'vl t 0 'C
a •
GO b e o c vl N 0 1.7 �:
` F"' ��� c__mac (� ,,����•
a �,
is istu)is p" c ......•N CD I _ N N N N N oo w Z
d L
Ir.
i /
en ' s c�i 3 c
O Oh Oo c 0. I.
0 d
U isc. -8 y OA V y
Q Q rx GG - L!'. 00
c0 ccs
d C'
CIS
I 41 CO .y t
a ID
c v
l g E o F.00 e
0o M fr o ' ' 2 ,, c
3 ti
o o A,
N Iy'i . 0. fY `ri c..) c.) •
0.., o V \
0 � � � c
� �
Nix ---
A
as bD tip
'. O � o — ,SZ
' jillt‘,L: _<i>,::',,:•-.12:1:i'' _iniim;iiiii.;,./.,lir---11.i..,,,,,,,C)(N /.. '
Ca
OD _—==__--- -------- ---- 74
co -
a 1
E co
T dcD.<7) __-------- i
_ 1-,
RN, CI) V ,. ,a)
Ct i
� -c
Q U �1 0 � b o
bA CV 'b N a.)
rx C wGQ
� e 023
o ¢ N
0
0 .
/vtt Wetland B
0
r
Wei Zhou
Mitigation Plan
Parcel # 961 500 101
MLA#0800123
January 2009
MAR 1 8 SE
Prepared for:
Wei Zhou
200 Kincaid
Port Hadlock, WA 98339
\Y11
\ .J j
Olympic Wetland Resources, Inc.
856 50th. Street
Port Townsend, Washington 98368
360 385-6432
dixiellewellin( yahoo.com
Wei Zhou
Mitigation Plan
Parcel # 961 500 101
January 2009
Table of Contents
Introduction
Project Proposal
Mitigation Plan
Existing Conditions
Project Goals and Objectives
Best Management Practices
Revegetation
Installation
Maintenance and Weed Control
Irrigation
Summary
Appendices
Sheet #1 Site Plan and Buffer Impacts
Sheet #2 Mitigation Plan
Plant List and Landscape Specifications
Installation Specifications and Recommendation
MAR 18MN
•
Wei Zhou
Mitigation Plan
Parcel# 961 500 101
MLA# 0800123
January 2009
Introduction
Two wetlands were identified on the Zhou parcel at 130 Johnson Ave. during a reconnaissance in 1996
and confirmed in February 2008. These wetlands are located along the east and west boundaries of this
- 260' X 100' lot in the Cape George Highlands. Both wetlands were categorized as Category III
wetlands during a delineation by Olympic Wetland Resources, Inc (March 2008). Category III
wetlands are assigned 50-foot buffers (Jefferson County UDC January 2001). A mound septic system
was installed between the wetland buffers in 2001 prior to the delineation making a homesite location
outside buffers difficult. The goal of this Mitigation Plan is to locate the optimum location for a
building envelope while protecting the existing critical areas. All efforts have been made to minimize
wetland or wetland buffer impacts.
The wetland on the eastern edge of the parcel (Wetland A) is a high quality system with standing water,
a tangled shrub understory, and a high diversity of woody species. The wetland on the western
property boundary (Wetland B) is a smaller system with degraded buffers. The buffer was altered
during the septic system installation and also significantly impacted during construction of a new home
on the adjacent lot.
The best choice for a building envelope is between the impacted buffer of Wetland B and the existing
septic system mound. To accommodate the construction of the home, a portion of the already impacted
buffer of Wetland B will need to be temporarily altered The building envelope will be outside of
Wetland A and its associated buffer so there will be no impacts to this higher quality wetland.
Project Proposal
A proposed 20' X 62' single family residence and access driveway are proposed on a parcel that has a
septic system and access to the Cape George community water system. The reserve area for the
original septic system was located adjacent to the buffer of Wetland B which left no options for
building anywhere on the parcel. The reserve area has been redesigned by Nathan Cleaver Septic
Design, Inc. (November 2008) to accommodate one small homesite outside of buffers. The simple
rectangular home design will include a garage at the end of the structure. Access to the garage will be
directly from Johnson Ave. making a turnaround unnecessary. The 5-foot setback from the septic and
the 10-foot setback from the drainfield have been calculated into the homesite location.
Approximately 1,500 sq. ft. (100' X 15') of the Wetland B buffer will be impacted during 1 8 2009
excavation and construction of the home. Impacts will be temporary and will be mitigated through this
Wei Zhou Mitigation Plan 1 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 January 2009
•
proposal. After final construction is complete the buffers will be contoured to original slopes and re-
vegetated with native trees and shrubs.
Mitigation Plan
Mitigation requirements have been prepared to meet the standards outlined in the Department of
Ecology, Guidance on Wetland Mitigation in the State of Washington State (March 2006). The Zhou
Mitigation Plan summarizes functions and values of the existing conditions, vegetation for restoration,
and a voluntary maintenance schedule.
The Site Plan showing the installed septic system and redesigned reserve, proposed home location,
setbacks, and impacted buffer area is included in the Appendix (Sheet#1). The Mitigation Plan(Sheet
#2) includes zones and species to be planted after the final grading and construction are complete. The
plant and landscape specifications are also included in the Appendix.
Existing Conditions
The gradually sloping parcel consists of a mix of evergreen and deciduous tree cover with an
understory of upland and water tolerant shrubs. Native species dominate the site with over 20 species
recorded (Wetland Delineation 2008). The herbaceous understory includes sedges, rushes, water
parsley and sword fern with a shrub layer of salmonberry, hardhack, vine maple, Oregon grape, and
huckleberry. The tree layer is dominated by mature cedars and Douglas-fir. Only a few invasive weeds
patches were identified in disturbed soils and include Scot's broom and Himalayan blackberry. The
two wetlands are roughly parallel and fall within distinct swales along the east and west property
boundaries. They drain to the north along roadside ditches and across Johnson Ave.
Project Goals and Objectives
The goals and objectives for the septic site:
• to avoid any impacts to Wetland A and;
• to minimize impacts to the buffer of Wetland B by maintaining original contours and
revegetate buffer impacts (approximately 1,500 sq. ft.) after all grading is complete,
and;
• to increase diversity of plant species and structural layers with a dense planting of native
species, and;
• to control the small populations of non native species which include reed canarygrass
and thistle, and;
• to provide protective measures during the construction process to minimize impacts to
wetlands or buffers (BMP's during and after construction, outlined below), and ;
• to guarantee the success of the project through voluntary maintenance and irrigation of
planted species as needed.
Best Management Practices (BMP's)
Prior to any clearing or excavating the construction boundaries should be clearly marked with silt
fencing to prevent sediment passage or impacts to additional portions the wetland buffer. Excavated
soils will be stockpiled outside of all wetlands or wetland buffers.
MAR 1 8 2009
Wei Zhou Mitigation Plan 2 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 January 2009
•
BMP's are those practices as defined by the Jefferson County, State of Washington Department of
Agriculture, State of Washington Department of Ecology, State of Washington Department of Fish and
Wildlife, conservation district, and other professional organizations.
These Conservation Practices will be implemented at all times during and after construction.
1. Avoid or control soil loss and protect water quality from degradation caused by nutrients,
animal waste, toxins, and sediment; and
2. Avoid or minimize adverse impacts to surface water and ground water flow, and circulation
patterns; and
4 3. Avoid or control the movement of sediment and erosion control caused by land alteration
activities. It is recommended that the project to be conducted during dry weather to
minimize runoff. All soils should be stabilized with straw and re-seeded; and;
4. Avoid or minimize adverse impacts to the chemical, physical, and biological characteristics
of critical areas; and
5. No fertilizers, pesticides, or other lawn chemicals will be applied to the yard or adjacent
buffer vegetation.
6. A silt fence should be installed to guarantee that no sediments enter the wetland during
construction.
Revegetation
Final location of recommended plant species should be determined when final grading and construction
is complete. It should be noted that mature cedars are adjacent to the building site and in the wetland
buffer that could be impacted. During clearing, if possible these cedars should be retained.
The Mitigation Plan includes a list of native trees and shrubs that will be appropriate for this site. Soils
may need to be amended with imported soils and compost for the success of planted species. Success
rates should be high since the newly planted species will be shaded and protected by the surrounding
forest. Since deer grazing may be a problem all plants will require either planting tubes or fences. A
total of 15 trees and 20 shrubs are included in this enhancement plan which includes red cedar,
Douglas fir, aspen, red osier dogwood, ninebark, and hazelnut.
Installation
All plant material should come from plants grown in containers as specified. It is desirable to
obtain plants that are adapted to this region and propagated in local nurseries. If bare root
plants are substituted the total number should be at least 25% higher than in the Landscape
Plan due to lower survival rate.
Nursery specimens should be planted in dense groupings. In general, trees should be planted
8 to 10 feet apart and shrubs 3 to 5 feet apart. Native plant design encourages grouping of
species in clusters to mimic the natural surroundings, however for easy maintenance species
could be planted in rows or grids. Installing mulch circles (bark, wood chips, compost)to 3"
deep and a minimum of 3 feet in diameter around each tree and shrub is highly recommended.
Mulch circles help woody specimens become established by preserving moisture and reducing
competition for nutrients from weeds and grasses. Success rates of a restoration project are
greatly improved when commercial tree protectors are used on newly planted trees and shrubs.
With this added protection mortality is reduced during weeding and deer grazing.
MAR 1 8 2009
Wei Zhou Mitigation Plan 3 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 January 2009
Maintenance and Weed Control
The use of appropriate native species ensures that ongoing maintenance is minimized over
time. All new plantings must become established to successfully out-compete weeds. This
will require at least 3 years of maintenance and weeding. In the years following the initial
planting adding layering additional mulch around the plants will minimize weeds as well as
enrich the soils.
Irrigation
Irrigation may be required for the success of planted species through the dry summer months. In
the low-lying areas of the site hydrology may be present year-round. If the planted species
appear to be stressed in the summer months they must be irrigated. Trees and shrubs require a
minimum of 1 inch of water per week or 2 inches every two weeks from July thorough
September.
Summary
The only feasible building site with the least impacts to the critical areas on the Zhou parcel is between
the installed septic system and directly parallel to the buffer of Wetland B. The site plan has been
designed to have minimal environmental degradation to surrounding critical areas by minimizing
infrastructures and impervious area. The building envelope is sited to avoid impacts to the more
biologically diverse wetland (Wetland A) and its' associated buffers. The only way to accommodate
site excavation and homesite construction will be to temporally impact a linear portion (approximately
1,500 sq.ft.) of the buffer of Wetland B.
This voluntary mitigation plan addresses construction impacts by revegetating the buffer with native
trees and shrubs after the final grading is complete. If the plan is followed as outlined the functions
and values of wetland buffers will be enhanced over time. The final building inspection by Jefferson
County, prior to an occupancy permit should include an inspection and approval of this mitigation plan.
All plants should be installed in zones, which relate to a species water tolerance as described in this
plan.
The final authority over this Wetland Mitigation Plan rests with the Jefferson County Department of
Community Development. If there are further planning requirements or adjustment to this mitigation
plan do not hesitate to call.
Dixie Llewellin
Principal Biologist, Olympic Wetland Resources, Inc.
Certified for Wetland Delineation, 1987 Manual WTI, June 1995
DOE Rating Certified 2007, Mitigation Manual Certified 2008
MAR 1 8 2009
Wei Zhou Mitigation Plan 4 Olympic Wetland Resources,Inc.
Report File Number 2008-0308 January 2009
0 v u a c
y T III
-
O
io Q y u m > > `pro
ON 1:3
® z- C � - (0, CO@ N v., Qi m c L v
ar 3 �.0 3 zE> a ya, cd
a o -J g- o `' c 3- i
Qr W
z0 V.) NJ
W
«r ey ,g v• o o a z
a 0 =
cia
cis
.."' 4r
O
� U O co
lc) 1-,
_ - c
k
U
- = O O i
U ° IS pU N
ac o "CS
o 03 'OvN UI
in• CNI
%
O
s
CA v—I
• 3 QUi U I
�:��\ 1 7 E mw
"CJ :\ \� a` Hh
ice.°' U
v, .� a, 3oa a � �� Wasp Q .�
j tv U ..-r U
v • ct
Ui AvUi Cl,v -a1:3
O
c+-) c
• CT
Q.) N
C.vs Q o
VS+� c CC LC� C.
-o r^
`a'o �- o w w
p V1 H c�r9 C Q1 V cv 'x
. sc �_�'�.' a,
araei-.' Gay
> v r „�� _ a 3 avz
♦ I Q :..�.r•- -�'Et` °
o
b E c
co
17
011
m 1-4no ct
j O ,, =
h
Y, ai oQ u_co .a - ---
— MAR 1 8 2009
3
L
L
w v _ _ _ u 4 c
s
1 c o ▪ w
p .> S
T ; c°n
Tzt .re a: Ep x W
® z pipe, co [y ) _AAA, x0 12 Q _' �-F oo'^F a 1-27
�? um�1 ; v aJ GI•. 1 S a `�0 3 .c z aO U - �- F L /V�I 0 FA 01N Q LZM, Q '� •r. yr �iWC w m r ~•.
3S cz O "' F Z Z -
�F-/ O v g GJ -▪ c O O •• a 4.7 I ,-
U F
r •
o r i 114
� .�
11
N �O Q" pU 11 a h
b
z € s
w Q• •
M x X
co p ° 1
.. . 1__________________:>•,
p W1-4 o o ao
:: y N N7
<
Q
•
o r i • ''•f,I
Q _ \\\\
0 c� O Q\ \\ \ oaw a04i •
Em
ti �' x � • rn oo
o co
\ \\� - . N asoA Ni aN o �\\\\\ i•o Qo f •n oo \ \, �, 00 a X •174 CV
\ Q
x
o
JLICC raj 0 > C7 N
as .o c ••^" I I m
51 Fo 3 n -_�_���-..--rasa-- ---r--- y .n
•a .-1 t cn 92 F--I ..-pp
L; 0
K
CV)
2li
a Zne a z o
030 on N a d ° o
o
k r° o o < �
/ a. 0 v _ N w U C4
b 3 to N 'b CIA
Q,
OD'•••' H 03 c v =
chi v O U u, , '� a
c, UGaoo •w3N � - �
> .o 'Lj v N " p .�� 'o
o n. Z — t °'x MAR 1 8 2009
�
r x '/ �'" wetland B
Wei Zhou Plant List
IIIIIIIIIIIIIIIIIMMlli
Populus tremuloides Aspen 1-2 gal 8 5 1
Psudotsuga menzesii Douglas' fir 1-2 gal 10' 5 2
1Thujaplicata Red cedar 1-2ga1 10' _ 5 1
Total Trees 15
Ribes sanguineum Red-flowering currant 1-2gal 4to 5" 6 2
Corlyus cornuta Hazelnut 1-2gal 4to 5" 6 1
Cornus stolonifera Red-osier dogwood 2gal 5' 8 1
Total Shrubs 20
Total Plants 35
* Plants in Zone 1 have a greater tolerance for water than plants in Zone 2
Legend
Scientific and common names: Scientific name according to Hitchcock and Conquist(1976) Flora of the Pacific Northwest
Size:As typically planted for restoration projects.
Spacing: Recommended spacings.
Quantity: Total number of plants for project.
Native Plant Nurseries
Fourth Corner Nurseries, 3057 E. Bakerview Road Bellingham WA 98226 (360) 734-0079
Sound Native Plants, P.O. Box 7505, Olympia, WA 98507 (360) 943-7026
Woodbrook Nursery, 1620 59th Ave. Gig Harbor WA 98335 (206) 265-6271
MAR 18 2009
Installation Specifications and Recommendations
Fall Installation
Planting should be installed between mid-September and mid-November, unless the new •
plantings can be watered throughout the summer. Plantings installed in the fall generally
outperform those installed in the late winter or spring. Plants put in the ground in the fall
have the advantage of an extended period for root growth before rapid top growth in the
spring. In the fall,the soil is warmer and more aerated than in the spring and most plants
experience active root growth during this time.
The cool, cloudy days and frequent precipitation of fall and winter also provide ideal
transplanting conditions. Until sufficient root systems develop, newly installed plants will
undergo transplanting stress that can be exacerbated by hot sunny days. Fall and winter
weather allows for reduced transpiration and provides ample moisture for the roots while
the plant recovers from transplant shock.
Root Disturbance
Immediately before installation plants with broken, damaged, or twisted roots
must be pruned. Matted or circling roots of containerized plantings must be
pruned or straightened and the sides of the root ball must be roughened from top
to bottom to a depth of approximately half an inch in two to four places.
If circling roots are left, they may eventually girdle the plant as they grow and
thicken in place. If the roots at the edge of the root ball are straightened and
extended,they will have access to a greater volume of soil in the planting hole.
Also, the roughened edges of the root ball will have better contact with the
backfill soil.
Disturbing and removing one-fourth to one-half of the roots in the outer inch of
the root ball will damage only the most sensitive plants; most often,this treatment
actually stimulates increased plant growth.
Plant Depth
The finished height of each plant's root ball will be slightly higher than that of the
surrounding soil. The exception is for sandy soils, in which case the soil heights
will be even. The top of the root ball will not be covered with backfill soil. A
watering basin will be formed around each planting by building a berm of soil at
least 30 inches in diameter.
When planting a container-grown plant, the top of the root ball should npt be
covered with any other soil. Covering the root ball with soil, particularly if it has a
finer texture than the potting or field-growing soil, will generally cause water to
flow around the root ball instead of into it; root balls covered in this way may
receive water only from below. To allow direct wetting of the root ball from
MAR 1 8 2009
1