HomeMy WebLinkAboutCONSENT Resolution Tarboo Creek culvert replacement Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Josh Peters, County Administrator
From: Eric Kuzma, Public Works Director
Agenda Date: March 9, 2026
Subject: Resolution to Create County Project
Tarboo Creek Culverts Replacement Project
Coyle Road MP 1.15 and MP 1.23, County Road No. 403908
Statement of Issue: Create a county project known as the Tarboo Creek Culverts
Replacement Project.
Analysis/Strategic Goals/Pro's Et Con's: The scope of the project is to remove the fish
passage barriers and improve county road infrastructure by replacing the culverts at
Coyle Road MP 1.15 and Coyle Road MP 1.23 with a new bridges or bridge-type
structures. This project is being funded and managed by Northwest Watershed Institute
(NWI). Jefferson County staff will provide design review and coordination, and
assistance with right-of-way acquisition.
Fiscal Impact/Cost Benefit Analysis: The total estimated cost for Jefferson County
design review and coordination, and right-of-way assistance is $26,000. This work will be
funded at 100% by NWI's grant funding from the WDFW/RCO Fish Barrier Removal Board
through a reimbursable agreement between Jefferson County and NWI.
Recommendation: The Board is requested to sign one original of the Resolution to
Create County Project, Tarboo Creek Culverts Replacement Project.
Department Contact: Mark Thurston, P.E. Project Manager, 385-9210.
Reviewed By:
3 LOC,
J. r Peters, County Administrator Date
f
STATE OF WASHINGTON
COUNTY OF JEFFERSON
In the matter of initiating a x
county road project designated as: x RESOLUTION NO.
Tarboo Creek Culverts Replacement Project x
IT IS HEREBY RESOLVED that Coyle Road,County Road No.403908,M.P. 1.15 and M.P. 1.23 be improved
as follows:
Remove the fish passage barriers and improve county road infrastructure by replacing the culverts at
Coyle Road M.P. 1.15 and Coyle Road M.P. 1.23 with new bridges.This design project is being funded
and managed by Northwest Watershed Institute. Jefferson County will provide assistance with design
review and coordination,and right-of-way acquisition,per the table below.
PURPOSE FUNDING
County Tasks Previous Present
Appropriation Appropriation
Northwest Watershed Institute Road Fund Total
(FBRB)*
Preliminary $0 $10,000 $0 $10,000
Engineering
Right of Way $0 $16,000 $0 $16,000
Construction $0
Engineering $0 (future funding application) $0 $0
Construction $0 (future funding application) $0 $0
TOTAL $0 $26,000 $0 $26,000
*Funding for Preliminary Engineering and Right of Way coordination will be through a reimbursable
agreement between Jefferson County and Northwest Watershed Institute.
X This project is included in the officially adopted annual road program as Item No. 27
The project is hereby made a part of the officially adopted annual road program in accordance with
R.C.W. 36.81.130.
IT IS FURTHER RESOLVED that:
The construction is to be accomplished by contract in accordance with R.C.W. 36.77.020 et. seq.
The construction is to be accomplished by County forces in accordance with R.C.W. 36.77.065 and
W.A.C. 136.18.
X Northwest Watershed Institute will design and manage this project and be responsible for contracting and
payment.
PASSED AND ADOPTED THIS DAY OF
JEFFERSON COUNTY
BOARD OF COMMISSIONERS
SEAL:
Heather Dudley-Nollette,District 1
ATTEST:
Heidi Eisenhour,District 2
Carolyn Gallaway,CMC Greg Brotherton,District 3
Clerk of the Board