HomeMy WebLinkAboutWater Reclamation Plant for the Port Hadlock UGA Project Change Order No. 15 - 032326JEFFERSON COUNTY Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change 15 Date: 3/6/2026 CHANGE ORDER order No. Ordered by County Engineer under terms of nXX Article 9 and 11 of the General and Supplemental Conditions ,il,. 2 t Ili 0 Contract No. Change proposed by Contractor To: Interwest Construction Endorsed by: rn Olaf v-rcS k �D1~S a • L � 4575 Fey Rd port Angeles, WA 98363 Contractor Firm Name 3 � � S1 noture �} to Project Title Phase 2 - Water Tkie Consent given by Surety. (when required) Reclamation Facility for By: the PH Sewer Attorney-in%act Date You are ordered to perform the following described work upon receipt of an approved copy of this change order: The changes for this change order are priming of the girts in the MBR building; and upgrading the chemical piping in the them building. All work materials and measurement to be in accordance with the provisions of the standard specifications and special provisions for the type of construction involved. ORIGINAL CURRENT ESTIMATED ESTIMATED CONTRACT CONTRACT NETCHANGE CONTRACT TOTAL AMOUNT (Intl. 9.1% WSST) AMOUNT (Intl. 9.1% WSST) THIS ORDER (Intl. 9.2% WSST) ALTER CHANGE (Intl. 9.1% WSST) $ 10,020,835.00 $ 10,693,241.66 $19,136,04 $ 10,712,377.70 ORIGINAL CURRENT CONTRACTTIME NEW CONTRACT CONTRACTTIME CONTRACTTIME CHANGE(Add/deduct) TIME 502 606 0 606 AVAL RECOMMENDED APPRO A ENDED PProJeU onager Dote County Engineer Dote APPROVAL RECOMMENDED APPROy Engineering Services Manager Date Chair,lefferson County Commissioners Date JEFFERSON COUNTY Contract No. 405-2114-0 Sheet 2 of 2 i DEPARTMENT OF PUBLIC WORKS Date: 3/6/2026! CHANGE ORDER ESTIMATE Change Order No. 115 ESTIMATED ESTIMATED 1 UNIT UNIT QUANTITY AMOUNT MEASURE PRICE CHANGE CHANGE COP No. DESCRIPTION 21.4 Payment for priming grits in the MBR Building LS $13,023.85 1 $13,023.85 Upgrade the chemical piping for the citric acid and sodium hydrochlorite in the chemical 55 building LS $4,500.00 1 $4,500.00 $0.00 I CO 15 Subtotal $17,523.85 i ESTIMATED NET CHANGE SUBTOTAL: $17,523.85 9.2% Sales Tax! $1,612.19 ESTIMATED NET CHANGE TOTAL,; $19,136.04 Jefferson County Board of Commissioners Agenda Request To: Board of Commissioners Josh Peters, County Administrator From: Eric Kuzma, Public Works Director Agenda Date: March 23, 2026 Subject: Change Order No. Port Hadlock UGA, 22-96515-026 Department of Public Works O Consent Agenda Page 1 of 1 15, Phase 2 - Water Reclamation Plant for the Project No. 405-2114-0, Commerce Project No. Statement of Issue: Change Order No. 15 with Interwest Construction of Burlington, Washington. Analysis/Strategic Goals/Pro's Et Con's: This change order modifies and changes the original scope by priming the girts in the MBR building and upgrading the chemical piping for both citric acid and sodium hydrochlorite, located in the chem building. Fiscal Impact/Cost Benefit Analysis: The total amount for Change Order No. 15 is $19,136.04 (includes 9.2% Washington State Sales Tax). The contract amount will increase from $10,693,241.66 to $10,712,377.70. The project is funded at 100% by the Department of Commerce. Recommendation: Public Works recommends that the Board authorize Change Order No. 15 with Interwest Construction, and return one original to Public Works for further processing. Department Contact: Samantha Harper, P.E., Project Manager, 385-9175. Reviewed By: D-�Oi4� 3/18/2026 sh Peters, County Administrator Date