HomeMy WebLinkAboutCONSENT Little Quil bridge replacement - Supp 3 Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Josh Peters, County Administrator
From: Eric Kuzma, Public Works Director/
Agenda Date: June 22, 2026
Subject: Supplemental Agreement No. 3 with Sargent Engineers, Inc. for Little
Quilcene River Bridge Replacement, County Project No. 18020970,
Federal Aid No. BRS-Q161(010)
Statement of Issue: Local Agency Supplemental Agreement No. 3 with Sargent Engineers,
Inc. of Olympia, Washington for the Little Quilcene River Bridge Replacement.
Analysis/Strategic Goals/Pro's Et Con's: The Little Quilcene River Bridge, located at Center
Road MP 14.62, is classified as structurally deficient and has load restrictions for single unit
trucks. Replacement of this bridge is of high importance because Center Road is Jefferson
County's main north-south route for freight mobility and the travelling public. Public Works
was awarded federal funding for bridge replacement in 2021. Sargent Engineers was hired by
Public Works in 2022 for bridge design, and is currently working on PS&E and permitting for
the bridge replacement. This agreement provides for revision and updates to the PSB.E in
order to comply with the recently updated Stormwater Management Manual for Western
Washington, and incorporation of Large Woody Debris project elements that were not
included in the original scope of work. Supplement Agreement No. 3 also extends the
agreement completion date to December 31, 2027.
Fiscal Impact/Cost Benefit Analysis: The cost of this supplement is $75,516, which will
increase the maximum amount payable under this agreement from $535,138 to $610,654.
This will be funded at 100% by FHWA.
Recommendation: Public Works recommends that the Board execute all three originals of
the Supplemental Agreement with Sargent Engineers, Inc., and return two to Public Works for
further processing.
Department Contact: Mark Thurston, P.E., Project Manager, 385-9210.
Reviewed By:
(-- %25\() 67/(6,( -‘
Jos eters, County Administrator Date
CONTRACT REVIEW FORM Clear Form
(INSTRUCTIONS ARE ON THE NEXT PAGE) f�
CONTRACT WITH: Sargent Engineers,Inc. Contract No:f O/O �� D
Contract For: Little Quilcene River Bridge Replacement Term: December 31, 2027 J
COUNTY DEPARTMENT: Public Works
Contact Person: Mark Thurston/Chris Spell
Contact Phone: ext.210/ext.208
Contact email: mthurston@co.jeferson.wa.us/cspall@co.jellerson wa us
AMOUNT: $75,516 PROCESS: — Exempt from Bid Process
Revenue: 18033320.333133.20970 Cooperative Purchase
Expenditure: 18059500.41.000 Competitive Sealed Bid
Matching Funds Required: No Small Works Roster
Sources(s) of Matching Funds Vendor List Bid
Fund # RFP or RFQ
Munis Org/Obj ✓ Other: Consultant Supplemental Agreement
APPROVAL STEPS:
STEP 1: DEPARTMENT CERTIFIES COMPLIANCE WITH JCC 3.55.080 AND CHAPTER 42.23 RCW.
CERTIFIED: ■❑ N/A:a 6/8/2026
Signature Date
STEP 2: DEPARTMENT CERTIFIES THE PERSON PROPOSED FOR CONTRACTING WITH THE
COUNTY (CONTRACTOR) HAS NOT BEEN DEBARRED BY ANY FEDERAL, STATE, OR LOCAL
AGENCY.
CERTIFIED: N/A: 6/8/2026
Signature Date
STE 3: RISK MANAGEMENT REVIEW (will be added electronically through Laserfiche):
Electronically approved by Risk Management on 6/16/2026.
STEP 4• PROSECUTING ATTORNEY REVIEW (will be added electronically through Laserfiche):
Electronically approved as to form by PAO on 6/12/2026.
K at"Supplement Agreement Number 3" indicates Pre-approved by
Phil; no other signature block appears.
STEP 5: DEPARTMENT MAKES REVISIONS & RESUBMITS TO RISK MANAGEMENT AND
PROSECUTING ATTORNEY(IF REQUIRED).
STEP 6: CONTRACTOR SIGNS
STEP 7: SUBMIT TO BOCC FOR APPROVAL
1
.47 Washington State
.I/ Department of Transportation
Supplemental Agreement Organization and Address
Number 3 Sargent Engineers,Inc.
Original Agreement Number 320 Ronlee Ln NW
Olympia,WA 98502
LQBR-2022
Phone: (360) 867-9284
Project Number Execution Date Completion Date
August 15, 2022 December 31, 2027
Project Title New Maximum Amount Payable
Little Quilcene River Bridge Replacement $610,654
Description of Work
Work consists of preparing Large Woody Material design, revised stormwater design, and associated updates
to the Plans, Specifications, and Estimate.
The Local Agency of Jefferson County Public Works
desires to supplement the agreement entered in to with Sargent Engineers, Inc.
and executed on August 15. 2022 and identified as Agreement No. LQRB-2022
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
Preparation of Large Woody Material design, revised stormwater design, and updated Plans, Specifications,
and Estimate as described in Exhibit B.
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read: The completion date is extended to December 31. 2027
III
Section V, PAYMENT, shall be amended as follows:
The cost of this supplement is $75,516 increasing the Maximum Amount Payable to $610,654.
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
spaces below and return to this office for final action.
By: Jessica Soward. Sargent Engineers By:
Cc& ,LctJ
Consultant Signature Approving Authority Signature
Approved as to form only.
PRE-APPROVED CONTRACT 02/28/2023 Date
DOT Form 140-063 Philip C Hunsucker,
Revised 09/2005 Chief Civd Deputy Prosecuting Attorney
Exhibit "A"
Summary of Payments
Original
Subconsultants
Aspect Watershed
Estimated Costs Sargent Consulting Science Clearway Skillings Total
NHR Labor Cost $ 186,403 $ 25,664 $ 39,823 $ 124,100 $ 86,376 $ 462,366
Direct Non-Salary Costs $ 94 $ 20,507 $ 173 $ 30,610 $ 8,564 $ 59,948
Total 1 $ 186,497 $ 46,171 $ 39,996 $ 154,710 $ 94,940 1 $ 522,314
Supplement#1
Subconsultants
Aspect Watershed
Estimated Costs Sargent Consulting Science Clearway Skillings Total
NHR Labor Cost $ - $ - $ - $ - $ 6,849 $ 6,849
Direct Non-Salary Costs $ - $ - $ - $ - $ 105 $ 105
Total 1 $ - $ - $ - $ - $ 6,954 1 $ 6,954
Supplement#2
Subconsultants
Aspect Watershed
Estimated Costs Sargent Consulting Science Clearway Skillings Total
NHR Labor Cost $ - $ - $ - $ - $ 5,870 $ 5,870
Direct Non-Salary Costs $ - $ - $ - $ - $ - $ -
Total 1 $ - $ - $ $ - $ 5,870 1 $ 5,870
Supplement#3
Subconsultants
Aspect Watershed
Estimated Costs Sargent Consulting Science Clearway Skillings Total
NHR Labor Cost $ 19,282 $ - $ 6,496 $ - $ 49,738 $ 75,516
Direct Non-Salary Costs $ - $ - $ - $ - $ - $ -
Total 1 $ 19,282 $ - $ 6,496 $ - $ 49,738 1 $ 75,516
Original + Supplement#1 +Supplement#2 +Supplement#3
Subconsultants
Aspect Watershed
Estimated Costs Sargent Consulting Science Clearway Skillings Total
NHR Labor Cost $ 205,685 $ 25,664 $ 46,319 $ 124,100 $ 148,833 $ 550,601
Direct Non-Salary Costs $ 94 $ 20,507 , $ 173 $ 30,610 $ 8,669 $ 60,053
Total 1 $ 205,779 $ 46,171 $ 46,492 $ 154,710 $ 157,502 1 $ 610,654
ENTExhibit A
Prime Consultant Cost Computations
Little Quilcene River Bridge Replacement
Stormwater Design Update & Large Woody Material Design
Sen. Project Project Design
Principal Engineer Engineer Engineer Task Cost
Total Labor Rate: $249.28 $196.89 $152.43 $112.73
Task 1 -Project Management
Project Coordination 16 $3,989
Task 1 Subtotal 16 0 0 0 $3,989
Task 8-Plans, Specification,and Estimate
8.3 Stormwater Design Update(Performed by Skillings, incl. in subconsultants costs below)
8.4 Plans,Specifications,and Estimate
LWM Details 24 12 $6,554
Updated Plans 16 8 $4,370
Updated Estimate 8 4 $2,185
Updated Specifications 8 4 $2,185
Task 8 Subtotal 0 56 28 0 $15,294
Total Labor Hours 16 56 28 0
Direct Salary $78.50 $62.00 $48.00 $35.50
Overhead (187.56%) $147.23 $116.29 $90.03 $66.58
Profit(30%) $23.55 $18.60 $14.40 $10.65
Total Labor Rate: $249.28 $196.89 $152.43 $112.73
Total Labor Cost $3,989 $11,026 $4,268 $0 $19,282
Direct Costs&Subconsultants
Mileage $0
Task 3-LWM Design (Watershed Science&Engineering) $6,496
Task 8.3-Stormwater Update(Skillings) $49,738
$56,234
Total for Stormwater Design Update & Large Woody Material Design $75,516
Management Reserve Fund $0
Requested Supplement $75,516
Prepared by:JSS Page 1 5/27/2026
40. WATERSHED Estimate of Professional Services
�•� SCIENCE& ENGINEERING
Prepared for: Sargent Engineers
506 2nd Ave,Suite 2700 Project: Little Quilcene
Seattle,WA 98104 LWM Design
Tel.(206)521-3000 Date: April 9,2026
Prepared By: Chris Frei
Hours
TASK DESCRIPTION Prin Sr.Eng.1 Sr.Geom Staff Eng. Jr Eng. Clerical Totals
Final Hydraulic Design
LWM Design(Tasks 1-3) 1 4 16 $3,661
Hydraulic Update(Task 4) 1 4 $854
Update Reporting(Task 5) 1 2 4 $1,332
Admin 2 2 $650
Total Hours and Direct Labor Cost(DL) 2.0 9.0 0.0 24.0 0.0 2.0 1
Labor Rate($/hr)(WSDOT Approved OH 146.882%,30%profit on DL) $245.65 $232.37 $185.90 $155.36 $119 51 $92.52
TOTAL LABOR COST $491 $2,091 $0 $3,729 $0 $1851 $6,496
Direct txpense uetaii
Units Rate Cost
Mileage $0 725 $0
Total $0
Cost Summary
Total Labor $6,496
Total Direct Expenses $0
Total $6,496
jSKILLINGS D 6 $ p 0 6
SUBCONSULTANT COST COMPUTATION—HUMAN HOURS
22067
v
SARGENT ENGINEERS,INC. p 9 p
LITTLE QUILCENE BRIDGE REPLACEMENT 2 o m
m m m m
D 0 = 3
3 m Z Z
Z 3. Z m r7 2
D o m Z ��
22 m m
Gl 7� A -i
m 0
A
TASK# TASK DESCRIPTION
1 2024 SWMMWW Revisions to Stormwater
Prepare 90%plans with preferred option for
runoff treatment BMP and flow control BMP
(up to 5 plan sheets and up to 7 detail
1 sheets). 12 60 70
Prepare 90%Special Provisions for
2 stormwater design. 4 10
Prepare 90%Quantities Notebook and
Engineer's Estimate of Probable Costs to
3 Construct for stormwater design. 4 10
Update final stormwater drainage report
documenting the preferred options for
runoff treatment BMP and flow control BMP.
Update SWPPP and prepare Final
4 Maintenance Plan. 4 40 20
Phone conference with Sargent to discuss
5 90%storm PS&E and comments. 2 2
Incorporate 90%storm PS&E comments,
6 prepare 100%storm PS&E package. 4 10 10
Provide project coordination and QA and QC
7 of deliverables. 4 12 2
HOURS PER DISCIPLINE 4 14 30 130 100 2
Project No.22067
Little Quilcene River
Bridge Replacement
(360) 491-3399 • 5016 Lacey Boulevard SE, Lacey, Washington 98503 • www.skillings.com
jSKILLINGS 0 0 $ n 0 0
SUBCONSULTANT COST COMPUTATION—SUMMARY
22067
SARGENT ENGINEERS,INC.
LITTLE QUILCENE BRIDGE REPLACEMENT
NEGOTIATED HOURLY RATE(NHR):
Classification Man Hours X Rate = Cost
PRINCIPAL.IN•CHARGE 4 X $283.22 = 51,132.88
PROJECT MANAGER 14 x $272.62 = $3.816.67
PROJECT ENGINEER 30 X $230.97 = 56,929.07
ENGINEER 130 x $156.00 = 520,279.82
TECHNICIAN 100 X $172.66 = 517,265.87
PROJECT ADMINISTRATOR 2 x $156.79 = 5313.57
Total Hours= 280 Total NHR•
REIMBURSABLES:
Mileage 0 X $0.725 = $0.00
Miscellaneous Expenses $0.00 X 10% = $0.00
SUB TOTAL Rebnbursables• ' -,
SUBCONSULTANT COST(See Exhibit Ej: _
Geotechnical $0.00 X 15% • $0.00
Subconsuttant 1 $0.00 X 10% • $0.00
Subconsuttant 2 $0.00 X 10% • $0.00
Subconsultant 3 50.00 X 10% • $0.00
SUB TOTAL Subconsultants=L 50.00.
MANAGEMENT RESERVE FUND
SUB TOTAL 549,737.88 X 0% • 50.00
GRAND TOTAL
GRAND TOTAL = ( _ $49,737.88
PREPARED BY: Ian Lee,PE DATE: 5/12/2026
REVIEWED BY: Patrick Skillings,PMP DATE: 5/12/2026
Project No.22067
Little Quilcene River
Bridge Replacement
(360) 491-3399 • 5016 Lacey Boulevard SE, Lacey, Washington 98503 • www.skillings.com
Exhibit B
Scope of Work
Little Quilcene River Bridge Replacement:
Stormwater Design Update & Large Woody Material Design
OBJECTIVE
The objective of this supplement is to provide the professional services necessary to provide Large
Woody Material (LWM) design and a revised stormwater design for the replacement of the Little
Quilcene River Bridge in Jefferson County.
The LWM design will provide hydraulic design of two LWM structures in the vicinity of the new bridge to
increase channel stability and habitat. Plans and details will be developed, along with updated cost
estimates,and specifications for the LWM.
The stormwater design revision will provide final design, plans, and specifications for an updated
stormwater system that follows the requirements of the 2024 Stormwater Management Manual for
Western Washington, including preparation of the revised drainage report.
Additionally, the project special provisions and bid items will be updated to the 2026 WSDOT Standard
Specifications.
DURATION
The development of the LWM design, revised stormwater design, and completion of the associated
changes to the PS&E (90%) are anticipated to require approximately six weeks following selection of the
preferred stormwater system concept (redesigned concept being completed under original budget).
Completion of the Final PS&E (100%) is anticipated to take approximately one week following County
review of the 90% PS&E.
SERVICES
The Consultant will perform all services and furnish all materials necessary to accomplish the following
work items:
TASK 1—PROJECT MANAGEMENT(Sargent)
This task includes the additional project management required for the stormwater system revision and
LWM design.
TASK 3-HYDRAULIC ANALYSIS(Watershed Science & Engineering)
This task includes the additional hydraulic engineering services to support the design of LWM associated
with the bridge replacement.
Little Quilcene River Bridge Replacement
Exhibit B Scope of Work Page 1 of 3
The hydraulic design tasks include:
1. Provide design details for LWM components that will be placed on site. Complete design
calculations and determine the location and orientation of each piece and corresponding
ballast/anchoring requirements.
2. Create sketches showing the design and installation requirements for LWM components to be
placed at the site, to be used for preparation of CAD drawings for inclusion in the project plan
set.
3. Prepare specifications for the LWM components.
4. Update the project HEC-RAS 2D hydraulic model to reflect the final crossing design grading,
riprap countermeasures, and LWM, and run the model to evaluate hydraulic conditions,
including 100-year water surface elevation and channel velocities.
5. Update the hydraulic design report to include the final design analysis. The Consultant will
submit a draft of the final report for review. Upon receipt of comments, the Consultant will
prepare a final report.
Deliverable:Updated Draft and Final Hydraulic Report, with WSBIS scour code(PDF electronic file).
TASK 8- PLANS, SPECIFICATION AND ESTIMATE(PS&E)
This task includes the additional engineering services to prepare a revised stormwater design in
accordance with the 2024 Stormwater Management Manual for Western Washington
(SWMMWW), prepare revised stormwater plans and details, prepare LWM plans and details,
and make corresponding updates to the plan set. The project quantities, cost estimate, and
technical specifications will also be updated to include the new design elements, and to
correspond to the 2026 WSDOT Standard Specifications.
8.3 Stormwater Design (Skillings)
Stormwater design for the project previously used the 2019 SWMMWW. Under the 2019
SWMMWW,the project did not trigger evaluation of all minimum requirements, only MR1-5.
This meant that runoff treatment and flow control were not required to be evaluated, and only
implementation of LID BMPs were required to be considered.
County code and NEPA approval requires the use of the latest drainage design manual,which
was released by the Department of Ecology in July 2024. With the current 2024 SWMMWW
manual,the project will trigger evaluation of all minimum requirements (MR1-9), which will
require the evaluation of runoff treatment BMPs and flow control BMPs.
Stormwater design tasks include:
Little Quilcene River Bridge Replacement
Exhibit B Scope of Work Page 2 of 3
1. Update final stormwater drainage report documenting the preferred options
for runoff treatment BMP and flow control BMP. Update SWPPP and prepare
Final Maintenance Plan.
2. Prepare 90% plans with preferred option for runoff treatment BMP and flow
control BMP (up to 5 plan sheets and up to 7 detail sheets).
3. Prepare 90%Special Provisions for stormwater design.
4. Prepare 90%Quantities Notebook and Engineer's Estimate of Probable Costs
to Construct for stormwater design.
5. Incorporate 90%storm PS&E comments, prepare 100%storm PS&E package.
6. Provide project coordination and QA and QC of deliverables.
Deliverable: Preliminary and Final Storm water Drainage Report(PDF electronic file)
Assumptions:
1. Runoff treatment and flow control modeling will use WWHM2012.
2. Runoff treatment BMPs are assumed to be a manufactured treatment device.
8.4 Plans,Specifications and Estimate (Sargent)
The Consultant will prepare updated plans, specifications, and cost estimate for the bridge
replacement to include the LWM details and revised stormwater design.
The Consultant will prepare updated specifications for Division 3 thru 9 of the Special Provisions
using WSDOT General Special Provisions to include the new design elements, and to align with
the 2026 WSDOT Standard Specifications.
The Consultant will provide an updated Engineer's estimate of quantities, construction costs,
and bid items to include the new design elements, and to align with the 2026 WSDOT Standard
Specifications.
Deliverables:
1. 90 Percent PS&E Submittal:
o Updated Drawings—pdf 11x17 electronic file
o Updated Specifications—electronic, word format
o Updated Cost Estimate—electronic, excel spreadsheet format
2. 100 Percent PS&E Submittals:
o Stamped Drawings—pdf 11x17 electronic file, electronic AutoCAD file
o Stamped Specifications (Divisions 3-9)—electronic,word format, and stamped
cover sheet in PDF format
o Cost Estimate—electronic, excel spreadsheet format
o Bid Item List—electronic, excel spreadsheet or word format
Little Quilcene River Bridge Replacement
Exhibit B Scope of Work Page 3 of 3