Department of Public Works
o Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
From:
Board of Commissioners
Philip Morley, County Administrator
Frank Gifford, Public Works Director ,-=fY1
To:
Agenda Date:
May 16, 2011
Subject:
Award of Contract; E. Price St. Improvement Project,
County Project No.CR-1806
Statement of Issue: Award of Contract to Shold Excavating, Inc. of Port Hadlock,
Washington for the above referenced project.
Analysis/Strategic Goals/Pro's 8: Con's: Public Works has completed checking the
bids for the above referenced project, and recommends award of the contract to
Shold Excavating, Inc. for their bid amount of $136,877.15.
Fiscal Impact/Cost Benefit Analysis: Project funding in the amount of $136,877.15
will be from the County Road Fund.
Recommendation: Public Works recommends that the Board authorize the Award of
Contract to Shold Excayating, Inc., and return one (1) copy to Public Works for further
processing.
Department Contact: Monte Reinders, PE, County Engineer, 385-9242.
Reviewed By:
- / ,~/'---:".-",-)
^'.- ," -.. t'
",--(:).;(;:::')C:Z . ", (/
Ptlilip MClrJe~, C9unty.l>,dministrator
\ --,...-~// -,'.-
5~d.I;/
Date
\
Jefferson County
Department of Public Works
623 Sheridan St.
Port Townsend, WA 98368
(360) 385-9160
Frank Gifford, Public Works Director
Monte Reinders, P.E., County Engineer
DATE:
May 6,2011
TO:
Board of County Commissioners
FROM:
Frank Gifford, Public Works Director
SUBJECT:
AWARD OF CONTRACT
E. Price Street Improvement Project
County Project No. CR-1806
County Road No. 667009, MP 0.00 to MP 0.25
· The Call for Bids was issued by the Board of County Commissioners on April 11, 2011.
· Due notice of the Call for Bids was given as required by law.
· Sealed bids were received and opened in public on May 2,2011 at 10:00 a.m. in the Commissioner's
Chambers.
· The Public Works Department has completed checking the bids and has investigated the qualifications
of the lowest bidder.
· Bid tabulations are attached for reference.
The Public Works Department recommends that the construction contract be awarded to the lowest responsive
bidder:
Shold Excavating, Inc. of Port Hadlock, Washington for its bid of$136.877.15.
for the
East Price S1. Improvement Protect. County Proiect No. CR-1806. County Road No. 667009.
MP 0.00 to MP 0.25.
Approved:
John Austin
Chairman, Board of County Commissioners
Date
BID TABULATIONS: E. PRICE ST. IMPROVEMENT PROJECT fFfF)) ~. )
County Project CR-1806 BID OPENING DATE: Monday, May 2, 2011 CONTRACTOR #1 CONTRACTOR #2 CONTRACTOR#3 '- ~O~OI :J4 L CONTRACTOR #5
County Road 667009 BID OPENING TIME: 10:00 A.M. ENGINEER'S ESTIMATE SHOLD EXCAVATING, INC. C&J EXCAVATING, INC. SETON CONSTRUCTION LAKESIDE INDUSTRIES, INC. PACIFIC COAST GENERAL
M.P. 0.00 to M.P. 0.25
ITEM QUANTITY UNIT ITEM DESCRIPTION UNIT TOTAl UNIT TOTAl UNIT TOTAl UNIT TOTAl UNIT TOTAl UNIT TOTAl
NO. BID BID BID BID BID BID BID BID BID BID BID BID
PREPARATION
1 1 L.S. MOBILIZATION $15.751.34 $15,751.34 $13,891.00 $13,891.00 $6,000.00 $6,000.00 $26,400.00 $26,400.00 $7,900.00 $7,900.00 $19,265.00 $19,265.00
2 1 l.S. CLEARING AND GRUBBING $18,000.00 $18,000.00 $8,080.00 $8 080.00 $4,000.00 $4,000.00 $4,085.00 $4,085.00 $10,000.00 $10,000.00 $7,195.00 $7,195.00
3 1 L.S. REMOVAl OF STRUCTURE AND OBSTRUCTION $2,000.00 $2,000.00 $3,840.00 $3.840.00 $1,100.00 $1,100.00 $1,500.00 $1,500.00 $4,875.00 $4,875.00 $1,500.00 $1,500.00
GRADING
4 1,080 CY ROADWAY EXCAVATION INCL. HAUL (INCLUDES PATHWAY) $18.00 $19,440.00 $14.30 $15,444.00 $11.00 $11,880.00 $9.00 $9,720.00 $14.00 $15,120.00 $7.85 $8,478.00
5 365 CY EMBANKMENT COMPACTION $6.00 $2,190.00 $10.00 $3,650.00 $1.00 $365.00 $2.00 $730.00 $2.50 $912.50 $4.51 $1,646.15
DRAINAGE
6 26 LF SCHEDULE-A CULVERT PIPE, 121N. DIAM. $45.00 $1,170.00 $15.00 $390.00 $27.00 $702.00 $25.50 $663.00 $27.00 $702.00 $33.20 $863.20
7 210 LF PERF. CORRUG. POLY. UNDERDRAlN PIPE 121N. DIAMETER $45.00 $9,450.00 $17.00 $3,570.00 $9.00 $1,890.00 $12.50 $2,625.00 $29.00 $6,090.00 $24.00 $5,040.00
8 635 CY INFILTRATION TRENCH $63.48 $40,309.80 $21.85 $13,874.75 $40.00 $25,400.00 $38.00 $24,130.00 $50.00 $31,750.00 $49.21 $31,248.35
9 296 SY SWALE $12.00 $3,552.00 $9.00 $2,664.00 $4.25 $1,258.00 $20.00 $5,920.00 $6.00 $1,776.00 $32.34 $9,572.64
STORM SEWER
10 15 EA CATCH BASIN TYPE 1 P $1,100.00 $16,500.00 $690.00 $10,350.00 $1,225.00 $18,375.00 $850.00 $12,750.00 $1.056.00 $15,840.00 $1,097.00 $16,455.00
SURFACING
11 1.503 TON GRAVEL BORROW $14.00 $21,042.00 $11.00 $16,533.00 $10.25 $15,405.75 $10.00 $15,030.00 $13.50 $20,290.50 $17.73 $26,648.19
12 692 TON CRUSHED SURFACING TOP COURSE $26.00 $17,992.00 $27.00 $18,684.00 $25.00 $17,300.00 $20.00 $13,840.00 $15.95 $11,037.40 $28.10 $19,445.20
13 140 TON TRAIL SURFACING MATERiAl (CUSTOM MIX) $50.00 $7,000.00 $27.00 $3,780.00 $38.00 $5,320.00 $40.00 $5,600.00 $40.00 $5,600.00 $57.93 $8,110.20
EROSION CONTROL AND PLANTING
14 3 DAY ESC LEAD $150.00 $450.00 $50.00 $150.00 $225.00 $675.00 $150.00 $450.00 $100.00 $300.00 $625.00 $1,875.00
15 1 LS SWPP PlAN; CONTRACTOR PREPARED $2,400.00 $2,400.00 $100.00 $100.00 $150,00 $150.00 $500.00 $500.00 $250.00 $250.00 $315.00 $315.00
16 1 LS EROSION-WATER POLLUTION CONTROL $5,700.00 $5,700.00 $500.00 $500.00 $4,500.00 $4,500.00 $1,500.00 $1,500.00 $300.00 $300.00 $8,070.00 $8,070.00
17 0.37 AC SEEDING, FERTILIZING, AND MULCHING $1,500.00 $555.00 $800.00 $296.00 $2,700.00 $999.00 $3,500.00 $1,295.00 $3,000.00 $1,110.00 $2,995.00 $1,108.15
TRAFFIC
18 1 LS OTHER TEMPORARY TRAFFIC CONTROL (DEVICES) $800~00 $800.00 $200.00 $200.00 $350.00 $350.00 $500.00 $500.00 $2,000.00 $2,000.00 $3,250.00 $3,250.00
19 1 LS TRAFFIC CONTROL SUPERVISOR $4,100.00 $4,100.00 $100.00 $100.00 ' $900.00 $900.00 $6,600.00 $6,600.00 $3,000.00 $3,000.00 $5,250.00 $5,250.00
20 240 HR FlAGGERS AND SPOTTERS $55.00 $13,200.00 $40.00 $9,600.00 $56.00 $13,440.00 $55.00 $13,200.00 $47.00 $11,280.00 $47.39 $11,373.60
21 52 SF CONSTRUCTION SIGNS ClASS-A $18.00 $936.00 $18.95 $985.40 $15.00 $780.00 $35.00 $1,820.00 $16.00 $832.00 $18.50 $962.00
OTHER ITEMS
22 95 CY STRUCTURE EXCAVATION ClASS B INCl. HAUL $25.00 $2,375.00 $25.00 $2,375.00 $7.00 $665.00 $12.00 $1,140.00 $16.00 $1,520.00 $9.75 $926.25
23 740 SF SHORING OR EXTRA EXCAVATION CL. B $2.00 $1,480.00 $3.00 $2,220.00 $0.75 $555.00 $1.00 $740.00 $2.50 $1,850.00 $2.30 $1,702.00
24 28 MGAl WATER $50.00 $1,400.00 $50.00 $1,400.00 $42.00 $1,176.00 $50.00 $1,400.00 $20.00 $560.00 $120.00 $3,360.00
25 1 EST ROADSIDE CLEANUP $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00 $1,000.00
26 1 LS TRIMMING AND CLEANUP $1,800.00 $1,800.00 $2,000.00 $2.000.00 $1,800.00 $1,800.00 $2,500.00 $2,500.00 $1,500.00 $1,500.00 $7,860.00 $7,860.00
27 1 EST REIMBURSEMENT FOR THIRD PARTY DAMAGE $500.00 $500.00 $500.00 $500.00 $500.00 $500.00 $500.00 $500.00 $500.00 $500.00 $500.00 $500.00
28 1 LS SPCC PlAN $350.00 $350.00 $100.00 $100.00 $150.00 $150.00 $750.00 $750.00 $250.00 $250.00 $315.00 $315.00
29 60 LF DRAIN PIPE 4-IN. DIAMETER $20.00 $1,200.00 $10.00 $600.00 $22.00 $1,320.00 $15.75 $945.00 $30~OO $1,800.00 $20.65 $1,239.00
CORRECT AMOUNT: $212,643.14 $136,877.15 $137,955.75 $157,833.00 $159,945.40 $204,572.93
.- REPORTED IN BID PACKAGE: N/A OK OK OK OK
P_"'" by Project Maoaaocr:. ~ _~_t7 .%W/ $ Dlff. = $0.78
% Diff. = 0.00% % Diff. = -35.63% % Diff. = -35.12% % Diff. = -25.78% % Diff. = -24.78% % Diff. = -3.80%
~1 - lSate I
ReviewedbyEng.Se<v._ \1 ~ DBE Goal: XXX DBE Goal: N/A DBE Goal: N/A DBE Goal: N/A DBE Goal: N/A DBE Goal: N/A
---- Bond: XXX Bond: YES Bond: YES Bond: YES Bond: YES Bond: YES
;:tI> S"-3-11
""""\ License: XXX license: YES license: YES license: YES license: YES license: YES
-= Jon ~ J Date Addendum's: XXX Addendum's: YES Addendum's: YES Addendum's: YES Addendum's: YES Addendum's:
~byCOwrty~~ /S-:f-// Sign Proposal: XXX Sign Proposal: YES Sign Proposal: YES Sign Proposal: YES Sign Proposal: YES Sign Proposal: YES
Debarred: XXX Debarred: NO Debarred: NO Debarred: NO Debarred: NO Debarred: NO
~te Reinae~...r:::- Date
Printed: 5/312011 ~
10f1