HomeMy WebLinkAboutWashington State Department of Transporation Olympic Discovery Trail - Anderson Lake Connection Project Change Order No. 6 - 100526 1 Washington State� Change Order
Department of Transportation
Contract Number Contract Title Federal Aid Number
18019893 Olympic Discovery Trail- Anderson Lake Connection STBGR•2016(030)
Change Order Number Change Description Date
6 Work at intersection of SR20 and South Discovery Road 9/25/2026
Prime Contractor/Design-Builder
Seton Construction Inc.
✓ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
C Change proposed by Contractor/Design-Builder
Change Description
See attached.
Verbal Approval Given By Verbal Approval Date Working Days 4/-
John Fleming, Jefferson County Public Works 9/25/2026 0
Original Contract Amount Current Contract Amount Est.Net Change is C J. Est.Contract Amount
$3,782,268.93 $4,716,727.81 $34,766.25 $4,751,494.06
Approval Recommended Approved Ap oved
Project Engineer Approving A ority per C.A.Agreement
9/25/2026 9 fr9/Z+t>Qb —_
Date Date
Approval Recommended Other Ap I s quired
ai/9
_ O
By Prime Contractor • n r ate
L au( ACC
Date Representing
WSDOT Form 140-005 Page 1
Revised 04/2015
JEFFERSON COUNTY Contract# 18019893
Sheet 2 of 2 DEPARTMENT OF PUBLIC WORKS
Change
Date: 9/25/2026 CHANGE ORDER ESTIMATE Order No. 6
NEW BID ITEMS-GROUP 1(Trail)
Bid
Item Unit Bid
No. DESCRIPTION Unit Amount Qty Unit Bid Total
GROUP 1(Trail)CO 06 New Bid Item Added Total $0.00
EXISTING BID ITEMS DELETED-GROUP 1(Trail)
Bid
Item Unit Bid
No. DESCRIPTION Unit Amount Qty Unit Bid Total
GROUP 1(Trail)CO 06 Ex.Bid Item Deleted Total $0.00
EXISTING BID ITEMS ADDED-GROUP 1(Trail)
Bid
Item Unit Bid
No. DESCRIPTION Unit Amount Qty Unit Bid Total
GROUP 1(Trail)CO 06 Ex.Bid Item Added Total $0.00
ESTIMATED NET CHANGE GROUP 1(Trail)SUBTOTAL: $0.00
NEW BID ITEMS-GROUP 2(SR-20)
Bid
Item Unit Bid
No. DESCRIPTION Unit Amount Qty Unit Bid Total
Project Temporary Traffic Control-Additional work
4C to accommodate antiquated WSDOT infrastucture LS $ 6,750.00 1 $ 6,750.00
Rectangular Flashing Beacon System-Additional
conduits for new circuits to rectangular rapid
flashing beacon due to existing conduits not having
21C adequate capacity LS $ 25,000.00 1 $ 25,000.00
GROUP 2(SR-20)CO 06 New Item Total $ 31,750.00
EXISTING BID ITEMS DELETED-GROUP 2(SR-20)
Bid
Item Unit Bid
No. DESCRIPTION Unit Amount Qty Unit Bid Total
GROUP 2(SR-20)CO 06 Ex.Bid Item Deleted Total $0.00
EXISTING BID ITEMS ADDED-GROUP 2(SR-20)
Bid
Item Unit Bid
No. DESCRIPTION Unit Amount Qty Unit Bid Total
GROUP 2(SR-20)CO 06 Ex.Bid Item Added Total $0.00
ESTIMATED NET CHANGE GROUP 2(SR-20)SUBTOTAL: $ 31,750.00
9.5%Sales Tax $3,016.25
ESTIMATED NET CHANGE TOTAL: $ 34,766.25
Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Josh Peters, County Administrator
From: Eric Kuzma, Public Works Director
Agenda Date: October 5, 2026
Subject: Change Order No. 6, Olympic Discovery Trail- Anderson Lake Connection
Project, County Project No. 18019893, County Road No. 850200, Federal
Aid Project No. STBGR-2016(030), RCO Project No. 20-1745
Statement of Issue: Change Order No. 6 with Seton Construction for the Olympic Discovery
Trail- Anderson Lake Connection Project, County Project No. 18019893.
Analysis/Strategic Goals/Pro's Et Con's: This project is for construction of a new
approximately 3.2 mile-long segment of the Olympic Discovery Trail between Milo Curry Road
and Anderson Lake State Park. Change Order No. 6 changes the original scope of work to add
alternative electrical conduit for a rectangular rapid flashing beacon, and advanced warning
beacon upon determination that the existing conduits were inadequate.
Fiscal Impact/Cost Benefit Analysis: This change order will increase the current contract
amount by $34,766.25 from $4,716,727.81 to $4,751,494.06 (includes 9.5% WSST on `Group 2'
items). The construction portion of this project is funded with WA State Recreation and
Conservation Office WA Wildlife and Recreation Program- Trails grant (WWRP) and Federal
Highway Administration Surface Transportation Block Grant (STBG). There are sufficient grant
funds to cover this Change Order amount.
Recommendation: Public Works recommends that the Board execute two originals of Change
Order No. 6 with Seton Construction and return one original to Public Works for further
processing.
Department Contact: John Fleming, P.E., Project Manager, 385-9217.
Reviewed By:
[306
Jos eters, County Administrator Date