RESOLUTION NO.
x
IT IS HEREBY RESOLVED that Undie Road, County Road No. 150009, Irom M.P. 0.99 to M.P. 1.15, be
improved as follows:
Acquisition ofa right of way easement adjoining the northerly boundary of the subject roadway for the purpose of
roadway realignment to the north due to the increasing encroachment of the Bogachiel River from the south. The long-
term viability of this local access road\vay has been seriously threatened by recent severe erosion continuing to advance
on the roadway structure. The river has the potential to wash out the County roadway just south of Gov't Lot 7 in Sec.
1, T27N, R 13 W, W.M. This project will provide the necessary right-of-way to be able to react quickly to maintain
public access for residents located easterly of the impacted areas.
IT IS FURTHER RESOLVED that an appropriation from the oftieially adopted road fund budget and based on the
County Engineer's estimate is hereby made in the amounts and for the purpose shown:
PURPOSE
PREVIOUS APPROPRIATION PRESENT APPROPRIATION
Right of Way
Acquisition
$
o
$ 15,000
TOTAL
$
o
$ 15,000
_This project is included in the ofticially adopted annual road program as Item No.
XX The project is hereby made a part of the officially adopted annual road program in accordance with R.C.W.
36.81.130.
PASSED AND ADOPTED THIS 27TH DAY OF June, 2011.
<
JEFFERSON COUNTY
BOARD OF COMMISSIONERS
,~,;~
.
."
.
SEAL: "
.,
t~
"
-.
.,
ATTEST:
David Sul)ivan, JI1ember
/t.......!~
Ii f'i
. ."' ..
~., - .' A_to' . . ,___
PhrrJhhnson, clnber-
/-......
\.i..._
Lorna L. Delaney
Clerk of the Board
,...l"
Undie Road
Realhmment ACQuisition Proiect
June, 2011
r
----
)ForkS
pi"
'fO~
~r
I
'Ii
,
\ A Grader Creek'H.
,
- ,
\..
LDgdosttl
A
u
---
,Reade H.
to
*
~
- -
-~ -
.-.
Bog.chiel
o
Project Site
-- -~ I
I
c
I
I
Department of Public Works
Consent Agenda
Page 1 of 2
Jefferson County
Board of Commissioners
Agenda Request
To:
Board of Commissioners
Philip Morley, County Administrator
From:
Frank Gifford, Public Works Director /;2' ~. I
Agenda Date:
June 27, 2011
Subject:
A Resolution creating a County Road Project
pertaining to the future realignment of Undie Road,
County Road No. 150009.
Statement of Issue:
A request to adopt a Resolution creating a County Road Project to acquire necessary right of
way to realign a portion of the following County Road:
Undie Road No. 150009: Located in Section 1, Township 27 North, Range 13 West, W.M., at
Mile Post 1.0. Situate in Jefferson County, State of Washington.
This project will be added to the 2011 Annual Construction Program.
Analysis/Strategic Goals:
The County Engineer has examined this county road and determined that its current viability
and usefulness is seriously threatened by recent erosion by the activity of the Bogachiel River.
Therefore, in an effort to plan ahead for potential emergency, the Department of Public
Works is seeking to create the above referenced project to acquire additional right of way
necessary to allow the Department to react quickly to repair future damage and maintain
public access for residents lying easterly of the subject site. Upon approval of the attached
resolution, the Department of Public Works will initiate the approved acquisition procedures,
which will include future authorization and concurrence from the Board with respect to the
actual right of way acquisition.
Fiscal Impact:
The 6-Year Transportation Improvement Program contains a programmatic project category,
Countywide Safety Improvements (No. 21), for small projects like this. The estimated cost
for this right of way acquisition project is $15,000.00.
Department of Public Works
Consent Agenda
Page 2 of 2
Department Contact: Monte Reinders, P.E., County Engineer, 385-9242
Recommendation:
The Department of Public Works recommends the Board of County Commissioners adopt the
attached resolution creating the Undie Road Realignment Acquisition Project and adding it to
the 2011 Annual Construction Program.