HomeMy WebLinkAbout090611_ca12
.. '<
Department of Public Works
o Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To:
Board of Commissioners
Philip Morley, County Administrator
From:
Frank Gifford, Public Works Director
Agenda Date:
September 6, 2011
Subject:
Execution of Contract Change Order with Shold Excavating, Inc. for Leland
Valley Road West Flood Fix, County Project No. CR1854,
Statement of Issue:
Execution of the contract change order with Shold Excavating, Inc. for Leland Valley Road
West Flood Fix, County Project No. CR1854.
Analysis/Strategic Goals/Pro's & Con's:
The Change Order No.1 provides for replacing 250 tons of Gravel Borrow with 250 Tons of
Crushed Surfacing Base Course and for adding the placement and removal of a Turbidity
Curtain.
Fiscal Impact/Cost Benefit Analysis:
The cost of the contract change order is $3,400.00. This will be funded at 100% by Jefferson
County roads fund. The original contract amount was $40,464.36
Recommendation:
The attached contract change order is recommended for your execution. The Board is asked
to sign the contract change order where indicated, and return two signed originals to Public
Works (attn. Jon Watson).
Department Contact:
Monte Reinders, P.E., County Engineer 385-9242
j ,
f-h,I({
Date I j
.'~
(""")
t .~.. r-.
,
\ /
I ,
Philip Morfey, Co nty--:6.dministrator