From:
Board of Commissioners
Philip Morley, County Administrator
Frank Gifford, Public Works Director ,'1$
November 21,2011
To:
Agenda Date:
Subject:
Resolution to Create County Project
Snow Creek Road Culvert Replacement, MP 3.78, Project No. CR1899
Statement of Issue: A Resolution is necessary to add this project to the officially
adopted annual road program.
Analysis/Strategic Goals/Pro's & Con's: The culverts at Snow Creek Road Milepost 3.78
are falling and In need of replacement. Public Works applied for a grant for culvert
replacement through the Federal Highway Administration (FHWA) Forest Highway
Program and received 100 percent funding for design and construction. The project will
consist of replacing the existing culverts with a fish-passable culvert or bridge.
Fiscal Impact/Cost Benefit Analysis: The total project cost Is estimated at $458,538
and is funded at 100% by the Federal Highway Administration.
Recommendation: The Board Is requested to sign one original of the Resolution to
Create County Project.
Department Contact: Monte Reinders, County Engineer, 385-9242.
Reviewed By:
1/4~
Date
STATE OF W ASHINOTON
COUNTY OF JEFFERSON
In the matter of:
Creating a County project
designated as CR1899
x
x
x
RESOLUTION NO.
IT IS HEREBY RESOLVED that Snow Creek Road. County Road No. 352909. M.P. 3.78. be improved as follows:
Replace the failing culverts at Milepost 3.78 on the Snow Creek Road with a fish passable culvert or hridge.
IT IS FURTHER RESOLVED that an appropriation from the officiaily adopted road fimd budget and based on the County
Engineer's esthnate is hereby made in the amounts and for the purpose shown:
PURPOSE ROADS APPROPRIATION OTIffiRFUNDINO
Engineering $ 0 $ 115.000 rFHWA)
Right of Way $ 0 $ 0
Construction: $ 0 $ 343.538 (FHWA)
TOTAL $ 0 $ 458.538 (FHWA)
This project is included in the officially adopted annual road program as Item No._.
X The project is bereby made a part of the officially adopted annual road program in accordance with R.C.W. 36.81.130.
IT IS FURTHER RESOLVED that:
X The construction is to be accomplished by contract in accordance with R.C.W. 36.77.020 et. seq.
The construction is to be accomplished by County forces in accordance with R.C.W. 36.77.065 and WAC. 136.18.
PASSED AND ADOPTED TIllS
DAY OF
2011 .
JEFFERSON COUNTY
BOARD OF COMMISSIONERS
John Austin, Chair
Phil Johnson, Member
David W. Sullivan, Member