From: Frank Gifford, Public Works Director -9/y
Agenda Date: August 5, 2013
Subject: Amendment No. 2 to the Federal Highway Administration (FHWA)
Reimbursable Agreement
Snow Creek Road Culvert Replacement, MP 3.78, Project No. CR1899
FHWA Agreement No. DTFH70-1 1 -E-00039
Statement of Issue: The attached Amendment with FHWA is necessary in order to
proceed with construction of the Snow Creek Road Culvert Replacement project.
Analysis /Strategic Goals /Pro's £t Con's: The culverts at Snow Creek Road Milepost 3.78
are failing and in need of replacement. In 2011, Public Works was awarded a grant for
culvert replacement through the Federal Highway Administration (FHWA) Forest Highway
Program. Preliminary engineering for this project is nearing completion. Amendment
No. 2 to the funding agreement will provide the construction funding for installation of a
24 -ft. span, three -sided concrete box culvert.
Fiscal Impact /Cost Benefit Analysis: The current amount obligated under this grant is
$170,000. Amendment No. 2 will add $452,200 for construction funding, bringing the
total obligated amount to $622,200. This project is funded at 100% by the Federal
Highway Administration.
Recommendation: The Board is requested to sign the three originals of the Amendment
and return all three originals to Public Works. After the Amendment has been executed
by FHWA, an original will be returned to the Board.
Department Contact: Mark Thurston, P. E., Project Manager, 385 -9160.
Re e y:
12-
P Morl ) ounty A minist ator
Date
Page 1 of 4
U.S. DEPARTMENT OF TRANSPORTATION AGREEMENT No.
FEDERAL HIGHWAY ADMINISTRATION DTFH70 -11 -E -00039
REIMBURSABLE AGREEMENT Amendment No. 2
PARTIES TO THE AGREEMENT
a. REIMBURSING ORGANIZATION b. ORGANIZATION TO BE REIMBURSED
Federal Highway Administration Jefferson County Public Works
Western Federal Lands Highway Division 623 Sheridan Street
610 East Fifth Street Port Townsend, WA 98368
Vancouver, WA 98661 -3893
a.l APPROPRIATION CHARGEABLE b.l APPROPRIATION REIMBURSED
1517530430001 531.CE.G200.53 1753000000 25304$58,100
1517530430001 531.CN.G200.53 1753000000 25304 $394,100
c. EFFECTIVE DATE:
Original: August 09, 2011
Amend No. 1: January 4, 2013
Amend No. 2: When Fully Executed
d. AMOUNT:
$ 115,000.00 Original
$ 55,000.00 Amend No. 1
$ 452,200.00 Amend No. 2
$ 622,200.00 Amended Total
Agreement Information: WA PFH 430), Snow Creek Road Project
The purpose of this Amendment is to add funds for the Construction and Construction
Administration activities for the above referenced project.
1. Cover Page, Block 5. FUND AMOUNT: The Agreement is hereby increased by $452,200.00 from
$170,000.00 to amended total of $622,200.00 as stated in H. Cost Budget and by reason of this
amendment, as shown by Attachment I, Cost Estimates.
2. FHWA will reimburse Jefferson County for all eligible costs incurred under this Agreement.
The current estimated cost of the work described in this Agreement is $622,200.00. In no
case shall the FHWA and the County exceed this amount without a mutually agreed upon
modification of this Agreement.
3. ALL OTHER PROVISIONS OF THE ORIGINAL AGREEMENT REMAIN THE SAME.
AUTHORIZED APPROVALS
a.3 REIMBURSING ORGANIZATION I b.3 ORGANIZATION TO BE REIMBURSED
SIGNATURE DATE SIGNATURE DATE
y7�Z.r / f.
TITLE !y TITLE
Marlene M. Marcellay, Contracting Officer
Western Federal Lands Highway Division Jefferson County
roved as to form ly
Jcfferson Co. Prosecutor's, Bice
David Alvarez. Chief Ci DPA
SNOW CREEK ROAD CULVERT REPLACEMENT
ATTACHMENT I
7/6/2012
Alternate 1a: Precast Reinforced Concrete Three Sided Box with
Precast Pedestal Footings
ITEM
No
ITEM
APPROX.
QUANTITY
UNIT PRICE
TOTAL
PREPARATION
I
MOBILIZATION
L.S.
$29,852
2
EROSION / WATER POLLUTION CONTROL
L.S.
$10,000
3
-- -- ------
4
--------
CLEARING & GRUBBING
--- - --------------------------- - --- - - - ---- ------- - --------------------------------------
STRUCTURE EXCAVATION CLASS A, INCL. HAUL
-----
403
------
c.y.
L.S.
$45.00
$10,000
$18,135
5
STRUCTURE EXCAVATION CLASS B, INCL. HAUL
396
$15.00
$5,940
6
SHORING & CRIBBING OR EXTRA EXCAVATION CLASS A
1
_Ic.y.
L.S.
$10,000
7
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
L.S.
$5,000
EARTHWORK
8
CRUSHED SURFACING BASE COURSE (CULVERT FOOTING)
34
$25.00
$850
9
GRAVEL BORROW INCL. HAUL
177
__;tons
c.y.
$3500
$6,195
SURFACING
10
CRUSHED SURFACING TOP COURSE (—ROADWAY)
—BASE
67-1tons
$65.00
$4,355
11
GRAVEL
134 _------!tons
$35.00
$4,690-.-
STRUCTURE
12
—
PRECAST REINF. CONC. THREE SIDED STRUCTURE
1
lea
-
M-04,000.00
$104,000
13
TI ME SIDED BOX INSTALLATION
I
lea
$20,500.00
$20,500
MISC.
i
- 14
SEEDING-REVEGETATION AND MISCELLANOUS WORK
- I
F.A.
$5,000
15
STREAM BED GRAVEL WITH BOULDERS _
C.y.
$150.00
$26,550
_16
LIGHT LOOSE RIPRAP
12
Tons
$65.00
$780
17
BRIDGE RAILING TYPE OREGON SIDE MOUNT
76
Lf.
$150.00
$11,400
18
19
APPROACH GUARDRAIL
TEMPORARY TRAFFIC CONTROL
1
L.S.
L.S.
$10,000
$5,000
20
SILT FENCE
325
l.f.
$5.00
$1,625
21
TEMPORARY STREAM FLOW BYPASS SYSTEM
I
L.S.
$15,000
22
PROJECT SURVEYING
I
L.S.
$3,000
23
SPCC PLAN
I
L.S.
$500
24
LOG GRADE CONTROL
L.S.
$10,000—
25
HABITAT LOG
4
$10,000
_$2,50000
TOTAL: DOLLARS
$328,372
Contingency @ 20%
_SUBT0_TA_L___
$65,674
CONSTRUCTION COSTS
$394,046
------
Construction Engineering @ 15%
$59,107
CONTRACT COSTS TOTAL (Rounded)
1454,000
Date Estimate Prepared:
July. 6, 2012
7/6/2012
ATTACHMENT
Preliminary Engineering Estimate
Snow Creek Road Culvert Replacement
Snow Creek Road milepost 3.78
Date Prepared: 7/18/12
Prepared by: Mark Thurston
Note: This is an estimate of all costs from project inception until award of the
construction contract. It is assumed that after contract award, construction
funds would be applied, which are estimated separately.
ITEM
QUANTITY
UNIT
UNITCOST
AMOUNT
Actual expenditures -- 9/1/2011 through 6/15/2012:
Jefferson County staff:
$11,012.54
Consultant management and general project management
Consultant:
Standard Consultant Agreement No. 1: Type, Size, and Location Study
(includes Topographical Survey, Geotechnical Investigation, Hydraulic
Analysis)
$49,516.67
Subtotal of Actual expenditures
$60,529.21
Estimated remaining expenditures — 6/15112 t roug 3 anticipate
contract award date):
Jefferson County staff:
General project management
120
hour
$57.00
$6,840.00
Set -up Consultant Agreement, Consultant management
120
hour
$57.00
$6,840.00
Assembly of boiler plate bid documents
60
hour
$57.00
$3,420.00
Contract advertisement and award
120
hour
$57.00
$6,840.00
Subtotal
$23,940.00
Consultant:
Standard Consultant Agreement No. 1: Type, Size, and Location Study
(includes Topographical Survey, Geotechnical Investigation, Hydraulic
Analysis)
$8,725.33
Standard Consultant Agreement No. 2: PS &E and Environmental Services
(see attached Compensation schedule for further breakdown of costs):
Project Management
$6,013.00
PS &E
$33,484.00
Environmental Services
$37,934.00
Subtotal
$77,431.00
Subtotal of Estimated remaining expenditures
$110,096.33
TOTAL (ACTUAL PLUS REMAINING EXPENDITURES)
$170,625.54
ATTACHMENT
Construction Engineering Estimate
Snow Creek Road Culvert Replacement
Snow Creek Road milepost 3.78
Date Prepared: 6/25/12
Prepared by: Mark Thurston
ITEM
AMOUNT
Salaries -- General project management (150 hours @ $58 /hr)
$8,700.00
Salaries -- on -site construction inspection (350 hours @ $58 /hr)
$20,300.00
Overtime (30 hours @ $87 /hr)
$2,610.00
Benefits (included in Salaries)
$0.00
Operating Supplies
$100.00
Professional Services
$25,000.00
Communications
$300.00
Travel
$1,000.00
TOTAL
$58,010.00