To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Rounders, PE, Public Works Director /County Engineer u�
Agenda Date: December 16, 2013 /,
Subject: Bid Award for 2014 Supply of Liquid Asphalt Products
Statement of Issue:
Public Works staff has completed checking the bids opened on December 9,
2013 for the 2014 Supply of Liquid Asphalt Products, and finds it to be in the County's
best interest to award a Purchase & Sate Agreement to Albino Asphalt of Vancouver,
WA for the amounts specified in their bid.
Analysis/Strategic GoaWPro's & Con's:
This Bid Award is consistent with the County's goals in that it provides for
maintenance of the County roads infrastructure. This product is used in the County's
pavement surfacing and preservation program.
Fiscal Impact/Cost Benefit Analysis:
Purchase of these materials is accounted for in the 2014 Road Operations
Budget. Estimated Purchase a Sale Agreement amount is $383,200.00 plus Washington
State Sales Tax; however, there is no guaranteed minimum order with the supplier.
(This is a supply Agreement).
Recommendation:
The Board is asked to award the Purchase & Sale Agreement by signing and
returning the attached Memorandum to Public Works for further processing. The
Purchase & Sale Agreement will then be returned to the Board for final execution.
Department Contact:
Dale Seward, Project Manager 385 -9353
Reviewed By:
12111 j
Philip Morleiipunty Adminiatator Date
Jefferson County
Department of Public Works
623 Sheridan St.
Port Townsend, WA 98368
(360) 385 -9160
Monte Reinder, P.E.
Public Works Director /County Engineer
MEMORANDUM
To: Board of County Commissioners
From: Monte Reinders, PE, Public Works Director /County Engineer
Date: December 10, 2013
Subject: Recommendation for Award of `Purchase & Sale Agreement' for
Supply of Liquid Asphalt for the 2014 Bituminous Surfacing Treatment Program
Public Works staff has completed checking bids opened on December 9, 2013 for the Supply of Liquid
Asphalt Products for the County's 2014 `Bituminous Surfacing Treatment Program'.
Public Works finds it to be in the County's best interest to award a Purchase & Sale Agreement per the
General Contract Provisions to:
Albino Asphalt of Vancouver, WA
For the following unit bid prices:
CRS -2P (500 Tons): $550.00 per ton of product plus $76.00 per ton for freight. $313,000.00
CSS -1 (50% Dilute) (200 Tons): $275.00 per ton of product plus $76.00 per ton for freight. $ 70,200.00
Contractor Performance Bond: .................................................................................................. $ 3,000.00
For an estimated value of $386,200.00, plus Washington State Sales Tax.
The Jefferson County Board of Commissioners approves award of bid to the above - listed supplier.
John Austin, Chair
Board of County Commissioners
Date
BID TABULATIONS
SUPPLY OF LIQUID ASPHALT PRODUCTS FOR
BST PROGRAM FOR CALENDAR YEAR 2014
DIV
C Co tJ
CONTRACTOR BIDS
Contractor #1
Contractor #2
Contractor #3
Albina Asphalt
Paramount Petroleum Corp.
McAsphalt Industries
Address
Address
Address
Bid Opening Date: December 9. 2013
Bid Opening Time: 10:00 A.M.
ENGINEERS ESTIMATE
801 Main Street
5501 NW Front Ave.
19770 101 Ave.
City, State Zip Code
City. State Zip Code
City, State Zip Code
Vancouver, WA 98660
Portland, OR 97210
Langley, BC
Ph: 360. 816 -8546
Ph: 503- 273.4734 -
Ph: 604 - 888.6262
Contact: Dave Zillman
Contact: Daniel R. Briggs
Contact: Trent Gofers
e -mail: dave.zillman (C& aibina.com
e-mail: Dqnggs@ppcIa .com
e-mail: t ofers mcas halt.com
ITEM
NO.
ITEM DESCRIPTION
UNIT
APPROX.
QUANT
- UNIT
BID
PRICE
PER TON
UNIT
BID
TRANS
COSTS
ESTIMATE
TOTALS
UNIT
BID
PRICE
PER TON
UNIT
BID
TRANS
COSTS
BID
TOTALS
UNIT
BID
PRICE
PER TON
UNIT
BID
TRANS
COSTS
BID
TOTALS
UNIT
BID
PRICE
PER TON
UNIT
BID
TRANS
COSTS
BID
TOTALS
1
CRS -2P
TON
500
$630.00
$85.00
1 $357,500.00
$550.00
$76.00
$313,000.00
$560.00
.$75.00
$317,500.00
1 $645.00
$90.00
$367,500.00
$100,000 Performance Bond:
$3,000.00
$100,000 Performance Bond:
$800.001
$100,000 Performance Bond:
$0.00
BID AMOUNTS .FORCRS- 2P'INCLUDING,BOND>>
-::
- ,CRS- 213`TotaL'
:$316,000.00
,ir-r;-
CR52Pdotal:-
`$318,30000'1'1,
• =`• i.
CRS -2P Total:
t$367,500.00
2
CSS -1 50 °h DILUTE)
TON 1 200 1 $325.00 1 $85.00
1 $82,000.00
$275.00
$76.00
$70,200.00
$0.001
$0.00
$0.00
$0.001
$0.00
$0.00
ENGINEERS ESTIMATE TOTAL:
(NOT INCLUDING BOND COSTS)
$439,500.00
Eshmate amount rnclodmg
Bond andCSS 1 product costs`
s uct
+',$386,200.00-"
ar .7�.
Bid amoum'not-rnGuding' y
Bond or CSS 1 productcosts}
$318,'300.00
+: r
Bid amount not including
Boritl or CSS tproduct costs'
r $367 500.06.
PREPARED BY:
DALE SEWA D, PROJECT MANAGER
DATE: ! ^-F� l✓
Demurrage Per Hour Rate:
After 3 -Hour Unloading Time
$100.00
Demurrage Per Hour Rate.
After 3 -Hour Unloadin Time
$100.00
Demurrage Per Hour Rate:
After 3 -Hour Unloadin Time
$100.00
WA Sales Tax:
J 409 018 228
WA Sales Tax:
601 660 810
WA Sales Tax:
UBI No.
UBI No.
UBI No.
WA Cont. No:
WA Cont. No:
WA Cont. No:
FED Tax ID:
FED Tax ID:
FED Tax ID:
980 085 291
Addendum's:
0
Addendum's:
0
Addendum's:
0
REVIEWED BY: ��SI l4 l.. L[O DATE: or
PAUL WALTERS, ROAD OPERATIONS SUPERINTENDENT
1
APPROVE Y:
MO E REINDER IRECTOR /COUNTY ENGINEER
DATE: �� 3
12/10/2013