HomeMy WebLinkAbout121613_ra03Regular Agenda
JEFFERSON COUNTY
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
TO: Board of County Commissioners (BOCC)
Philip Morley, County Administrator
FROM: Carl Smith, Department of Community Development Director
DATE: December 16, 2013
SUBJECT: Corrected ordinance for amending the Jefferson County Code Fees Appendix
ATTACHED: Corrected ordinance for amending the Jefferson County Code Fees Appendix
STATEMENT OF ISSUE:
On November 12, 2013, the Board of County Commissioners adopted ordinance No. 04- 1112 -13,
adopting a new fee schedule for the Department of Community Development. The new fees are shown in
a column identified as: "2014 fees" on Appendix A of the fee ordinance. Fees that do not change were
intentionally omitted under the interpretation that they are not new, so do not need to be shown in the
column "2014 fees." However, in cases where no fee is shown, it can lead to an interpretation that no fee
is charged. This is not intended. Therefore, in order to avoid possible misinterpretation on the correct fee
amount, this corrected ordinance includes all fees, whether new or existing, in the column "2014 fees ".
ANALYSIS:
This request does not change the fees that were adopted in Ordinance No. 04-1112-13. This proposed
corrected ordinance merely avoids misinterpretation by including all fees, whether new or existing, in the
column "2014 fees ".
FISCAL IMPACT /COST BENEFIT ANALYSIS:
These additional fees for services are warranted and necessary to provide cost recovery for DCD services
and help maintain the staff necessary to provide customer service. Additionally, the customer assistance
meeting is expected to be beneficial to applicants by providing more in -depth information to guide
applicants through the permitting process.
RECOMMENDATION:
Staff recommends the BOCC adopt this corrected Fee Appendix ordinance to establish fees for DCD for
the year 2014.
REVIEWED BY:
Philip Morley, Co
JEFFERSON COUNTY
STATE OF WASHINGTON
In the matter of a corrected ordinance } Ordinance No. 04A- 1216 -13
amending the Jefferson County Code }
Fee Appendix; to add certain new }
fees and adjust other fees of the }
Department of Community Development }
WHEREAS, the purpose of this ordinance is to set a new few schedule for the
Department of Community Development; and
WHEREAS, the Department of Community Development or DCD includes Building,
Development Review and Long Range Planning; and
WHEREAS, the Department of Community Development is an "enterprise" fund
meaning that it is to be funded primarily, if not solely, by permit application fees and
grants rather than by receiving money from the County's general fund; and
WHEREAS, for the year 2013 permit application fees provided forty percent (40 %) of
the DCD budget and will be relied upon for at least that portion of the 2014 DCD Budget;
and
WHEREAS, the sole purpose leading to enactment of the Ordinance was to increase the
permit application revenue received by DCD rather than reduce it; and
WHEREAS, in light of the continued need to fund DCD activities with permit
application fees it was never the intent of the County Commission to reduce certain fees
to zero as might be concluded from the absence of a fee amount at certain locations
within the column for the year 2014 on the fee appendix amended by this Ordinance; and
WHEREAS, nowhere in the staff report made part of the November 12, 2013 Agenda
Bill for this Ordinance was there any discussion or recommendation by DCD that certain
of the fees previously collected by DCD be reduced to zero and /or abolished.
WHEREAS, Ordinance 04- 1112 -13 was the subject of a properly noticed public hearing
on November 12, 2013; and
WHEREAS, Ordinance 04- 1112 -13 included an attached Fee Schedule that was
incomplete in that it did not reflect the intent of this Board that certain fees for the year
2014 would remain the same as they had been during 2013; and
WHEREAS, the incompleteness of the 2014 column in the fee appendix reflects, in part,
the decision of DCD that it need not state the obvious, i.e., that the existing fees related to
certain activities (for example, an application for a short plat) to which a distinct pre-
Page 1
application fee was being added did not need to be repeated in the 2014 column because
everyone understood the already existing fee amounts for a given activity were being
carried over so as to be equally applicable in 2014; and
WHEREAS, it would be an absurd result and contrary to the intent of the County
Commission if a scrivener's error would be interpreted and implemented in such a way
that numerous fees collected for many years by DCD are suddenly abolished and /or
reduced to zero for the year 2014; and
WHEREAS, in the absence of adoption of this amended Ordinance there would be the
possibility of anomalies in what DCD could or could not collect from applicants in 2014.
NOW, THEREFORE, BE IT ORDAINED as follows
Section 1: Fee Schedule
The document attached as Appendix "A" to this Ordinance lists the applicable fee for all
services, permits or other activities that may be provided to citizens by all divisions of the
Jefferson County Department of Community Development.
Section 2: Commission Action:
The County Commission by this action adopts Corrected Ordinance No. 04- 1112 -13 to
be known hereafter as Ordinance No. 04C- 1112 -13.
Section 3: Severability
In the event any one or more of the provisions of this ordinance shall for any reason be
held to be invalid, such invalidity shall not affect or invalidate any other provisions of
this ordinance, but this ordinance shall be construed and enforced as if such invalid
provision had not been contained therein; PROVIDED, that any provision which shall for
any reason be held by reason of its extent to be invalid shall be deemed to be in effect to
the extent permitted by law.
Page 2
Section 4: Effective Date
This ordinance shall be in full force and effect on January 2nd, 2014.
Approved and signed this 16th day of December, 2013.
Seal:
Attest:
Carolyn Avery
Deputy Clerk of the Board
Approved as to Form Only:
David Alvarez
Deputy Prosecuting Atto ey
Page 3
JEFFERSON COUNTY
BOARD OF COMMISSIONERS
John Austin, Chairman
Phil Johnson, Member
David Sullivan, Member
Appendix A
STATE of WASHINGTON
COUNTY of JEFFERSON
DEPARTMENT OF COMMUNITY DEVELOPMENT
BUILDING DIVISION, DEVELOPMENT REVIEW AND LONG RANGE PLANNING
a) Applies to new construction only, otherwise, number 7 applies.
b) The fee is determined by a schedule established in the International Residential Code, and is based on
the value of the structure.
c) Auditor's Office fee.
d) The fee for residential square footage valuation is based on Building Valuation Data established by
International Code Council, Building Safety Journal. Building Valuation Data is published in February
and August of each year.
e) Building Official will verify valuation per IBC Section 109.3 Building Permit Valuations.
Main Floor
b
b
Base Fee
65%
65%
Plan Check Fee
a, d, a
a, d, a
Valuation
e
e
2) Additional Floors, Finished Basement
b
b
Base Fee
65%
65%
Plan Check Fee
a, d, a
a, d, a
Valuation
3) Unfinished basement
b
b
Base Fee
0.65
0.65
Plan Check Fee
a, d, a
a, d, a
Valuation
4) Carports, Garages, Pole Buildings, Decks
b
b
Base Fee
65%
65%
Plan Check Fee
a, d, a
a, d, a
Valuation
4a) Semi - Heated Space
b
b
Base Fee
65%
65%
Plan Check Fee
a, d, a
a, d, a
Valuation
5) Modular Home foundations & foundations for relocated
b
b
Base Fee
structures
65%
65%
Plan Check Fee
$34.131sq.
$34.13/sq.
Valuation
ft.
ft.
e
d, e
6) COMMERCIAL structures, construction or improvements
b
b
Cost or Fair Market Value, IRC Fee table
65%
65%
Plan Check Fee
e
e
7) Manufactured Homes / mobile homes (one or two sections)
228.00
532.00
8) Additional sections for manufactured home / mobile home
40.00
40.00
9) New - propane tanks, lines, and associated appliances
228.00
228.00
(In existing structures)
r9a) New or existing wood stove, inserts, pellet stoves, hot I 152.00 I 152.00 f
water heater, heat pump, propane tank swap out
(In existing structures)
or
c I Ib.VV c
15) Fire Code Official Services
76.00
76.00'
'Per hour or based on contract provider
149.00
Notice of App
for expenses, facilities, etc.
fee
16) Notification of Water Availability
40.00
40.00
In addition to Health Department Review
10.00
Fee
171 Water Svstem Review
228.00
228.00
1 3 hour minimum charge
now
a Public Works ree
a Public Works Fee
applied to permit
26) Customer Assistance Meeting
Hearing Examiner plus actual costs as incurred
149.00
149.00
Notice of App
for expenses, facilities, etc.
149.00
I
I
149.00
1
Public Hearin g Notice
10.00
10.00
Notice Board
a
Hearing Notice
nn
149.00 1 149.00 1 Public Hearing Notice
532.00 ) 532.00 1 Base
Page 2
Consultant Work)
Base & Actual Cc
Consultant Work)
WNW 61ax,
36) Pre - application for more than 10,000 sq /ft of impendous
380.00
surface or more than 5,000 sq/ft of non - single family
development or for a CASP
37) Allowed "Yes" Use Consistency
228.00
228.00
Base
37a) Road / Lot Segregation
304.00
304.00
Base
37b) Road Setback Administrative Variance
304.00
304.00
Base
38) Tree ! Vegetation Removal
228.00
Base
39) Stormwater Management Permit Stand Alone Only or in
380.00
380.00
Base
conjunction with Class IV General Forest Practices
40) Boundary Line Adjustment
684.00
684.00
Base
41) Minor Plan Modification
304.00
304.00
Base
(Preliminary approval only)
42) Site Plan Approval Advance Determination
532.00
532.00
Base
43) Shoreline Master Program Permit Exemption
532.00
532.00
Base
(Stand alone or with Single Family Residence)
44) Shoreline Master Program Permit Revision
152.00
152.00
Base
45) Last Will & Testamentary Division
532.00
532.00
Base
46) Home Business
228.00
228.00
Base
47) Temporary Use
228.00
228.00
Base
48) Sign Permit
228.00
228.00
Base
49) Minor PRRD Amendment
228.00
228.00
Base
(Planned Rural Residential Development)
50) CASP (Critical Areas Stewardship Plan)
532.00
532.00
Base
380.00
Pre -app
51) Additional fee for State Environmental Policy Act (SEPA)
760.00
760.00
Base
Review (including SEPA base fee, Notice of Application, and
Notice Board)
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Base
52) Discretionary D" or Unnamed Use Classification
380.00
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
53) Short Plat
2,052.00
2,052.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
53a) Plat Alteration
684.00
684.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
54) Conditional (Administrative) "C(a)" Use
836.00
836.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
Page 3
Page 4
380.00
Pre -app
55) Conditional (Discretionary) "C(d)' Use
836.00
836.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
56) Cottage Industry
836.00
836.00
Base -
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
57) Temporary Use
228.00
228.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
58) Variance, Minor
836.00
836.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
59) Shoreline Substantial Development
1,216.00
1,216.00
Base
(Primary Use)
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
60) Release of Six Year Moratorium under
532.00
532.00
Base
Forest Practices Act (Partial)
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
61) Conversion Option Harvest Plans
532.00
532.00
Base
149.00
149.00
Notice of App
10.00
10.00
Notice Board
380.00
Pre -app
62) Additional fee for State Environmental Policy Act (SEPA)
760.00
760.00
Base
Review
63) Binding Site Plans
6,536.00
6,536.00
Base
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
380.00
Pre -app
64) Conditional °C' Use
1,748.00
1,748.00
Base
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
380.00
Pre -app
65) Long Plat, Preliminary (including Planned Rural Residential
6,536.00
6,536.00
Base
Development)
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
Page 4
Development
70) Shoreline
380.00 1 Pre -app
149.00
149.00
Notice of All
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
10.00
380.00
Pre -app
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
10.00
380.00
Pre -app
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
10.00
380.00
Pre -app
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
10.00
380.00
Pre -app
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
10.00
380.00
Pre -app
Review
Site Plans; Final (including Planned Rural Residential
Development application)
Page 5
380.00 1 Pre -app
1,672.00 I Base
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
380.00
Pre -app
71 a) Release of Moratorium
1,596.00
1,596.00
Base
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
380.00
Pre -app
Review
Site Plans; Final (including Planned Rural Residential
Development application)
Page 5
380.00 1 Pre -app
1,672.00 I Base
Page 6
149.00
149.00
Notice of App
149.00
149.00
Notice of Public Hrg
10.00
10.00
Notice Board
380.00
Pre-app
75) Request for Jefferson County Comprehensive PlarVUDC
532.00
532.00
Base (if docketed, then hourly charge)
Amendment (Suggested)
380.00
Pre-app
76) J.C. Comprehensive Plan/UDC Amendment (Site Specific)
3,648.00
3,648,00
Base
—Includes Noticing & SEPA
380.00
Pre-app
In
-n
14011MM
77) Open Space/Open Space & Open Space Timber
1,748.00
1,748.00
Base
Applications
149.00
149.00
Notice of App & Public Hrg Notice
10.00
10.00
Notice Board
78) Open Space Agriculture Applications
Assessor Fee
Processed by Assessors Office
79) Transfer Forest Land (RCW 84.33) to Timber Land (RCW
Assessor Fee
Processed by Assessor's Office
84.34) Application
k-
80) Copy of Duplicating Fee - 8 1/2" x 11" or 8 1/2' x 14"
0.15
0.15
Per page
11 "x17"
0.30
0.30
Per Page
Color or Oversized Documents
At Cost
At Cost
Compact Disc
1.10
1.10
Land Use Maps
20.00
20.00
Each
Publicafions
At Cost
At Cost
Scanning
19.00
Base, or actual at hourly rate if over
hour.
Refunds
At cost
Amount paid minus staff time expended at
hourly rate.
Page 6