To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, Public Works Director
Agenda Date: November 10, 2014
Subject: Contract Supplement #1: Port Hadlock Wastewater Facility Collection
System Local Improvement District Support Services
Statement of Issue:
The Department of Public Works requests Board approval of the attached Supplement #1 for the
Collection System Local Improvement District (LID) Support Services contract with Tetra Tech, Inc.
for the Port Hadlock Wastewater System. Supplement #1 extends the completion date by one
year until December 31, 2015.
Analysis /Strategic Goals /Pro's it Con's:
The contracted work will provide outreach, finance planning, and cost estimating services for the
process of forming an LID to finance the Port Hadlock Wastewater Facility Collection System.
Fiscal Impact/Cost Benefit Analysis:
Supplement is for time only.
Recommendation:
The Department of Public Works recommends that the Board execute Supplement #1 for Port
Hadlock Wastewater Facility Final Design Services, Reclamation Plant and Influent Pipeline and
return two originals to the Department for further processing.
Department Contact:
Monte Reinders, 385 -9242
Reviewed By:
Ph ft Morlej , C unty Admints ator
/l1/,
Date
..
The Local Agency of Jefferson County desires to supplement the agreement entered
into with Tetra Tech, Inc. and executed on March 11, 2013
and identified with Project Title: Collection System Local Improvement District Support Services — Port
Hadlock Wastewater Facility.
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 11, SCOPE OF WORK, is hereby changed to read:
No Change
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is changed to read:
December 31. 2015.
III
Section V, PAYMENT, shall be amended as follows:
No Change
Page 1 of 2
Organization and Address
Supplemental Agreement
Number 1
Tetra Tech, Inc.
1420 Fifth Avenue, Suite 600
Seattle, WA 98101
Agreement Number:
Project Number:
Execution Date:
New Completion Date:
40516932
March 11, 2013
December 31, 2015
Original Contract Amount:
Amount This Supplement:
New Maximum Amount Payable:
$451,117
$0
$451,117
Project Title:
Collection System Local Improvement
District Support Services — Port Hadlock Wastewater Facility
Description of Work:
This supplement extends the completion date by one year.
The Local Agency of Jefferson County desires to supplement the agreement entered
into with Tetra Tech, Inc. and executed on March 11, 2013
and identified with Project Title: Collection System Local Improvement District Support Services — Port
Hadlock Wastewater Facility.
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 11, SCOPE OF WORK, is hereby changed to read:
No Change
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is changed to read:
December 31. 2015.
III
Section V, PAYMENT, shall be amended as follows:
No Change
Page 1 of 2
If you concur with this supplement and agree to the changes as stated above, please sign in the
appropriate spaces below and return to this office for final action.
Consultant
Consultant's 94ature
%D -
Date
COUNTY OF JEFFERSON
BOARD OF COMMISSIONERS
John Austin, Chair
Phil Johnson, Member
David W. Sullivan, Member
Nprov as to Orm only: �6)
T/9
David Alvarez Date
Deputy Pros Attorney
rV me Reinders Date
Pu rks Director