HomeMy WebLinkAbout030215_ca03Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, Public Works Director /County Engineerf
Agenda Date: March 2, 2015
Subject: Supplemental Agreement for Consultant Services with Sargent
Engineers, Inc. for Upper Hoh Road Culvert Replacements, Federal
Aid No. PLH- A160(001), County Project No. CR1896
Statement of Issue: Public Works staff requests a modification of the scope of work
and budget in the basic agreement with Sargent Engineers, Inc. to include additional
services for Upper Hoh Road Culvert Replacements.
Analysis /Strategic Goals /Pro's 8: Con's: This supplement to the existing scope of
work between Jefferson County and Sargent Engineers is for construction support
services for the culvert replacements at Upper Hoh Road MP 3.338, MP 4.38, and
MP6.95. It also provides for necessary updates to the contract documents for the
culvert replacement projects at Upper Hoh Road MP 4.38 and MP 6.95.
Fiscal Impact /Cost Benefit Analysis: The maximum amount payable for this
supplement is $49,398.00. The maximum amount payable for the Sargent Engineers
agreement will increase from $398,925.00 to $448,323.00. This project is 100 percent
funded by the Federal Highway Administration.
Recommendation: The Board is requested to sign all three originals of the
Supplemental Agreement with Sargent Engineers, and return two originals to Public
Works.
Department Contact: Mark Thurston, P.E., Project Manager, 385 -9160.
Date
The Local Agency of Jefferson County desires to supplement the agreement entered into with
Sargent Engineers, Inc. and executed on November 5, 2012 and identified as Agreement No.
1896- SARGENT -2
All provisions in the basic agreement remain in effect except as expressly modified by this
supplement.
The changes to the agreement are described as follows:
II
Section II, SCOPE OF WORK, shall be amended by creating a new task -- Task No. 9,
Construction Support. The items of work that will be done under Construction Support are set
forth in the attached Exhibit A, and by this reference made a part of this supplement.
UT
Section V, PAYMENT, shall be amended as follows:
Task No. 9, Construction Support, will have a maximum amount payable of $49,398. The new,
total maximum amount payable will be $448,323.00, as shown below.
Page 1 of 3 Revised 8/9/2013
Organization and Address:
Supplemental Agreement
Sargent Engineers, Inc.
Number 3
320 Ronlee Ln. NW
Olympia, WA 98502
Phone: (360) 867 -9284
Agreement Number: 1896- SARGENT -2
Project Number: CR1896
Execution Date:
Completion Date:
December 31, 2016
•Project Title: Upper Hoh Road Culvert
New Maximum Amount Payable:
Replacements
$448,323.00
Description of Work: This supplement provides for construction support services for the culvert
eplacement projects at Upper Hoh Road MP 3.338, MP 4.38, and MP 6.95. It also provides for
ecessary updates to the contract documents, prior to bidding, for the culvert replacement projects at
Upper Hoh Road MP 4.3 8 and MP 6.95.
The Local Agency of Jefferson County desires to supplement the agreement entered into with
Sargent Engineers, Inc. and executed on November 5, 2012 and identified as Agreement No.
1896- SARGENT -2
All provisions in the basic agreement remain in effect except as expressly modified by this
supplement.
The changes to the agreement are described as follows:
II
Section II, SCOPE OF WORK, shall be amended by creating a new task -- Task No. 9,
Construction Support. The items of work that will be done under Construction Support are set
forth in the attached Exhibit A, and by this reference made a part of this supplement.
UT
Section V, PAYMENT, shall be amended as follows:
Task No. 9, Construction Support, will have a maximum amount payable of $49,398. The new,
total maximum amount payable will be $448,323.00, as shown below.
Page 1 of 3 Revised 8/9/2013
Task Description
Current
Maximum
Amount Payable
Supplement #3
New Maximum
Amount Payable
EXISTING TASKS:
Project Management
$17,615.00
$0.00
$17,615.00
Geotechnical Analysis
$57,294.00
$0.00
$57,294.00
Pipe Boring Analysis and Design
$16,049.00
$0.00
$16,049.00
Environmental Services
$119,840.00
$0.00
$119,840.00
Stream Hydraulic Design
$19,874.00
$0.00
$19,874.00
Road and Bridge Design
$107,391.00
$0.00
$107,391.00
Land Surveying
$56,205.00
$0.00
$56,205.00
Culvert Load Rating
$4,657.00
$0.00
$4,657.00
NEW TASKS:
Construction Support
$0.00
$49,398.00
$49,398.00
TOTAL
$398,925.00
$49,398.00
$448,323.00
Page 2 of 3 Revised 8/9/2013
If you concur with this supplement and agree to the changes as stated above, please sign in the
appropriate spaces below and return to this office for final action.
Sargent Engineers, Inc.
Consultant
Consult t s Signature
Z f7 je-
Date
COUNTY OF JEFFERSON
BOARD-OF COMMISSIONERS
Chair
Member
Member
Approved as tQ form only:
q)OA"tt 4
David Alvarez U Date
Deputy Prosecuting Attorney
MonTe Reinders, P.E. Date
Public Works Director /County Engineer
Page 3 of 3
Revised 8/9/2013
EXHIBIT A
SUPPLEMENT NO.3 -- SCOPE OF WORK
UPPER HOH RD. MP 3.338 CULVERT REPLACEMENT
UPPER HOH RD. MP 4.38 CULVERT REPLACEMENT
UPPER HOH RD. MP 6.95 CULVERT REPLACEMENT
INTRODUCTION
This supplement- provides for additional professional services necessary to provide support
during construction for the three projects listed above. The work is described per site and per
task category below.
Upper Hoh Rd. MP 3.338
1. Review Contractor Submittals: The Consultant will assist the County with review and
approval of Contractor submittals, which may include but not be limited to:
• Pipe ramming work plan.
• Pipe sliplining and grouting plan.
• Materials acceptance and approval. The County will handle materials
acceptance and approval, but may request assistance for specific items. A
limited time allocation is established to provide this assistance.
• Temporary stream diversion plan.
2. Respond to Questions during Construction: The Consultant will assist the County in
answering questions that may arise during construction. The majority of these requests
will be responded to by the County. A limited time allocation is established for the
Consultant to respond to questions when requested by the County.
3. Trenchless Engineering Support: Time is allocated for five days of on -site inspection
by the subconsultant Staheli Trenchless Consultants, to assist the County with inspection
and approval of the installation of the steel casing.
4. Site Visit: Time is allocated for one site visit by the prime consultant, Sargent Engineers,
on an as needed basis.
Page 1 of 3
Upper Hoh Rd. MP 4.38
1. Assist County with final revisions to Contract Documents: The Consultant will assist
the county in performing minor revisions /updates to the contract documents in order to be
in accordance with current WSDOT specifications, standard plans, and other applicable
requirements, for bid advertisement in January 2016. This item will only be utilized if
Task 6 Road and Bridge Design funds are exhausted.
2. Review Contractor Submittals: The Consultant will assist the County with review and
approval of Contractor submittals, which may include but not be limited to:
• Shop drawings for the Precast voided slabs
• Shaft Construction Submittal
• Crosshole Sonic Log Testing results
• Materials acceptance and approval. The County will handle materials
acceptance and approval, but may request assistance for specific items. A
limited time allocation is established to provide this assistance.
3. Respond to Questions during Construction: The Consultant will assist the County in
answering questions that may arise during construction. The majority of these requests
will be responded to by the County. A limited time allocation is established for the
Consultant to respond to questions when requested by the County.
4. Geotechnical Construction Support: Time is allocated for five days of on -site
inspection by the subconsultant PanGEO, Inc., to observe pile foundation conditions and
to provide recommendations for the placement of the drilled shafts.
5. Site Visit: Time is allocated for one site visit by the prime consultant, Sargent Engineers,
on an as needed basis.
Upper Hoh Rd. MP 6.95
6. Assist County with final revisions to Contract Documents: The Consultant will assist
the county in performing minor revisions /updates to the contract documents in order to be
in accordance with current WSDOT specifications, standard plans, and other applicable
requirements, for bid advertisement in January 2016. This item will only be utilized if
Task 6 Road and Bridge Design funds are exhausted.
1. Review Shop Drawings for Three -Sided Structure: The Consultant will perform
review of shop drawings for the precast reinforced concrete three sided structure.
2. Respond to Questions during Construction: The Consultant will assist the County in
answering questions that may arise during construction. The majority of these requests
Page 2 of 3
will be responded to by the County. A limited time allocation is established for the
Consultant to respond to questions when requested by the County.
3. Geotechnical Construction Support: Time is allocated for one site visit by the team's
geotechnical engineer, PanGEO, Inc., to observe footing conditions and to provide
recommendations for the placement of the precast concrete footings.
4. -Site Visit: Time is allocated for one site visit by the prime consultant, Sargent Engineers,
on an as needed basis.
Page 3 of 3
Exhibit E -2
Consultant Fee Determination
Project: Hoh River Culverts - Construction Support
Salary Cost
Task
Principal
Senior
Engineer
Senior
Project
Engineer
Project
Engineer
Drafter 11
Task Cost
Rate:
$158.31
$123.13
$121.53
$99.14
$85.55
Upper Hoh Road MP 3.338
1. Review of Contractor Submittals
b. Pipe sliplining and grouting plan
4
$397
c. Materials acceptance and approval
4
$397
d. Temporary stream diversion plan
6
$595
2. Respond to questions during construction
4
12
$1,823
4. Site Visit
8
$1,266
Mileage
282
miles at
0.56
per mile
$158
Total Sargent Engineers
$4,635
Staheli Trenchless
Principal
Engineer
Trencless
Inspector
Admin.
Assistant
$194.00
$130.00
$83.00
1. Review of Contractor Submittals
a. Pipe ramming work plan
8
4
$2,072
3. Trenchless Engineering Support
2
50
5
$7,303
Ferry Fee
1
trip at
14
$14
Mileage
420
miles at
0.56
per mile
$235
Lodging and Per Diem
5
days at
189
per day
$945
Total Staheli Trenchless
$10,569
Total Upper Hoh Road MP 3.338
$15,205
Exhibit E -2 Page 1
Exhibit E -2
Consultant Fee Determination
Project: Hoh River Culverts - Construction Support
Salary Cost
-
Task _
Principal
Senior
Engineer
Senior
Project
Engineer
Project
Engineer
Drafter II
Task Cos
Rate:
$158.31
$123.13
$121.53
$99.14
$85.55
Upper Hoh Road MP 4.38
1. Assist County with final revisions to contract documents
24
12
24
$7,042
2. Review Contractor Submittals
a. Shop drawings for precast voided slabs
8
$793
d. Materials acceptance and approval
4
$397
3. Respond to questions during construction
4
12
$1,823
5. Site Visit
8
$1,266
Mileage
285
miles at
0.56
per mile
$160
Total Sargent Engineers
$11,481
PanGEO
Geotechnical
Project
Manager
Project
Engineer /
Geologist
$151.71
$91.89
2. Review Contractor Submittals
b. Shaft construction submittal
2
8
$1,039
c. Crosshole sonic log test results
3
2
$639
4. Geotechnical Construction Support
4
57
$5,845
Mileage
300
miles at
0.56
per mile
$168
Per Diem
51
days at
189
per day
$945
Ferries and Field Consumables
$200
Total PanGEO -
$8,835
Total Upper Hoh Road MP 4.38
$20,316
Exhibit E -2 Page 2
E
Exhibit E -2
Consultant Fee Determination
Project: Hoh River Culverts - Construction Support
Salary Cost
Task
Principal
Senior
Engineer
Senior
Project
Engineer
Project
Engineer
Drafter II
Task Cost
Rate:
$158.31
$123.13
$121.53
$99.14
$85.55
Upper Hoh Road MP 6.95
1. Assist County with final revisions to contract documents
241
12
24
$7,042
2. Review Contractor Submittals
a. Shop drawings for precast culvert
8
$793
3. Respond to questions during construction
4
12
$1,823
5. Site Visit
8
$1,266
Mileage
2901
miles at
0.56
per mile
$162
Total Sargent Engineers
1 $11,087
PanGEO
Geotechnical
Project
Manager
Project
Engineer/
Geologist
$151.711
$91.89
4. Geotechnical Construction Support
2
21
$2,233
Mileage
300
miles at
0.56
per mile
$168
Per Diem
1
days at
189
per day
$189
Ferries and Field Consumables
$200
Total PanGEO
$2,790
Total Upper Hoh Road MP 6.95
$13,878
Grand Total -
$49,398
Exhibit E -2 Page 3
CONTRACT REVIEW FORM ILI 01�9'
CONTRACT WITH: Sargent Engineers, Inc.
(Contractor /Consultant)
CONTRACT FOR: Upper Hoh Road Culvert Replacements TERM: December 31, 2016
W"r n cam.,+ za V ME
COUNTY DEPARTMENT: Public Works
For More Information Contact: Mark Thursto:
Contact Phone #: (360) 385 -9210
RETURN TO: Mark RETURN BY:
(Person in Department)
AMOUNT: $49,398.00 PROCESS:
Revenue:
Expenditure:
Matching Funds Required:
Sources(s) of Matching Funds
Step 1:
Ex APPROVED FORM
omtnents
180000010.333.20.22
180000010.595.00.65
yes
100% FHWA
REVIEW BY
Review by: �li
Date Reviewed.
Step 2: REVIEW BY
Review by:
Date Reviewed:
NZ/ APPROVED AS TO FORM
DEC 12 201
Exempt from Bid Process
X Consultant Selection Process
Cooperative Purchase
Competitive Sealed Bid
Small Works Roster
Vendor List Bid
RFP or RFQ
Other
QReturned for revision (See Comments)
ATTORNEY
Returned for revision (See Comments)
Mor
David Alvarez
Step 3: (if required) DEPARTMENT MAKES REVISIONS AND RESUBMITS TO RISK MANAGEMENT AND
PROSECUTING ATTORNEY
Step 4: CONTRACTOR/CONSULTANT SIGNS APPROPRIATE NUMBER OF ORIGINALS
Step 5: SUBMIT TO BOCC FOR APPROVAL
Submit originals and 7copies of Contract, Review Form, and Agenda Bill to BOCC Office.
Place "Sign Here" markers on all places the BOCC needs to sign.
MUST be in BOCC Office by 4:30 p.m. TUESDAY for the following Monday's agenda.
(This form is to stay with the contract throughout the contract review process and accompany the Agenda Bill.)
C: \Active Files \Active Projects \Upper Hoh Rd PLHD culverts \Consultant \Sargent Engineers\PS &E Contract\Supplement No. 3\Contract
Review Form.docx rev. 6/10/2013