To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, P.E., Public Works Director /County Engineer As�
Agenda Date: September 8, 2015
Subject: Change Order No. 1, Dowans Creek Road Realignment, County
Project No. CR17993, FEMA 1734- DR -WA, Grant No. E08 -796
Statement of Issue: Change Order No. 1 with Bruch and Bruch Construction for the
Dowans Creek Road Realignment, County Project No. CR17993.
Analysis /Strategic Goals /Pro's Et Con's: This Contract is for construction of the road
realignment between Dowans Creek Road milepost 0.85 and milepost 1.53. The road
realignment is necessary in order to move the road out of an active landslide area and
preserve access to properties served by Dowans Creek Road beyond the slide area.
Change Order No. 1 was proposed by the Contractor to utilize an alternate material
for road embankment construction, providing a cost savings to the County.
Fiscal Impact /Cost Benefit Analysis: This change order will decrease the original
contract amount by $6,825.00, from $338,466.75 to $331,641.75. This project is
funded at 75% by the Federal Emergency Management Agency (FEMA), 12.5% by
Washington State, and 12.5% by the County Road Fund.
Recommendation: Public Works recommends that the Board execute all three
originals of Change Order No. 1 with Bruch and Bruch Construction and return two (2)
originals to Public Works for further processing.
Department Contact: Mark Thurston, P. E., Project Manager, 385 -9160.
Reviewed By:
P i ip Morley C unty dmini ator Date
JEFFERSON COUNTY
Sheet 1 of 1
DEPARTMENT OF PUBLIC WORKS
Change
1
Date: 8/11/2015
CHANGE ORDER
Order No.
Ordered by County Engineer under terms of
Section 1 - 04. 4 of the Standard Specifications
CR17993
Contract No.
Change proposed by Contractor
To:
Bruch & Bruch Consh action, Inc_
1706 Highway 101 West
End ��
6%19 C� �u 7
Port Angeles, WA98363
1 >s` _ �r�.c.4�f ontraator Firm Name
Project Title Dovrans Creek Road
igignature� Date
Title �
Consent given by Surely (when required)
Realgnment
By
Attorney -in -fact Date
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
This change order authorizes replacement of approximately 1,300 cubic yards of Light Loose Riprap (Bid Item No. 8)
with a new bid item, Quarry Spall Blend (Bid Item No. 22), consisting of the following materials:
Approximately 1,000 cubic yards of 4!'- 2" spalls from Snider Quarry blended with approximately 300 cubic
yards of 3" -1 -112" minus crushed rock from Beaver Falls Quarry.
Materials
Section 8 -15.2 is supplemented with the following:
Materials for Quarry Spall Blend will be be visually approved and accepted by the Engineer.
Measurement
Section 8 -15.4 is supplemented with the following:
Quarry Spall Blend will be measured by the cubic yard of Quarry Spall Blend actually placed.
Payment
Section 8-15.5 is supplemented with the following:
"Quarry Spall Blend", per cubic yard. The unit price for the blended material shall be $32.35icy.
The estimated total decrease in the contract amount for this change order is as follows:
(1,300 cy)`($37.60 - $32.35) = $6,825.00
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
ORIGINAL
CURRENT
ESTIMATED
ESTIMATED
CONTRACT
CONTRACT
NET CHANGE
CONTRACT TOTAL
AMOUNT
AMOUNT
THIS ORDER
AFTER CHANGE
$338,466.75
$338,466.75
- $6,825.00
$331,641.75
ORIGINAL CONTRACT
CURRENT CONTRACT
CONTRACT TIME
NEW CONTRACT
TIME (days)
TIME (days)
CHANGE (Add!DeO
TIME (days)
50
50
0
50
APPROVAL RECOMMENDED APPROVAL ECOMMEND
X
t4-/ -z
Project Man ger Date County Epw Date
APP OVA R COMMENDED APPROVED
Engin ng Services Manager Date Chair, Jefferson County Commissioners Date