HomeMy WebLinkAbout112315_ca04Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, Public Works Director/County Engineer/
Agenda Date: November 23, 2015
Subject: Adopt the 2016-2021 Six -Year Transportation
Improvement Program
Statement of Issue:
Adopt of the 2016-2021 Jefferson County Six -Year Transportation Improvement
Program (TIP).
Analysis / Strategic Goals / Pros ft Cons:
RCW 36.81.121 requires the annual adoption of a six-year transportation improvement
program after holding a public hearing. The purpose of the law is to "assure that each
county shall perpetually have available advanced plans looking to the future for not
less than six years as a guide in carrying out a coordinated transportation program"
(RCW 36.81.121(1)).
A public hearing was conducted on November 2, 2015. Public testimony included
requests to add Project No. 30, ODT - Feasibility Study - Four Corners Road to S.
Discovery Bay. This change has been made to the TIP and as discussed at the hearing,
this project relies on the Peninsula Trails Coalition (PTC) to secure funding from non -
county sources. Placement on the TIP is subject to reassessment in two years if full
funding has not been secured.
The PTC received an estimate of $75,000 to conduct the study. The $85,000 estimate
shown on the TIP includes a small buffer for cost increases and some Public Works
staff time.
Fiscal Impact / Cost -Benefit Analysis:
The TIP relies heavily on the availability of outside grant and program funding from
the State and Federal government. Fiscal impact is evaluated through the annual
budgeting process including adoption of an Annual Road Construction Program.
Department of Public Works
O Consent Agenda
Page 2 of 2
Recommendation:
Approve by Resolution the proposed Six -Year Transportation Improvement Program.
Return a signed copy of the Resolution to Public Works for further processing.
Department Contact: Zoe Ann Lamp, AICP, Transportation Planner 385-9162
ved By:
i
Philip M(06y, County
Date
In the Matter of Adoption of the
2016-2021 Six -Year Transportation
Improvement Program
COUNTY OF JEFFERSON
STATE OF WASHINGTON
RESOLUTION NO.
WHEREAS, State law obligates the legislative authority of each county to adopt on an annual basis a
six-year transportation improvement program, holding a public hearing prior to adoption, the purpose of which
is to "assure that each county shall perpetually have available advanced plans looking to the future for not less
than six years as a guide in carrying out a coordinated transportation program" (RCW 36.81.121(1)), and;
WHEREAS, an analysis of the Road Fund was prepared covering the six-year program period
using the County's best estimate of future revenues and expenditures in accordance with WAC 136-15-130
and,
WHEREAS, the Board of County Commissioners, Jefferson County, State of Washington, has
reviewed the transportation priority array and bridge condition report as prepared by the Department of Public
Works, and has conducted a public hearing on the corresponding proposed six-year transportation improvement
program;
IT IS HEREBY RESOLVED that the Board of County Commissioners does approve and adopt the
Six -Year Transportation Improvement Program for the years 2016 through 2021, inclusive.
IT IS FURTHER RESOLVED that, with respect to the items listed in the Program, the County
Engineer is authorized to make revision to individual project scope, length and termini, timing, and funding
sources, as may be required from time to time due to additional resources becoming available or unavailable
and in accordance with RCW 36.81.130 and WAC 136-16, without the Board of County Commissioners
having to conduct a public hearing or adopt a resolution to amend the Program
ADOPTED and signed this day of 2015.
ATTEST:
Erin Lundgren
Clerk of the Board
JEFFERSON COUNTY
BOARD OF COMMISSIONERS
David Sullivan, Chair
Phil Johnson, Member
Kathleen Kler, Member
Agency: Jefferson County DRAFT SIX-YEAR Hearing Date:xx/xx/15
County No. 16 TRANSPORTATION IMPROVEMENT PROGRAM Adoption Date: xx/xx/15
2016-2021 Resolution No.xx-xx
Last updated: 11/17/2015 DRAFT
p
U
X
o.
F
PROJECT IDENTIFICATION
A. Federal Aid No.
B. Road Log Number - Bridge Number
Beginning and End Milepost
D. Project I Road Name
E. Description of Work and Total Cos[ (incl. prior/future)
w
y
w
> a
K
-
n
¢
y
o
LL
r
z
Z"
E
Q-
O
F
w
O
U
�-
PROJECT COSTS IN DOLLARS
FUNDING SOURCE INFORMATION EXPENDITURE SCHEDULE
FEDERALFUNDS STATE FUNDS
RAP/
y¢STATE
y TIA/UATA OTHER LOCAL YEAR1 YEAR2 YEAR3 YEAR4 YEAR5 YEAR6 TOTAL
s COST BY TOTAL
rT'Si.
z y / PHASE REVENUES FUNDS 2016 2017 2018 2019 2020 2021 2016-2021
OTHER
FEDERALLY
FUNDED
PROJECTS ONLY
w
¢
aCAPP/
r
v
w
o
0.QC.
z
z z
w
zr^
O >_Z
K U iwLL
a
0 1
07
1
93150 MP 0.00-2.26
Center Road Overlay - Phase 5
2R project: Asphalt overlay on segment between Chimacum
Crossroads and beginning of 2009 overlay.
Total=$933.000
05
S
2.26
P.E.
R/W
Const.
Total
0
DCE
N
1/13 RAP/PIF 61,740
0
61,740 53,840 7,900 61,740
1
0
01 1 10
5/16 RAP/PIF 855,000
0
855,000 855,000 855,000
0 916,740
0
0
916,740 53,840 862,900 0 0 0 0 916,740
07
2
91160
QuinaultSouth Shore Road Repair
Large woody debris, bank roughening, and other measures
per Washington State Integrated Streambank Protection
Guidelines as miligation for 2010 repair. Total=$1,529,400
20
S
NIA
P.E.
RW
Const.
Total
0
DCE
Y
3/15
1/13 ER 85,233
13,302
98,535 98,535 98,535
9/15 ER 6,000
0
6,000 6,000 6,000
6/16 ER 914,300
0
914,300 914,300 914,300
1,005,533 0
0
13,302
1,018,835 104,535 914,300 0 0 0 0 1,018,835
08
3
25000 MP 1.60 to MP 1.75
Dosewallips Rd. Permanent Slide Repair
Repair work: Install catch basins, under drains, asphalt curb to
direct water away from site. Landscaping & pavement repair
Total: $160,000
05
S
0.15
P.E.
R/W
Const.
Total
0
EA
N
RAP 30,600
3,400
34,0001 34,000 34,000
0
0 0
3/15 RAP 127,800
14,200
142,000 142,000 142,000
0 158,400
0
17,600
176,000 34,000 142,000 0 0 0 0 176,000
07
4
91420 MP 3.338
Access Preservation: Hoh Rain Forest, Olympic Nat. Park
2011 Public Lands Highways Discretionary (PLHD)
Program funding for replacement of substandard failing culvert
at MP 3.338 Upper Hoh Rd. CN Phase Total=$733,565
11
S
NIA
P,T
P.E.
RW
Const.
Total
0
DCE
Y
6/14
0
0 0
0
0 0
8/15 PLHD 5,000
0
5,000 5,000 5,000
5,000 1 0
0
0
5,000 5,000 0 0 0 0 0 5,000
07
5
91420 MP 4.38
Access Preservation: Hoh Rain Forest, Olympic Nat. Park
2011 Public Lands Highways Discretionary (PLHD)
Program funding for replacement of substandard failing culvert
at MP 4.38 Upper Hoh Rd. (CN Phase) Total=$1,209,394
11
S
N/A
P,T
P.E.
R/W
Const.
Total
0
DCE
Y
5/14
PLHD 13,400
0
13,400 13,400 13,400
PLHD
0
0 0
8/16 PLHD 980,140
0
980,140 980,140 980,140
993,540 0
0
0
993,540 13,400 980,140 0 0 0 0 993,540
07
6
91420 MP 6.95
Access Preservation: Hoh Rain Forest, Olympic Nat. Park
2011 Public Lands Highways Discretionary (PLHD)
Program funding for replacement of substandard failing culvert
at MP 6.95 Upper Hoh Rd. (CN Phase) Total=$1,206,084
11
S
N/A
P,T
P.E.
RW
Const.
Total
0
DCE
Y
11/14
PLHD 13,500
0
13,500 13,500 13,500
12/13 PLHD
0
0 0
8/16 PLHD 1,024,620
0
1,024,620 1,024,620 1,024,620
1,038,120 0
0
0
1,038,120 1,038,120 0 0 0 0 0 1,038,120
NIA
7
91420 MP 0.0 to MP 12.0
Upper Hoh Road/ Olympic Nat. Park FLAP Project
2013 Federal Lands Access Program (FLAP) funding ($13.7)
Match funding for infrastructure protection projects performed
by Western Federal Lands division of FHWA. Total = $13.7 M
11
S
12.0
P,T
P.E.
RW
Const.
Total
0
DCE
Y
4/14
30,000
30,000 15,000 15,000 30,000
4/15
0
0 0
6/17
0
0 0
0 0
0
30,000
30,000 15,000 15,000 0 0 0 0 30,000
N/A
8
STP(R)-2016(018)
Rick Tollefson Memorial Trail -Phase 1 (Chimacum Valley)
Multi -use trail from HJ Carroll Park to Old Hadlock Rd
crossing Chimacum Creek and Chimacum Road.
Total=$1,657,705
01
S
0.30
P, T
P.E.
RW
Const.
Total
0
DCE
Y
9/13
2/10 STP -R PBSP 0
4,800
4,800 4,800 4,800
6/12
0
0 0
3/16 STP -R 641,797 PBSP 311,514
0
953,311 953,311 953,311
641,797 311,514
0
4,800
958,111 958,111 0 0 0 0 0 958,111
NIA
9
Rick Tollefson Memorial Trail - Ball Field Connection
Realignment of Old Hadlock Road to g0° intersection and
pedestrian crossing linking RTMT at Old Hadlock Rd to
Bob Bates Field Project Total=$85,000
21
S
0.25
P.E.
RW
Const.
Total
0
Y
10/14
15,000
15,000 15,000 15,000
5,000
5,000 5,000 5,000
3/15
65,000
65,000 65,000 65,000
0 0
0
85,000
85,000 15,000 70,000 0 0 0 0 85,000
02
10
SR 101 & multiple county roads MP 294.7 US 101
Quilcene Complete Streets
Crosswalk improvements & multi -use facilities involving
US 101, county roads & separated paths. Connects school,
community center& ballfields. Total=$884,165
21
S
I
0.50
I
P,T
P.E.
RW
Const.
Total
0
DCE
Y
8/14
1
1/14 SRTS/PBSP 55,000
0
55,000 55,000 55,000
1115
0
0 0
1/16 SRTS/PBSP 695,350
0
695,350 695,350 695,360
0 750,350
0
0
750,350 55,000 695,350 0 0 0 0 750,3501
NIA
11
Old Gardiner Road to Salmon Creek
DDT South Discovery Bay - Segment A
Construction Segment A of ODT along west side
of Discovery Bay between Old Gardiner Road & Salmon Creek
Total=$1,455,000
01
S
.75
W
P.E.
RW0
Const.
Total
01
1
Y
0
0 0
0 0
WWRP/ALE 1,250,000
10,000
195,000
1,455,000 1,455,000 1,455,000
0 1,250,000
10,000
195,000
1,455,000 1,455,000 0 0 0 0 0 1,455,000
Last updated: 11/17/2015 DRAFT
Agency: Jefferson County DRAFT SIX-YEAR Hearing Date:xx/xx/15
County No. 16 TRANSPORTATION IMPROVEMENT PROGRAM Adoption Date: xx/xx/15
2016-2021 Resolution No.xx-xx
^
U
Z
LL
p
Fw
a
F
PROJECT IDENTIFICATION
A. Federal Aid No.
B. Road Lo
Beginning and End Milepost
E. Description of Work and Total Cos[ (incl. prior/future)
z
>
Fr
rO
o
U
-
PROJECT COSTS IN DOLLARS
FUNDING SOURCE INFORMATION EXPENDITURE SCHEDULE
FEDERALFUNDS STATE FUNDS
RAP/
D
CAPP/
w U
TI STATE OTHER LOCAL YEAR1 YEAR2 YEAR3
YEAR YEAR YEAR TOTAL
COSTBY
267C.
O / REVENUES FUNDS 2016 2017 2018 2019 2020 2021
TPHASE
OHER
FEDERALLY
FUNDED
PROJECTS ONLY
w
¢x
r
w¢u
0TOTAL
zz
z
wwaU
QU wy>_
O
Ky
Z
0
08
12
60150 MP 3.20 to MP 4.56
South Discovery Road Pavement Preservation
2R Project: Pavement preservation overlay. The purpose is to
preserve the structure and improve ride quality and safety.
Total=$503,000
05
S
1.28
P.E.
R/W
Const.
Total
0
N
RAP 40,000
5,000
45,000 211,000 211,000 5,000 45,000
0
0 0
RAP 410,000
48,000
458,000 456,000 458,000
0 450,000
0
53,000
503,000 20,000 20,000 463,000 0 0 0 503,000
08
13
060 MP 1.53 to MP 2.25
Paradise Bay Road - Phase 3
�'3R'Project:Overlay and widen with asphalt concrete.
Roadside obstructions evaluated and removed where
warranted. Total=$1.000,000
06
P
1.43
P,T,C
P.E.
R/W
Const.
Total
0
N
RAP 157,500
17,500
175,000 87,500 87,500 175,000
0
0 0
RAP 742,500
82,500
825,000 825,000 825,000
0 900,000
0
100,000
1,000,000 0 0 67,500 67,500 825,000 0 1,000,000
07
14
93250 (Sidewalk & Separated Path)
Rick Tollefson Trail - Phase 2 (Connections)
Pedestrian connection from Lopeman Rd. to Jefferson County
Library
Project Total=$775,000
21
P
0.62
P.E.
R/W
Const.
Total
1 0
DCE
Y
6/18
125,000
25,000
150,000150,000 150,000
0
0 0
0
0 0
0 125,000
0
25,000
150,000 0 0 0 0 0 150,000 150,000
08
15
60150 MP 3.62 to MP 4.00
South Discovery Road Realignment
Realign a portion of S. Discovery Rd. to provide adequate
setbacks from an eroding shoreline bluff.
Project Total = $2,170.000
07
P
0.38
P,T
P.E.
R/W
Const.
Total
0
Y
RAP 153,000
17,000
170,000 20,000 20,000 75,000 55,000 170,000
RAP 450,000
50,000
500,000 500,000 500,000
RAP 1,350,000
150,000
1,500,000 1,500,000 1,501000
0 1,953,000
0
217,000
2,170,000 0 20,000 20,000 75,000 555,000 1,500,000 2,170,000
09
16
50020 MP 0.84
Salmon Creek Bridge Construction -W. Uncas Rd -MP 0.804
Replace deteriorated metal culvert with bridge.
Fish passage project with North Olympic Salmon Coalition
Total=$997,000
11
P
N/A
P,T
P.E.
R/W
Const.
Total
0
N
1/14
5,000
5,000 5,000 5,000
0
0 0
7/17
USFW-NFPP 100,000 RCO-SRFB 763,300
34,700
898,000 898,000 898,000
100,000 763,300
0
39,700
903,000 5,000 898,000 0 0 0 0 903,000
07
17
93250 MP 0.34 to MP 0.96
Chimacum Rd Improvement
Intersecton realignment, extend multi -use trail/sidewalk/bike lane
along Chimacum Road from Church Lane to Redeemer Way
Project Total=$1,850.000
21
P
0.30
P.E.
R/W
Const.
Total
0
DCE
Y
STP -R 259,500
40,500
300,000 15,000 235,000 50,000 300,000
STP -R 43,250
6,750
50,000 50,000 50,000
STP -R 1,297,500
202,500
1,500,000 1,500,000 1,500,000
1,600,250 0
0
249,750
1,850,000 15,000 0 0 235,000 100,000 1,500,000 1,850,000
NIA
18
Salmon Creek Crossing Highway 20
DDT South Discovery Bay - Segment B
Construction of Segment B of DDT along south side of Discovery
Bay between Salmond Creek and crossing Hwy. 20
Total=$852,500
01
P
.33
P.E.
R/W
Const.
Total
0
Y
RCO 130,000
12,500
142,500 142,500 142,500
RCO 45,000
5,000
50,000 50,000 50,000
RCO 600,000
60,000
660,000 660,000 660,000
0 775,000
0
77,500
852,500 0 0 0 192,500 660,000 0 852,500
09
19
51410 MP 2.555
West Valley Road Culvert Replacement - Naylor Creek
Replace culvert at Naylor Creek with a fish -passable culvert.
Total=$500.000
11
P
N/A
P.E.
R/W
Const.
Total
0
N
OTHER 50,000
0
50,000 50,000 50,000
1 01
0 0
OTHER 450,000
0
450,000 450,000 450,000
0 500,000
0
0
500,000 0 0 0 50,000 450,000 0 500,000
09
20
35290 MP 0.84
Snow Creek Road Culvert Replacement - MP 0.84
Replace deteriorated metal culvert with jacked/bored casing.
Total=$1,000,000
11
P
N/A
P.E.
R/W
Const.
Total
0
DCE
N
FLAP 250,000
0
250,000 250,000 250,000
0
0 0
FLAP 750,000
0
750,000 750,000 750,000
1
1,000,000 0
0
0
1,000,000 0 0 0 250,000 750,000 0 1,000,000
07
21
93150 MP 1.358
Center Road Culvert Replacement
Replace deteriorated metal pipe with bored/lacked casing.
Total=$100.000
11
p
N/A
1
P.E.
R/W
Const.
Total
0
Y
15,000
15,000 15,000 15,000
10,000
10,000 10,000 10,000
75,000
75,000 75,000 75,000
0 0
0
100,000
100,000 0 0 25,000 75,000 0 0 100,000
NIA
22
Cedar Avenue Non -Motorized & Intersection Improvements
"Safe Routes to School" project including roadside safety,
channelization, intersection and pedestrian facilities.
Total=$565,000
21
P
0.61
P.E.
R/W
Const.
Total
0
N
SRTS/PBSP 50,000
15,000
65,000 15,000 50,000 65,000
0
0 0
SRTS/PBSP 500,000
0
500,000 500,000 500,000
0 550,000
0
15,000
565,000 15,000 50,000 500,000 0 0 0 565,000
Last updated: 11/17/2015 DRAFT
Agency: Jefferson County DRAFT SIX-YEAR Hearing Date:xx/xx/15
County No. 16 TRANSPORTATION IMPROVEMENT PROGRAM Adoption Date: xx/xx/15
2016-2021 Resolution No.xx-xx
^
Z
LL
p
a
PROJECT IDENTIFICATION
A. Federal Aid No.
B. Road Lo
Beginning and End Milepost
Description of Work and Total Cos[ (incl. prior/future)
z
>
LLE.
U
-OH
it ut/
PROJECT COSTS IN DOLLARS
FUNDING SOURCE INFORMATION
FEDERALFUNDS STATE FUNDS
RAP/
CAPP/
TI STATE OTHER
COSTBY
T'Si.REVENUES
TPHASE
ER
LOCAL
FUNDS
YEAR1
2016
YEAR2
2017
EXPENDITURE SCHEDULE
YEAR3 YEAR YEAR YEAR
2018 2019 2020 2021
TOTAL
261C.
FEDERALLY
FUNDED
PROJECTS ONLY
w
z¢r wo
0TOTAL
zz
z
wa wy
QU
O
Ky
Z
1
N/A
23
Chimacum Grange to HJ Carroll Park -Pedestrian Improvemen
Non -motorized path completing connection from Chimacum
School to HJ Carroll Park
Total=$190,000
21
P
0.28
P.E.
R/W
Const.
Total
0
N
PBSP 25,000 15,000 40,000 15,000 25,000 40,000
1 0 0 0
PBSP 150,000 0 150,000 150,000 150,000
0 175,000 0 15,000 190,000 15,000 25,000 150,000 0 0 0 190,000
N/A
24
DDT - Milo Curry Rd. to Transit Center at Four Corners Rd.
Separate non -motorized path or widened shoulder connecting
Larry Scott Trail to Transit Center at Four Corners Rd.
Total=$611.500
01
P
0.40
P.E.
R/W
Const.
Total
0
DICE
Y
STP -R 96,447 15,053 111,500 111,500 111,500
0 0 0
0 0 0
96,447 0 0 15,053 111,500 0 0 0 0 0 111,500 111,500
N/A
25
Run -Off -Road & Intersection Safety Project
Countywide safety project: Add guardrails and signs on
eligible county roads.
Total=$600,000
21
P
N/A
P.E.
R/W
Const.
Total
0
DCE
N
HSIP 100,000 0 100,0001 1 100,0001 100,000
0 0 0
HSIP 500,000 0 500,000 500,000 500,000
600,000 0 0 0 600,000 0 0 0 100,000 500,000 0 600,000
07
26
93150 MP 14.59-15.01
Duilcene Center Rd Rebuild & Pedestrian Improvement
Asphalt rehabilitation with sidewalk replacement and expansion.
ADA Upgrade
Total=$500.000
05
P
.42
P.E.
R/W
Const.
Total
0
DICE
N
STP -R 43,250 6,750 50,000 50,000 50,000
0 0 0
STP -R 0 0 0
1 1 43,250 0 0 6,750 50,000 0 0 0 0 0 50,000 50,000
27
Countywide Bridge Load Resting Per Federal
Requirements
Total=$150,000
21
P
I
P.E.
R/W
Const.
Total
0
STP -R 129,750 20,250 150,000 150,000 150,000
0 0 0
0 0 0
129,750 0 0 20,250 150,000 0 150,000 0 0 0 0 150,000
28
Engineering Assessment for Mulitple Locations for
Roads Accessing Federal Lands: Oil City Road.. Undie Road,
Quinault South Shore Road
Total=$250.000
18
P
N/A
P.E.
R/W
Const.
Total
0
FLAP 250,000 0 250,000 250,000 250,000
0 0 0
0 0 0
250,000 0 0 01 250,000 01 250,000 0 0 0 0 250,000
N/A
29
Various
Countywide Various Improvements
Various projects countywide involving safety, culvert
replacement, drainage, surfacing upgrades, pedestrian and
bicycle facilities, or other improvements. Total=$30,000
P
N/A
P.E.
R/W
Const.
Total
0
N
10,000 10,000 5,000 5,000 10,000
0 0 0
50,000 50,000 25,000 25,000 50,000
0 0 0 60,000 60,000 30,000 0 0 30,000 0 0 60,000
30
DDT - Feasibility Study - Four Corners Rd to S. Discovery
Bay - Funding to come from non -county source and placement
on TIP will be reassessed in 2017 if full funding is not secured.
Total=$85.000
18
P
8.0
P.E.
R/W
Const.
Total
0
85,000 0 85,000 85,000 85,000
0 0 0
1 0 01 1 1 1 0
0 01 85,0001 01 85,0001 01 01 85,000 0 0 0 85,000
31
P.E.
R/W
Const.
Total
0
21 0 0
0 0 0
�00
0 0 0
0 0 0;;;
0 0 0 00 0 0
Last updated: 11/17/2015 DRAFT