HomeMy WebLinkAboutPC Agenda 05-07-2014 Workshop, PT 7 PHMPR SEIS TimelinePLEASANT HARBOR SEIS PROCESS & TIMELINE (contingent upon accuracy of step 1 date) 2014
Prepared by Project Planner, David Wayne Johnson revised April 7th, 2014
STEP WHO WHAT WHY WHEN
1 Applicant All Final Reports to Consultant For Production of Preliminary Draft SEIS May 5th
2 Consultant
Preliminary/Working Draft SEIS to County For County & Applicant Review and
comment
May 12th (1 week)
3 County Staff Review & comment due back to
Consultant
Ensure accuracy and readability May 26th
(2 weeks)
4 Consultant
Produce Final Draft Incorporate staff & applicant comments June 9th
(2 weeks)
*5 County PC meeting & BoCC Afternoon Briefing Opportunity to inform of upcoming
release, requirements, work schedule
and requirements
PC Meeting February 19th
BoCC - Monday Afternoons in
March 17th
6 County Notice of Availability, Press Release and
Notice of Public Hearing
To inform the public of availability Concurrent with Draft SEIS release
– Step 7
7 County &
Consultant
Publish Final Draft and release to public Public review for 45 day public
comment period
June 30th
(3 weeks)
9 County &
Consultant
Open House & PC Public Hearing
(Brinnon School Gym) – after release of
the Draft but before end of comment
period
Present Project, Staff Report & Take
Public Testimony and written comments
July 16th
(2 weeks)
10 County Staff Review of public & agency
comments
Compile comments to address in Final
SEIS
45 days after release of Draft SEIS
August 13th
11 Consultant
Produce Final SEIS Incorporate staff, agency and public
comment – release to public - seven
days before BoCC action. 60 day notice
to Commerce – intent to amend UDC
prior to BoCC decision
Nov 5th
(12 weeks)
12 County PC Recommendation to BoCC Required per JCC 18.45.090 TBD
13 County BoCC deliberations to accept PC
recommendation or hold Public Hearing
Required per JCC 18.45.090 TBD
14 County BoCC Public Hearing or instruct staff to
draft ordinance
Required per JCC 18.45.090 TBD
15 County BoCC decision to adopt Development
Agreement & regulations
Required per JCC 18.45.090 TBD
PC = Planning Commission BoCC = Board of County Commissioners * = Completed