HomeMy WebLinkAboutClark Land Office, Amendment No. 1 - 080116Professional Services
Organization and Address
Supplemental Agreement No. I
Clark Land Office
P.O. Box 2199
Sequim, WA. 98382
Agreement Number
N/A
Project Number
Execution Date
Completion Date
CRP 180199000 / 18020070
August 8, 2016
December 31, 2019
Project Title
New Maximum Amount Payable
Undie Road Emergency Relocation
$80,644.00
Description of Work
Construction Surveying Services for the construction of the Undie Road Emergency Relocation project.
The Local Agency of Jefferson County desires to supplement the agreement entered into with
Clark Land Office, PLLC and executed on March 28, 2016 and identified as Agreement No. N/A.
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 2. SCOPE OF SERVICES, is hereby changed to read:
Additional work per Exhibit "A" attached hereto.
II
Section 3. TIME FOR PERFORMANCE, is amended to change the number of calendar days for
completion of the work to read: No Change.
III
Section V, PAYMENT, shall be amended as follows:
New Maximum Amount Payable is $80,644.00.
as set forth in the attached Exhibit B and B-1, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the
appropriate spaces below and return to this office for final action.
Clark Land Office, PLLC
Consultant
Consultant's Signature
;7/z /1'e
Date
COUNTY OF JEFFERSON
BOARD OF COMMISSIONERS
Kathleen Kler, Chair
Phil John Me er
Davi W. Sullivan, Member
Approved fo only:
°f 2A6
Date
Dtq fy Prosecuting Attorney
p /
onte R ' �, P.E.
Date
Public Works Director/County
Engineer
EXHIBIT A
SCOPE OF WORK
CONSTRUCTION SURVEYING SERVICES
UNDIE ROAD RELOCATION
COUNTY PROJECT NO. CRP 18020070
INTRODUCTION
This supplemental agreement provides for construction surveying services that will be necessary
during construction of the Undie Road Relocation project.
TASK 1- ADMINISTRATION AND COORDINATION
The Consultant will be required to continually coordinate with the Agency the work effort involved
in all tasks under this agreement. Work completed under this task shall include the following:
A. Provide one-on-one liaison between the Agency Project Manager and Consultant team.
B. Provide notification of anticipated delays or problems.
C. Provide monthly invoice, which shall include the following:
a. Name of each employee that worked on the project in the billing period
b. Each employee's job classification
c. Each employee's hours worked
d. Each employee's hourly wage rate
e. Each invoice will also include all direct non -salary costs and copies of supporting invoices
or bills. The Agency will disallow all or part of any claimed cost, which is not adequately
supported by documentation.
£ Summary of work completed.
D. The Consultant shall coordinate the work effort for this project with the Agency's schedule and
the construction activities of the Contractor, through the duration of the project. All construction
staking times shall be coordinated through the Agency.
3
TASK 2 - MAPPING
A. Survey the location of existing stakes placed by the Agency, representing mean high water
along the banks of the creek near station 26+00. Provide a drawing in AutoCAD format of
the surveyed stake locations to the Agency.
Task 3 — R/W AND CONSTRUCTION STAKING
This work consists of providing construction surveying for the items identified within this scope
of work. The Consultant shall perform the necessary surveying to establish horizontal and vertical
control of the roadway, to ensure that the project is staked and constructed at the proper location
and grades. The Consultant shall coordinate work with the Agency to ensure meeting the
Contractor's schedule. The Consultant shall provide professional guidance on procedures and
methods involved in this work to the Agency when necessary. The construction staking described
below shall apply to the road realignment between Station 10+00 and Station 56+50 as shown on
the plans, subject to revision by the Agency. It is anticipated that the construction staking for this
project will require the following work:
A. Coordinate the construction staking work with Agency.
B. Review of proposed project construction plans and AutoCAD drawings provided by the
Agency. Calculation and preparation of roadway points for construction staking. Uploading
of field staking data to surveying equipment.
C. Stake the right of way/clearing and grubbing limits, at 50' intervals and at all offset/angle
points as shown on the right of way plans. The clearing and grubbing limits coincide with the
right of way lines. Stake the corners of the 4 "debris disposal" areas as shown on the right of
way plans.
D. Establish additional horizontal and vertical surveying control for construction staking as
needed. Establish temporary elevation benchmarks adjacent to the roadway construction zone
as needed.
E. Stake the horizontal alignment and vertical profile of the construction centerline. Stakes shall
be placed at 50' intervals along the alignment and at all curve points (P.C.s and P.T.$).
F. Place primary slope stakes at 50' intervals along the alignment on tangents and at 25' intervals
on curves. Place bottom of ditch stakes in cut situations where ditches are required. Place
offset reference stakes for all primary slope stakes; reference stakes to be set at 5 foot offset
from all primary slope stakes (or as requested by the Agency's contractor).
G. Place roadway surfacing material stakes at the elevation of the top of the Select Borrow
material (Roadway Section A) and the Quarry Spalls material (Roadway Section B), at 50'
intervals along the alignment on the tangents and at 25' intervals on the curves. Stakes shall
be placed at the centerline and roadway edges, including the 12 widened areas with horizontal
tapers. Stakes shall consist of hubs with whiskers.
Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engine"
Agenda Date: August 1, 2016
Subject: Professional Services Supplemental Agreement with Clark Land
Office for Undie Road Emergency Relocation, County Project No.
CR18020070, FEMA Disaster No. 4249 -DR -WA
Statement of Issue: Professional Services Supplemental Agreement with Clark Land
Office of Sequim, Washington for construction surveying services for the Undie Road
Emergency Relocation.
Analysis/Strategic Goals/Pro's Et Con's: Construction surveying work is required to
construct this project in addition to the work contained in the original agreement.
The work will consist of construction staking for the Undie Road Emergency Relocation
project, scheduled for August -October, 2016.
Fiscal Impact/Cost Benefit Analysis: The maximum amount payable under the
original Consultant Agreement was $23,934.00, this Supplemental Agreement No. 1
adds $56,710.00; the new total maximum amount payable of the Consultant
Agreement is $80,644.00. Total funding for this project is $209,000.00 from FEMA,
withthe remainder funded from Jefferson County. 'tt-L �s F -(s cve,.`�, Tod
r� C
Recommendation: The Board is requested to sign all three originals of the
Professional Services Supplemental Agreement with Clark Land Office, and return two
originals to Public Works.
Department Contact: John Wayand, Project Manager, 385-9377.
Reviewed By:
ihl'
ilip M " y, County Administra Date
CONTRACT REVIEW FORM
CONTRACT WITH: Clark Land Office
(Contractor/Consultant)
CONTRACT FOR: Undie Road Emergency Relocation project
I (r-,- /V I
TXRM: Decernher 31., 2019
COUNTY DEPARTMENT: Public Works
For More Information Contact: John Wa and JUL 12 2616
Contact Phone #: (360) 385-9377 jZa 0 Crt r
.- I R W No, P V 14mr ;k r
RETURN TO: John Wayand RETURN BY: 7/ MMISSIONERS
(Person in Department) (Date)
AMOUNT: $56,710.00 PROCESS:
Revenue: 180000010.333.20.22
Expenditure: 180000010.545.00.65
Matching Funds Required: yes
Sources(s) of Matching Funds FEMA: $209,000.00
Jefferson County:
remainder
Step 1:
10— APPROVED FORM
Comments
REVIEW BY
Review by:
Date Reviewed.
Exempt from Bid Process
X Consultant Selection Process
Cooperative Purchase
Competitive Sealed Bid
Small Works Roster
Vendor List Bid
RFP or RFQ
❑ Other
Returned for revision (See Comments)
Step 2: REVIEW BY PROSECUTIN ATTOR EY
Review by: y_______
Date Reviewed:�� �zc
APPROVED AS TO FORM ❑ Returned for revision (See Comments)
omments
Step 3: (If required) DEPARTMENT MAKES REVISIONS AND RESUBMITS TO RISK MANAGEMENT AND
PROSECUTING ATTORNEY
Step 4: CONTRACTOR/CONSULTANT SIGNS APPROPRIATE NUMBER OF ORIGI���n1L�'�
Step 5: SUBMIT TO BOCC FOR APPROVAL :116
Submit originals and 7copies of Contract, Review Form, and Agenda Bill to BOCC Office._ -
Place "Sign Here" markers on all places the BOCC needs to sign.
MUST be in BOCC Office by 4:30 p.m. TUESDAY for the following Monday's agenda. JEFF
(This form is to stay with the contract throughout the contract review process and accompany Czll.), v r)NEY
rev. 6/10/2013