HomeMy WebLinkAbout090616_ca03Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, P.E.
Public Works Director/County Engineer fb ��inS
Agenda Date: September 6, 2016
Subject: Transfer Station &t MRW: Prep and Paint Project
Execution of Contract Change Order #1
County Project No.: 401 594 1982
Statement of Issue: Execution of Change Order #1 to the Contract for Construction
with Mattila Painting, Inc., of Monroe, WA, for construction services at the Transfer
Station Et MRW: Prep and Paint Project.
Analysis/Strategic Goals/Pro's Et Con's: Necessary additions to construction work.
Including welding repairs to structural steel.
Fiscal Impact/Cost Benefit Analysis: With the addition of $13,336.15, the new
contract amount will be $309,545.83. This project is funded with local funds.
Recommendation: We recommend that this Contract Change Order #1 be signed by
the BoCC. Please sign all three (3) Change Order originals and return two (2) originals
to Public Works, retaining one original for your records.
Department Contact: Gordon D. Ramstrom, Architectural Projects Planner, 385-9380
Reviewed By:
Philip Mo t Admini r
T15d��e4-
Date
U
JEFFERSON COUNTY
Sheet 1 of 4
DEPARTMENT OF PUBLIC WORKS
change
Transfer Station & MRW: Prep and Paint
Order 1
Date 29 -Aug -16
CHANGE ORDER #1
Number
Ordered by County Engineer under terms of
Fx Contract documents
Contract No 401 594 1982
Change proposed by Contractor
To
Mattila Painting, Inc
Endorsed by
Mattlla Painting, Inc
ATTN Brian Forstie
14911 Chain Lake Rd PMB #443
Contractor Firm Name
/-?.
23 14
Monroe, WA 98272
Project Title
— ,7---�
A;tureMDar
"1
Tale
Consent given by Surety (when required)
Transfer Station & MRW Prep and Paint
By
Attorney -in fact Date
You are directed to perform the
following described work upon receipt of an approved copy of this change order
COP No DAYS ADDED COST WSST @ 9 0 % COST W/ WSST
COP #1 0
$ 1,95000 $ 17550 = $ 2,12550
COP #2 10
$ 4,78500 $ 43065 = $ 5,21565
COP #3 0
$ 5,50000 $ 49500 = $ 5,99500
TOTAL ADD 10
$ 12,235 00 $ 1,101 15 = $ 13,336 15
All work matenals and measurement
to be in accordance with the provisions of the specifications and
special provisions for the type of construction involved
ORIGINAL
CURRENT
ESTIMATED
ESTIMATED
CONTRACT
CONTRACT
NET CHANGE
CONTRACT TOTAL
AMOUNT
AMOUNT
THIS ORDER
AFTER CHANGE
$296,20968
$296,20968
13,336 15
$309,54583
ORIGINAL CONTRACT
CURRENT
CONTRACT TIME
NEW CONTRACT
COMPLETION DATE
CONTRACT TIME
CHANGE (Add/Del)
ME
12 -Sep -16
Seventy days
Add 10 days
2316
Tep-
APPROVAL RECOMMENDED
OMMENDED
- �PRV
A in
Project Mari 2ger ( I
Date Comity En weer Date
APPROVR M ENDED
APPROVED
u t
Engineeringrvic eager
Date Clair Jefferson County Commissioners Date
U
MATTILA PAINTING, INC.
14911 CHAIN LAKE ROAD, PMB 443
MONROE, WA 98272
LIC. # MATTIPI122CA
PHONE: (360) 863-0609
FAX: (360) 863-0403
EMAIL: bforstie@frontier.com
CHANGE ORDER PROPOSAL [
DATE: 7-25-16
JOB NAME: Jefferson County Transfer Station
ATTENTION: Gordon Ramstrom
CHANGE ORDER DESCRIPTION:
1) Pressure washing of the interior surface of the existing wall panels To be done following
the completion of the painting in this building No additional days to be added to the
contract period for this work
PRICE: $1,950.00 + 175.50 (9.0% sales tax) = $2,125.50
EXCLUSIONS:
1) Disposal of water
TAX: Included
Thanks,
Brian Forstie
Cell: 425-344-6497
MATTILA PAINTING, INC.
14911 CHAIN LAKE ROAD, PMB 443
MONROE, WA 98272
LIC. # MAITIPI122CA
PHONE: (360) 863-0609
FAX: (360) 863-0403
EMAIL: bforstie@frontier.com
CHANGE ORDER PROPOSAL #2
DATE: 8-24-16
JOB NAME: Jefferson County Transfer Station
ATTENTION: Gordon Ramstrom
CHANGE DESCRIPTION:
1) Provide labor and materials for column reinforcement repairs per details provided by JCPW
Includes prep for new welds, and prep and primer after repairs are complete In addition,
Intermediate and Finish coats of specified paint system Work requires additional travel to site
location The column repairs can be scheduled during the week of 8/29, and the prep and primer
to the repaired areas may take place following completion of the welding Welding is by Lincoln
Welding Welding work to be done outside of normal Transfer Station business hours
EXCLUSIONS: NA
Thanks,
Brian Forstie
Cell: 425-344-6497
Base
Mark up
Lincoln
$1,98500
$397.00
$2,382.00
Prep and primer
$1,35300
$1,353.00
Finish Painting
$1,050.00
$1,050.00
Pretax subtotal
$4,785.00
WSST
$ 43065
TOTAL
$5,215.65
EXCLUSIONS: NA
Thanks,
Brian Forstie
Cell: 425-344-6497
MATTILA PAINTING, INC.
14911 CHAIN LAKE ROAD, PMB 443
MONROE, WA 98272
LIC. # MATTIPI122CA
DATE: 8/26/16
PHONE: (360) 863-0609
FAX: (360) 863-0403
EMAIL: bforstie@frontier.com
CHANGE ORDER PROPOSAL #3
JOB NAME: Jefferson County Transfer Station
ATTENTION: Gordon Ramstrom
CHANGE ORDER DESCRIPTION: Column Cover Modifications & Reinstall
1) Provide labor and materials to modify & reinstall column covers per proposal request from
JCPW dated Aug 25, 2016 Provide separate mobilizations for prep and painting out of
sequence
Thanks,
Brian Forstie
Cell: 425-344-6497
1 OF1
Base
Mark up
Lincoln Welding
$2,50000
$3,000.00
_$50000
MPI
Labor
$1,28000
Travel
$95000
Overhead and
profit
$77000
Subtotal MPI
$3,00000
$3,00000
Credit from base bid
contract
($50000)
($50000)
Net MPI cost C 0 #1
$2,500.00
Pre-tax subtotal
$5,50000
WSST
$49500
TOTAL C 0 #1
$5,99500
Thanks,
Brian Forstie
Cell: 425-344-6497
1 OF1