From: Monte Reinders, P.E., Public Works Director/County Engineer Z2_
Agenda Date: November 28, 2016
Subject: Change Order #3
Undie Road Emergency Relocation Project 180-2007-0
Statement of Issue: Execution of Change Order #3 for the above referenced project.
Analysis/Strategic Goals/Pro's £t Con's: This change order reduces the amount of guardrail
from the plan quantity, specifies steel guardrail posts, changes post length in some areas, and
updates pricing.
Fiscal Impact/Cost Benefit Analysis: Estimated credit to County of $11,058. Project is on
budget and is approximately 98% complete.
Recommendation: Public Works recommends that the Board approve Change Order #3 by
signing all three attached forms and returning to Public Works for further processing.
Department Contact: Monte Reinders, P.E., County Engineer, 385-9160
Reviewed By:
Hip Morley,(9iJrMty Administrator
Date
JEFFERSON COUNTY
Sheet 1 of 1 DEPARTMENT OF PUBLIC WORKS Change
3
Dale: 1 111 5/201 6 CHANGE ORDER Order No.
Ordered by County Engineer under terms of
OX Section 1 - 04. 4 of the Standard Specifications 18020070
Contract No.
Change proposed by Contractor To:
— --- — interwest Construction, Inc.
Endorsed by: Interwest Construction, Inc. 609 North Hill Blvd.
Contractor Firm Name Burlington, WA 98233
_A 1 1S 0
I I Dstd
Title
Consent given by Surety: (when required) Project Title: Undie Road Emergency
Relocation
Attorney-in-fact Date
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
Reduce Item 20 Beam Guardrail Type 31 quantity to 550 I.f.
Reduce Item 21 to 2 Type 10 Anchors.
Updated pricing: Item 20: $53.04 per Lf. & Item 21: $1,277.29 per each
Estimated change: -$11,058.27
Delete 1 working day from contract.
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
ORIGINAL
CURRENT
ESTIMATED
ESTIMATED
CONTRACT
CONTRACT
NET CHANGE
CONTRACT TOTAL
AMOUNT
AMOUNT
THIS ORDER
AFTER CHANGE
$905,310.00
$927,504.69
-$11,058.27
$916,446.42
ORIGINAL CONTRACT
CURRENT CONTRACT
CONTRACT TIME
NEW CONTRACT
TIME (days)
TIME (days)
CHANGE (Add/Del)
TIME (days)
70
74
-1
73
APPROVAL RECOMMENDED APPROVAL COMMEND D
a
Project Manager Date County En ate
APPROVAL RECOMMENDED APPROVED
❑ a
Engineering Svcs. Manager Date Chair, Jefferson County Commissioners Date