HomeMy WebLinkAboutMLA08-00509 TRAFFIC IMPACT ASSESSMENT t !
DEC 2 3 203:
TRAFFIC IMPACT ASSESSMENT
TALA POINT
JEFFERSON COUNTY, WASHINGTON
December 2008
Prepared for:
OPG Properties LLC
GERALYN REINART, P.E.
159 DENNY WAY, # 1 1 1
SEATTLE, WASHINGTON 98109
(206) 285-9035
LOG ITEM
QE I of 7
r y
TRAFFIC IMPACT ASSESSMENT
TALA POINT
JEFFERSON COUNTY, WASHINGTON
Introduction/Executive Summary
The purpose of this assessment is to summarize the anticipated
transportation impacts resulting from the development of a 54-lot single-
family residential development. This report has reviewed the current traffic
conditions adjacent to the site, the proposed action and its impacts to the
transportation system, and developed appropriate mitigation, as
necessary, per Staff comments.
The subdivision would generate just over 500 new weekday trips and just
under 300 new weekend daily trips. Access to the subdivision would be
from Paradise Bay Road at East Ludlow Ridge Road and from an existing
logging road approximately 1 150 feet west of the existing East Ludlow
Ridge Road. Three intersections were reviewed in this analysis, two of
which are under the County's jurisdiction, and one under the control of
the Washington State Department of Transportation (WSDOT). Both
County intersections are currently operating at good levels of service, and
will continue to do so upon completion of the project. The WSDOT
intersection has some operating deficiencies, but the project's impact to
this location will be minimal.
Specific details on the project and the analysis of its impacts can be found
in the subsequent sections. In general, the project will have a limited
impact on the adjacent transportation system.
Background/Project Description
The proposed Tala Point development is located on the north side of
Paradise Bay Road adjacent to and west of East Ludlow Ridge Road, and
east of the main developed areas of Port Ludlow. The Tala Point
preliminary plat is for the subdivision of the parcel for construction of 54
single-family residences. Access to the plat will be from Paradise Bay Road
at East Ludlow Ridge Road and from an existing logging road
1
approximately 1 150 feet west of East Ludlow Ridge Road. East Ludlow
Ridge Road will serve 44 of the 54 lots. The existing logging road access to
the west of East Ludlow Ridge Road would serve 8 lots. Two lots, located
along the water near the northwesterly portion of the property, would be
provided access from an existing access easement that travels diagonally
to the southwest from these lots and connects to Ludlow Bay Road. East
Ludlow Ridge Road would provide direct access to 14 lots, but driveways
would be shared, i.e., one driveway would serve two lots. These lots are
located along the section of road immediately to the north of Paradise Bay
Road. The remaining 30 lots would be served from a new roadway that
would extend westerly from East Ludlow Ridge Road and then looping
back northeasterly into East Ludlow Ridge Road near the northerly property
line. This northerly connection would be limited to emergency access only.
(See site plan for roadway layout.)
The area near the site includes undeveloped parcels and limited residential
development. The site is currently zoned "Rural Residential 1 :5". It was re-
zoned in 2005 from "RR 1 :20" to the current zoning. A vicinity map of the
area is shown on Figure 1 and a reduced copy of the site plan has been
attached.
The remainder of this report will analyze the effects of the development of
the subject property and the traffic-related impacts that can be expected
on the adjacent intersections.
Existing Conditions
The proposed development will primarily impact East Ludlow Ridge Road
and Paradise Bay Road, with a very minor impact to Ludlow Bay Road. The
following describes these roadways, existing traffic volumes, and current
operating conditions.
1. Roadways
Paradise Bay Road is a minor collector that provides a connection
between SR-104 just west of the Hood Canal Bridge and Oak Bay Road
within the Port Ludlow community. The roadway is two lanes wide and is
characterized by fairly gentle horizontal and vertical curvature. The posted
speed varies from 25-mph to 50-mph, with a 40-mph speed posted within
most of the Port Ludlow community and adjacent to the proposed project
site. The roadway is 22 feet wide with shoulders varying from about
one foot up to ten feet. (The wider shoulder width is typically located at
2
the intersections serving newer developments within Port Ludlow.) The
section of the roadway near Oak Bay Road was recently upgraded and
includes a landscaped median, pedestrian crossings and amenities,
lighting, bus pull-outs and landscaping. The roadway is fronted by
undeveloped parcels, residential lots, and some commercial development
near its intersection with Oak Bay Road. Near the proposed project the
roadway is characterized by a long westbound upgrade and one to two-
foot paved shoulders plus some grass/gravel shoulder and open ditch, with
the adjacent land use mostly undeveloped. The posted speed is 40-mph,
dropping to 30-mph approximately 2000 feet to the east.
East Ludlow Ridge Road is a private local access that extends northerly
from Paradise Bay Road for several thousand feet. The roadway is gated
just north of Paradise Bay Road and is approximately 15 feet wide. The
roadway currently serves approximately 15 residences.
Ludlow Bay Road is a local access roadway that extends several thousand
feet northeasterly from Paradise Bay Road and serves approximately 50
residences. The roadway ranges from approximately 15 to 18 feet in
pavement width and is characterized by horizontal and vertical curvature
with no shoulders and open ditches. The posted speed is 25-mph.
Transit/Non-Motorized Facilities
Transit service in Jefferson County is provided by Jefferson Transit. Port
Ludlow is served by the Port Ludlow/Poulsbo/Tri Area #7 route, which
provides service between Port Townsend and Poulsbo via the Tri Area and
Port Ludlow. Service is provided daily, although service is reduced on the
weekend. Weekday service begins at approximately 6:00 AM and
continues until approximately 6:00 PM, at approximately one and a half to
four hour headways. Weekend service is limited to one AM and one PM
run in each direction.
Non-motorized facilities adjacent to the project site are limited, due to the
rural/semi-rural character of the area. Paradise Bay Road is considered an
on-road bicycle route between Oak Bay Road and SR-104. The section
along and near the project frontage has limited shoulder width and cyclists
must share the roadway with vehicles. Further to the west, within the Port
Ludlow community, some paved pathways have been constructed
through the residential areas. No trails or pathways are currently
constructed through the project site.
3
3. Traffic Volumes
Daily traffic count data was available from Jefferson County and WSDOT,
with additional count data collected for this project per the request of
County Staff. (Field data are attached for the counts completed with this
assessment.) The WSDOT counts are from 2007 and the Jefferson County
counts are from 2008. Furthermore, extensive traffic count data is collected
yearly within Port Ludlow as part of its monitoring program and is
referenced herein for the year 2007. PM peak hour counts at the
intersections of Paradise Bay Road/SR-104, Paradise Bay Road/Oak Bay
Road, and East Ludlow Ridge Road/Paradise Bay Road were also available
or completed for this analysis.
Figure 2 shows daily and weekday PM peak hour volumes at the
intersections. Daily volumes along Paradise Bay Road are moderately low,
with much higher volumes present along SR-104. The existing (weekday)
volume along East Ludlow Ridge Road is very low (less than 150 vehicles
per day).
While weekend volumes are not typically included or reviewed in the traffic
impact assessment, the Port Ludlow area is recreationally-oriented and
traffic volumes at some locations can be higher on the weekend than the
weekday. As such, Figure 2A shows the estimated weekend peak hour
volumes. The SR-104/Paradise Bay Road and Paradise Bay Road/Oak Bay
Road counts are from the 2007 Port Ludlow Monitoring Program and the
Paradise Bay Road/East Ludlow Bay Road is estimated from the 2008 daily
and weekday counts completed as part of this assessment.
A comparison of historical traffic count data shows that the WSDOT counts
had remained steady or dropped slightly since 2004. This same pattern was
also noted for the Jefferson County counts. Jefferson County has indicated
a historical annual traffic growth rate of 1 .94% to 3.34% along Paradise Bay
Road in its most recent Comprehensive Plan, which is higher than recent
history.
4. Traffic Accidents
Traffic accident data were provided by Jefferson County and WSDOT
(Washington State Department of Transportation) for Paradise Bay Road
between Oak Bay Road and SR-104. The following table summarizes the
accident frequency for this section of the roadway for the years 2005, 2006,
2007 and 2008 (partially complete, WSDOT data only).
4
TABLE 1
ACCIDENT HISTORY
PARADISE BAY ROAD
Accident Type
Property
Location/Year Damage Injury Fatality Total
at Oak Bay Road (MP 0.00)
2005 0 0 0 0
2006 0 0 0 0
2007 0 0 0 0
between Oak Bay Road and
Spinnaker Place (MP 0.00-0.45)
2005 1 0 0 1
2006 0 0 0 0
2007 1 0 0 1
between Spinnaker Place and
Edgewood Drive (MP 0.45-1.03)
2005 1 0 0 1
2006 2 0 0 2
2007 2 0 0 2
between Edgewood Drive and
Teal Lake Road (MP 1.03-1.53)
2005 0 0 0 0
2006 0 0 0 0
2007 0 0 0 0
between Teal Lake Road and
Milepost 2.00 (MP 1.53-2.00)
2005 0 0 0 0
2006 0 0 0 0
2007 0 1 0 1
between Milepost 2.00 and
Ludlow Ridge Rd. (MP 2.00-2.58)
2005 1 2 0 3
2006 1 0 0 1
2007 4 1 0 5
At Ludlow Ridge Road (MP 2.58)
2005 1 0 0 1
2006 0 0 0 0
2007 0 0 0 0
between Ludlow Ridge Road and
Pine Way(MP 2.58-3.10)
2005 0 2 0 2
2006 0 1 0 1
2007 2 0 0 2
between Pine Way and Alder
Street(MP 3.10-3.51)
2005 1 0 0 1
2006 0 0 0 0
2007 0 0 0 0
5
TABLE I (CON't.)
ACCIDENT HISTORY
PARADISE BAY ROAD
Accident Type
Property
Location/Year Damage Injury Fatality Total
between Alder Street and
Bywater Way (MP 3.51-4.31)
2005 0 1 0 1
2006 0 1 0 1
2007 0 0 0 0
between Bywater Way and
Seven Sisters Road (MP 4.31-5.34)
2005 0 1 0 1
2006 1 0 0 1
2007 0 0 0 0
Seven Sisters Road and Paradise
Bay Road (MP 5.34-6.00)
2005 2 1 0 3
2006 0 0 0 0
2007 0 0 0 0
Paradise Bay Road at SR-104(MP
6.00)
2005 4 1 0 5
2006 0 0 0 0
2007 0 1 0 1
2008* 1 0 0 1
* - partially complete; WSDOT records
The accident data showed that all but one of the reported collisions along
Paradise Bay Road involved either vehicles that lost control along a curve
and left the road, drivers falling asleep and left the roadway, or
striking/avoiding an animal and leaving the road. The majority of these
occurred on a wet or icy pavement condition. One collision was reported
at the Paradise Bay Road/East Ludlow Ridge Road intersection and
involved a vehicle making a left-turn and being struck by an oncoming
vehicle. Injuries were reported in about a third of the accidents.
Four of the seven reported collisions at the SR-104/Paradise Bay Road
intersection involved vehicles entering at an angle and typically were
attributed to failure to grant the right-of-way. The remaining collisions
included a rear-end collision, a left-turning collision, and an improper u-
turn.
6
5. Level of Service
Capacity analyses for the weekday and weekend peak hours were
conducted at Paradise Bay Road/Oak Bay Road, Paradise Bay Road/
Ludlow Ridge Road, and Paradise Bay Road/SR-104 intersections per the
request of Jefferson County Staff in order to determine the current level of
service. The Paradise Bay Road/Oak Bay Road intersection is controlled by
stop signs in all directions. The Paradise Bay Road/Ludlow Ridge Road is
stop controlled in the southbound direction, i.e. traffic on Paradise Bay
Road has the right-of-way. The Paradise Bay Road/SR-104 intersection is
controlled by stop signs in the north/south directions, i.e. traffic on SR-104
has the right-of-way.
"Level of service" is a common term used in the Traffic Engineering
profession that is defined as a qualitative measure describing operational
conditions within a traffic stream, and its perception by motorists and/or
passengers. These conditions are usually described in terms of such
factors as speed and travel time, freedom to maneuver, traffic
interruptions, comfort and convenience, and safety. Six levels of service
are designated, ranging from "A" to "F", with level of service "A"
representing the best operating conditions and level of service "F" the
worst. Jefferson County considers level of service "C" or better
acceptable in areas outside the urban line and level of service "D" or
better acceptable in areas within the urban lines and along urban/tourist
corridors.
Calculations for the level of service analyses were conducted using the
McTrans Highway Capacity Software version 4.1 d/e based on the 2000
Highway Capacity Manual. The following table shows the current levels of
service for the critical movements on the approaches. The critical
movements are typically those movements that are controlled by a stop
or yield sign or left-turn movements from the major street which must yield
to on-coming traffic. Calculations for the level of service analyses have
been attached. The peak hour volumes shown on Figures 2 and 2A were
used in these analyses.
7
TABLE 2
EXISTING LEVELS OF SERVICE
NORTH- SOUTH- EAST- WEST-
WEEKDAY BOUND BOUND BOUND BOUND OVERALL
Paradise Bay Road/ LOS A LOS A LOS A LOS A LOS A
Oak Bay Road 8.8 sec. 8.7 sec. 8.8 sec. 9.9 sec. 9.2 sec.
Paradise Bay Road/ LOS A LOS A
Ludlow Ridge Road N.A. 9.2 sec. 7.5 sec. N.A. N.A.
Paradise Bay Road/ LOS B LOS F LOS A LOS A
SR-104 13.3 sec. 77.1 sec. 9.3 sec. 8.7 sec. N.A.
WEEKEND
Paradise Bay Road/ LOS A LOS A LOS A LOS A LOS A
Oak Bay Road 8.4 sec. 8.9 sec. 8.5 sec. 9.5 sec. 8.8 sec.
Paradise Bay Road/ LOS A LOS A
Ludlow Ridge Road N.A. 8.9 sec. 7.4 sec. N.A. N.A.
Paradise Bay Road/ LOS E LOS F LOS A LOS A
SR-104 37.6 sec. >100 sec. 9.4 sec. 11.4 sec. N.A.
N.A.-not applicable (i.e., calculation not provided for specific analysis or no volume
recorded during the peak hour)
Note: Paradise Bay Road considered the east/west roadway at the Oak Bay Road and
Ludlow Ridge Road intersections, and the north/south roadway at the SR-104
intersection.
Where:
LOS Delay
A < 10 seconds
B > 10 & < 15 seconds
C > 15 & < 25 seconds
D > 25 & < 35 seconds
E >35 & < 50 seconds
F > 50 seconds
(for unsignalized intersections)
Table 2 shows the level of service results for the weekday and weekend
peak hours indicating that all movements at the Paradise Bay Road/Oak
Bay Road and Paradise Bay Road/East Ludlow Ridge Road intersections
are operating at level of service "A" on both the weekday and weekend,
with little delay experienced by the critical movements. The SR-104/
Paradise Bay Road intersection has side street movements operating at
level of service "E" or "F" during both the weekday and weekend peaks.
This condition has been reported for over a decade during the weekend
peak, and off and on over the past decade during the weekday peak
hour, and is a result of the high volume of traffic traveling along SR-104 and
the limited number of available gaps to allow side street traffic to enter the
highway.
8
6. Roadway Projects
Limited roadway improvement projects are proposed in the vicinity of the
proposed action by either Jefferson County or WSDOT. WSDOT is currently
involved in retro-fitting and replacing the Hood Canal Bridge to provide a
wider eastern half and new approach sections. An eight-foot continuous
shoulder will also be provided across the entire section upon completion.
Completion of the replacement and retro-fitting is planned for late 2010.
Jefferson County has improvements proposed along Paradise Bay Road
between milepost 0.37 and 1 .53, which would extend the recent
improvements from the Port Ludlow commercial area to Teal Lake Road.
The project would involve shoulder paving and an overlay. Engineering is
planned for 2010-2011 , with construction planned for 2012, pending
funding.
Future Conditions
The development of the subdivision will generate new traffic onto the
adjacent transportation system. The subsequent sections summarize the
impacts associated with the proposed action.
1. Trip Generation
The proposed subdivision would generate new traffic onto the adjacent
roadways. The ITE Trip Generation manual (published by the Institute of
Transportation Engineers, 2003, 7th Edition) is typically used to estimate the
number of trips expected to be generated by a development for the
weekday peak hour condition. Discussions with the project applicant have
indicated that this project will be similar, demographically, as existing
development within the Port Ludlow community. Thus, buyers of the lots
are expected to be "empty-nesters", retirees, or second home buyers and
are likely to have trip generation rates similar to those residents living within
the Port Ludlow community. As such trip generation that has been utilized
for development within Port Ludlow will also be utilized in this assessment, in
addition to the ITE data.
Data collected as part of the yearly Port Ludlow traffic monitoring program
includes trip generation information. Recent development proposals
within Port Ludlow have utilized weekend trip generation data from the
2002 program. As noted earlier, weekend traffic volumes along some of
the roadways in the area (specifically, SR-104) are higher than those
9
present on a weekday. As such, the weekend trip generation data from
the 2002 Port Ludlow program has been used for consistency purposes for
the weekend conditions. Table 3 summarizes the weekday trip generation
(using traditional ITE values) and weekend trip generation (using Port
Ludlow data) associated with the proposed action.
TABLE 3
ESTIMATED TRIP GENERATION
TALA POINT
Trip Rate Peak Hour Trips
Daily/Peak Hour Daily Trips In/Out Total
Weekday 9.57/1.01 517 35/20 55
Weekend 5.40/0.66 292 19/17 36
(Note: the ITE weekday daily rate corresponds very closely with the actual count data
collected along East Ludlow Ridge Road for the existing 15 homes using the roadway.)
Table 3 shows that although some of the traffic volumes on the adjacent
roadways may be higher on the weekend, the number of trips associated
with residential development in the area is not the contributing factor for
these higher volumes, since weekend trip generation is much lower than
the weekday rates.
2. Trip Distribution/Assignment
The estimated trip distribution/assignment for the weekend daily and peak
hour volumes for the site is shown on Figure 3, with the weekend volumes
shown on Figure 4. The distribution of traffic is based on current travel
patterns, a review of the existing roadway system and activity centers, prior
studies, and the proposed land use. Many of the trips associated with the
proposed action will be destined to and from activities/areas within the
Port Ludlow community, i.e., the commercial area, the marina, golf course,
other housing areas and/or could include social trips within the community.
Reasons for traveling beyond the Port Ludlow community include major
shopping, medical/health care, or social/recreational opportunities, for
example. Some of the trips would require traveling on SR-104 to reach the
ultimate destination, with many trips using Oak Bay Road or Beaver Valley
Road to access the Tri-Area or Port Townsend areas. The proposed action
would have its greatest traffic-related impact on Paradise Bay Road to and
from the west of the project site.
10
3. Traffic Volumes
Build-out of the project is expected over the next five years, i.e., late 2013/
early 2014. Figures 5 and 5A show the projected daily and weekday PM
peak hour traffic volumes for the year 2013 with and without the project
trips. Figures 6 and 6A show the projected weekend peak hour volumes
with and without the project.
As noted earlier, traffic volumes in the area have remained fairly stable or
decreased slightly over the past few years, although it is probable that
volumes will increase again over the next five years once economic
conditions improve. As such, the existing volumes were increased from
1 .55% to 2.79% annually for those locations along Paradise Bay Road and
3.76% along SR-104 for the 2013 volumes to account for miscellaneous
background traffic. These rates are consistent with most recent
Comprehensive Plan projections for the vicinity. Additionally, traffic
associated with pipeline development trips was also added into the
existing volumes. The "pipeline trips" consist of the traffic associated with
the developments in Port Ludlow including the Resort, Olympic Terrace 2,
and Ludlow Cove 2. The combination of the annual growth rate and
pipeline trips provide for a conservative approach to the analyses.
The "without project" conditions are the volumes shown on Figures 5 and
5A. The trips associated with the proposed project were added into the
volumes shown on Figure 5 and 5A to produce the volumes shown on
Figures 6 and 6A. (Note: the entering/exiting volumes shown on Figures 6
and 6A for East Ludlow Ridge Road include slightly higher volumes than
would occur from the 44 lots using this access. These additional volumes
would account for potential development of four lots on the DNR property
and a few remaining lots on Tala Point or the possibility of the eight lot
cluster to the west using East Ludlow Ridge Road as an optional access.
Either case would be insignificant with respect to the traffic impacts at the
intersection.)
4. Level of Service
Level of service calculations were conducted again for the three
intersections previously reviewed. It was assumed for purposes of analysis
that no changes in the geometric conditions at the intersections would
occur over the next five years. The results of the future conditions
without the project trips are shown in Table 4, with Table 5 showing the
results for the future conditions with the project trips. Peak hour volumes
shown in Figures 5, 5A, 6, and 6A were used in the analyses.
11
TABLE 4
FUTURE LEVELS OF SERVICE
WITHOUT PROJECT
NORTH- SOUTH- EAST- WEST-
WEEKDAY BOUND BOUND BOUND BOUND OVERALL
Paradise Bay Road/ LOS B LOS A LOS B LOS B LOS B
Oak Bay Road 10.9 sec. 9.6 sec. 10.2 sec. 12.3 sec. 11.2 sec.
Paradise Bay Road/ LOS A LOS A
Ludlow Ridge Road N.A. 9.4 sec. 7.5 sec. N.A. N.A.
Paradise Bay Road/ LOS C LOS F LOS B LOS A
SR-104 15.6 sec. >100 sec. 10.0 sec. 9.2 sec. N.A.
WEEKEND
Paradise Bay Road/ LOS A LOS A LOS A LOS B LOS A
Oak Bay Road 9.3 sec. 9.5 sec. 9.3 sec. 10.7 sec. 9.8 sec.
Paradise Bay Road/ LOS A LOS A
Ludlow Ridge Road N.A. 9.0 sec. 7.4 sec. N.A. N.A.
Paradise Bay Road/ LOS F LOS F LOS B LOS B
SR-104 77.7 sec. >l00 sec. 10.3 sec. 13.5 sec. N.A.
TABLE 5
FUTURE LEVELS OF SERVICE
WITH PROJECT
NORTH- SOUTH- EAST- WEST-
WEEKDAY BOUND BOUND BOUND BOUND OVERALL
Paradise Bay Road/ LOS B LOS A LOS B LOS B LOS A
Oak Bay Road 11.2 sec. 9.7 sec. 10.5 sec. 12.8 sec. 11.6 sec.
Paradise Bay Road/ LOS A LOS A
Ludlow Ridge Road N.A. 9.8 sec. 7.6 sec. N.A. N.A.
Paradise Bay Road/ LOS C LOS F LOS B LOS A
SR-104 15.6 sec. >100 sec. 10.0 sec. 9.2 sec. N.A.
WEEKEND
Paradise Bay Road/ LOS A LOS A LOS A LOS B LOS A
Oak Bay Road 9.5 sec. 9.6 sec. 9.4 sec. 11.0 sec. 10.0 sec.
Paradise Bay Road/ LOS A LOS A
Ludlow Ridge Road N.A. 9.2 sec. 7.4 sec. N.A. N.A.
Paradise Bay Road/ LOS F LOS F LOS B LOS B
SR-104 77.7 sec. >100 sec. 10.3 sec. 13.5 sec. N.A.
N.A.-not applicable (i.e., calculation not provided for specific analysis or no volume
recorded during the peak hour)
Note: Paradise Bay Road considered the east/west roadway at the Oak Bay Road and
Ludlow Ridge Road intersections, and the north/south roadway at the SR-104
intersection.
12
Where:
LOS Delay
A < 10 seconds
B > 10 & < 15 seconds
C > 15 & <25 seconds
D >25 & < 35 seconds
E >35 & < 50 seconds
F > 50 seconds
(for unsignalized intersections)
The results of the capacity analyses for the future conditions show only
minor increases in delay resulting from the project trips. All critical
movements (left-turns from the main street and all side street movements)
are expected to operate at level of service "B" or better for the weekday
and weekend peak hours at the Paradise Bay Road/Oak Bay Road and
Paradise Bay Road/East Ludlow Ridge Road intersections. The exception to
the good levels of service is the SR-104/ Paradise Bay intersection where the
southbound movement would be at level of service "F" during both the
weekday and weekend peaks, consistent with current conditions and prior
projections. The impact to this intersection from the proposed project
would be less than ten peak hour trips, which WSDOT does not consider as
significant.
5. Site Access
Paradise Bay Road will provide eventual access to the majority of lots within
the project from the East Ludlow Ridge Road intersection or an existing
logging road intersection about 1 150 feet west of East Ludlow Ridge Road.
(Note: two shoreline lots, located near the northwesterly portion of the
property would be provided access from an existing access easement that
travels diagonally to the southwest from these lots and connects to Ludlow
Bay Road. The traffic-related impacts on Ludlow Bay Road from these two
lots would be insignificant.)
East Ludlow Ridge Road would provide direct access to 14 lots, with the
remaining 30 lots served from a new roadway that would extend westerly
from East Ludlow Ridge Road and then extend northeasterly and looping
back into East Ludlow Ridge Road near the northerly property line. Near its
intersection with Paradise Bay Road, East Ludlow Ridge Road would have a
projected daily traffic volume of approximately 650 vehicles per day.
Beyond the new intersection that would serve the 30 lots, the volume
would drop below 150 vehicles per day. The loop roadway serving the 30
lots would have a projected daily volume of fewer than 300 vehicles per
13
day. The existing logging road would serve eight lots and have a projected
daily traffic volume of less than 100 vehicles per day.
The estimated peak hour volumes at the Paradise Bay Road/East Ludlow
Ridge Road intersection were shown on Figures 6 and 6A. The prior
capacity analyses indicate that the access should operate at a good
level of service with level of service "A" present during the peak hours. As
noted earlier, the entering/exiting volumes shown on Figures 6 and 6A for
East Ludlow Ridge Road include slightly higher volumes than would occur
from the 44 lots using this access. These additional volumes accounted for
potential development of four lots on the DNR property and a few
remaining lots on Tala Point, or the possibility of the eight lot cluster to the
west using East Ludlow Ridge Road as an optional access. As such, this
intersection would be impacted by the greatest number of project trips
and represent the more critical of the site accesses.
The need for left-turn storage on Paradise Bay Road at the East Ludlow
Ridge Road access was reviewed using Figure 910-12a from the WSDOT
Design Manual (figure has been attached). Based on the anticipated
volume of left-turns from Paradise Bay Road, left-turn storage is not
recommended. The need for right-turn storage on Paradise Bay Road
was also reviewed using Figure 910-15 from the WSDOT Design Manual.
Based on the projected volume of right-turns at this location, no additional
storage is needed.
The entering and stopping sight distances at the proposed accesses to
Paradise Bay Road were field measured. The approximate distances
were as follows:
APPROXIMATE MEASURED SIGHT DISTANCES
Site Accesses to Paradise Bay Road ESD SSD
At East Ludlow Ridge Road
From the east -- 560'
From the west -- >1000'
To the east 560' --
To the west >1000' --
At Logging Road Access
From the east -- >1000'
From the west -- 300'
To the east >1000' --
To the west 320' --
Note: ESD (entering sight distance) measured 10 feet back from the traveled way with
an eye height of 3.5 feet and an object height of 3.5 feet; 2.0-foot object height used
for SSD (stopping sight distance), as allowed under AASHTO.
14
Both horizontal and vertical curvature are present along Paradise Bay
Road (approximate 6-7% westbound upgrade cresting near the logging
road access and a horizontal curve east of East Ludlow Ridge Road)
which limit the available sight distance. The posted speed on Paradise
Bay Road is 40-mph. Assuming a 50-mph design speed, 425 feet of
stopping sight distance is required and 555 feet of entering sight distance
is required per AASHTO. Due to the presence of the grade, an adjustment
to the stopping sight distance is appropriate in both directions at East
Ludlow Ridge Road and to/from the east at the logging road access,
resulting in approximately 385 feet of stopping sight distance required in
the upgrade and 510 feet in the downgrade. (Note: per AASHTO, grade
adjustment is not needed for entering sight distance. Furthermore, the
grade is flattening from the west at the logging road access and
therefore an adjustment does not appear to be needed for the stopping
sight distance from the west.) Based on the approximate field
measurements, the entering sight and stopping distances to/from the east
and west at East Ludlow Ridge Road are met, as well as to/from the east
at the logging road access. However, neither entering nor stopping sight
distance is met to/from the west at the logging road access.
Although sight distance is adequate for the existing East Ludlow Ridge
Road intersection at Paradise Bay Road, other geometric conditions exist
along East Ludlow Ridge Road that are proposed to be upgraded to serve
the proposed development. Specifically, realignment of the horizontal
curves on the approach to Paradise Bay Road is proposed by relocating
the intersection approximately 260 feet to the east of the existing
intersection location. Both entering and stopping sight distance were
checked at the relocated intersection and exceeded 1000 feet to/from
the east and west. Thus, the proposed relocated intersection would meet
sight distance requirements.
Project Impacts
Development of Tala Point would generate new traffic onto the adjacent
roadway system. The project site is located to the east of the major activity
areas within Port Ludlow, and Port Ludlow is expected to attract many of
the future trips generated by the residents of Tala Point. The number of
trips associated with Tala Point would have a limited impact on the
adjacent County roadways. Both the weekday and weekend traffic
impacts were reviewed since the project would generate more traffic
15
during the week, but traffic volumes in the Port Ludlow area can be higher
on the weekends, especially during the summer along SR-104.
The new single-family residences would generate just over 500 weekday
trips, with 55 new trips during the peak hour. Weekend traffic would be
much lower. The main impact from the project would be to Paradise Bay
Road which would provide access to other arterials or to social,
entertainment/recreational or shopping activities. The additional volumes
generated by the project are within the capacities of the intersections and
roadways in the area. The major County intersection that will be
impacted by the development (i.e. Paradise Bay Road/Teal Lake Road) will
operate at level of service "B" or better in the future, with or without the
project. The one exception is at the Paradise Bay Road/SR-104 intersection
where the side street movements are, or will be at level of service "F", with
or without the project. This condition has been documented for the past
decade and the limited number of project trips through the intersection
is not considered significant by WSDOT and therefore not subject to
mitigation.
The majority of lots will be served from either East Ludlow Ridge Road or an
existing logging road. The East Ludlow Ridge Road/Paradise Bay Road
intersection would be impacted by the majority of project trips and is
expected to operate acceptably. Turn storage on Paradise Bay Road
would not be required to serve the site access(es) per WSDOT guidelines
and sight distance is adequate for a 50-mph design speed.
The most notable deficiency associated with the proposed action is the
entering and stopping sight distance to/from the west at the existing
logging road access. Potential options to mitigating this deficiency include
the following:
• Limiting the entering/exiting movements to right-turns only.
• Cutting the vertical curve sufficient to provide adequate sight
distance.
• Providing an internal connection between the eight lots served from
the logging road through the DOE parcel sandwiched between the
parcels on the east and west side.
• Providing turn storage on Paradise Bay Road for entering left-turns
and a as a refuge area for exiting left-turns.
All of these options have advantages and disadvantages that require
further analysis for both construction feasibility and cost.
16
Conclusions/Recommendations
The development of Tala Point will generate additional traffic onto the
existing transportation system. Further discussion with County Staff is
recommended with respect to the sight distance deficiency at the
proposed logging road access. Due to the limited off-site impacts
associated with the project, no other mitigation is recommended.
17
ATTACHMENTS
18
Site Plan/Figures
2 .d Z6i76- ILL-sat, iJag d{,G :Pi Rn F? pati
I
il,.1
Project Site
Stiranso -u:
N.T.S. ! 7.1:-.1i:::....-;.::::::,:•; :i.::':;:::::4::::: ::1:::::::.. ....:.:,...::.i.•:f:...,:11:iii::::ii:;;:.:1:.1,..1.ci...!:::;;;,:]i::;-1:1.'-i-..;:-.::.;;;. :.; ;;:i..,.:::::..il.i..isC.:.--,-1....e..........!:...;....:..;'..::..:,..mi ... IP* - •::..,:.'..:::.........:,....•,-..,...".s.'.....:5:!::::,-:..:;;--_:;;.:,„"jr.:•...:.::...f.-:.:::::-"ii...--:.i:!.1.:;i:.:;;;.:?....e.:..:.::::::::::?:::::::-.71t7:1'::::::"!:,:i"-!..:;;Iic;':1:,:;...........-::::;1:::;:'.:::E.:::-:i-::::..
cc
Zu
/1>2111°.;;;:.::::.'::::::.;:::.:1...:;;;....."1::::::.1:::-...:.;1::::.;;;.;.';:f:':::...... ,r
Ri
.
x..r.�rti
1-77.1.§ViiiZ;;:,i;.. . .-...:.i:y...:...,:.:,:.:,,,,i, 4016
J
p .,23 keig.itri:I.I:::::::::i.:::-.:,::;":....-:-..:..i?i,
.. Ial,
va
•,...jr;„,::_
isL'..
(___72
/ �1
/
/
PROJECT VICINITY MAP
Geralyn Reinert, P.E. FIGURE 1
159 Denny , Tala Point Page
Seattle.WA.Way98109#111 Jefferson County,WA. F-1
E 'd Z6b6— tLL—SZb iaa� d.bq :2T An Ra °art
411 5
6 / `__--6 4<-f`->1
1141 8 1
11 29 33 ( >165 1 123 _. - 124
67 .._43 124 100-=_. 99
,4 28
13 10- --146
184
N.T.S.
lvd��'e, 1
•
L.
1 /
�'
•
., 1
P•a &per !
e., t‘-‘' . L, , \
C $• - Project site
2926 ti g ,
I 140
1
U /.
cc
2138
0 -..
0 N
j
L
0 ti
0 '\.
0
fII -0 �-
•
AO, N / 1 , i
1
a
A.iii i /
2282 I
(-------75
-------•- 13000
h
6 ! 69 1 • SR-104
167 '� "•--•----- .
Y A
0
e 625 _ '_808
4 ( 16000
524//_r515 16
y
3
1
0- .. .->
=cc-average daily traffic
9
roc -pm peak hour volume
EXISTING DAILY & WEEKDAY PM PEAK HOUR VOLUMES
Geralyn Reinart, P.E. FIGURE 2
159 Denny Way,#111 Tala Point Page
Seattle,WA 98109 Jefferson County,WA. F-2
i7 'd a6176- ILL-Sal? i..la9 dSS :2I Rn PP. an
65 5
1O_ ., __ 5 i
7,
4�_ _
1
50
11 29�- -l;> 146 3 69__ 70
65-4----34 91
110 88
/
37
20 15 .—123
175
N.T.S.
is/ 1
,F
/ / •
__ l
d -.- `14 / \\ - a\o
•‘a �Vv
� o ` .
E '.•
Oa
-- - Project site
1
J
•LL
W `
'C.D. 1
m `
•
4 �9-0 •
/: 11 �..
i /
i 1
I.
i
i
105
106 ii
SR-104
0 t
5 700 __ 821
1
970-<\-.->963 15
1
V d,
2 1 —10
12
,oc -peak hour volume
ESTIMATED WEEKEND PEAK HOUR VOLUMES
Geralyn Reinart, P.E. FIGURE 2A
159 Denny Way,#111 Tala Point Page
Seattle,WA. 98109 Jefferson County,WA. F-2A
S 'd a6i76- T LL-S217 I Jecl dcc :71 on rnarr
r ,
14
roc% -Percent distribution
[xx] -Daily volume
xx% -Peak hour volume
N.T.S-
10°i°[52] �'a� I
Local trips- '1s, '
2 in/4 out L. 1 /
y /:
30- ' 1 1.
fid •
• 10 �Jd\O� i i •.\
..1 ( ' To
(../ 5.)[129] s Project site
(13 , [439] �4—
65%� (17 85°k -0 _ I
[336](23) (^) 1
"ti [103] (5
(4) [�
N y \
1
(3) -•'
16
1
la .....
!D -o tt _
I
v /
,0 1 \ /
i
•
(3) i
15%
44] 1
SR-104
ESTIMATED WEEKDAY TRIP DISTRIBUTION/ASSIGNMENT
Geralyn Reinert, P.E- FIGURE 3
159 Denny Way,#111 Tala Point Page
Seattle,WA. 98109 Jefferson County,WA. F-3
9 .d Z6i76- ILL-S2b 1...1an dcc : T on cHarr
• 4
1.1
roc% -Percent distribution
[xx] -Daily volume
xx% -Peak hour volume
N.T.S.
10%(30) �o�j I
Local trips- ',0
2 in/2 out �id I /• :
L
$8� / i
0°u
fid'-- -\--It-a''
(6 < ' a`o� / _'.
0a-1 (4) ..---- O�VJ / ` . \:
/25°f ..-"1 Q i' =gym /
,..0:4- 4)[72] & • Project site
(1 e • -- [848] •
65%k(12) (14 6 3
[19O] 20%4) — I
[58) ) 15%3Ce. (31 /
[44) 1
mTa (3)
m
ro
m -oma
o � ;:
d. l
I
I .
1`0 / ` •1
i
(3)
44) i
— --%(3)
SR-104
ESTIMATED WEEKEND TRIP DISTRIBUTION/ASSIGNMENT
Geralyn Reinert, P.E. FIGURE 4
159 Denny Way,#111 Tale Point Page
Seattle,WA 98109 Jefferson County,WA F-4
L 'd Z6i76- T LL-SZt7 i-la FI dqq :P T An P7 oarr
46 5
7)ilt _ ^ �7 �.
9 4�..- -1
1
32
12 57 262 1 152 _153
96 ! r 70 196 126-L� 125
1, 31
14 11 - . ---219
261
N.T.S.
y /
/ i
1
a
v \.
�� `.` QOML7: li
Oa • �••� -.-/
Project site
/ _
4150 140
J
CN\
^` 2660
W
\W
i.1
0
m 00
a f53
,
V�
,r0 -A s /' �
/ 1
2830 /
99
7. -/‘'- >92 - .-. ,.-` 16225 1
208 _ SR-104
0
7 780 _ _1007
+� r 20180
654 / .-643 ___..,,,19
Y l
4 0- ._g
xx c -average daily traffic
10
-roc -pm peak hour volume
2013 ESTIMATED DAILY & WEEKDAY PM PEAK HOUR VOLUMES
WITHOUT PROJECT
Geralyn Reinart, P.E. FIGURE 5 Tala Point Page
159 Denny Way,#111 9
Seattle,WA. 98109 Jefferson County,WA. F-5
8 •d 26i7G- ILL-sat, i-Ia9 dgq :21 Rn 1'P oan
k i ,
14 71 5
11- ..A----5 8 4�-%k--1 1
12 46 t,:,214 3 86_ 87
K22lB . l73 )
230
N.T.S.
hea/, I
1' —
e,-re,
1 I
% %
.• 1
v-d VJe / 1-.'. .--.742.--'s--..!-
— •\
a4 ..••N OCP.
/• -�
p �.• - -:•- • Project site
t
J
T I:
CC
/
V^'
W t
7
usW
ZY
usr
iii
/ r• ;.
I
1
r 30 /f\-----121 i ` .-
132 --
132i -,- _ - SR-104
Y
0
8 874 t - 1024
1210 L 1202
18
1
2 1 .1,-r•-12
14
-nor -peak hour volume
2013 ESTIMATED WEEKEND PEAK HOUR VOLUMES
WITHOUT PROJECT
Geralyn Reinert, P.E. FIGURE 5A
159 Denny Way,#111 Tale Point Page
Seattle,WA, 98109 Jefferson County,WA. F-5A
Z 'd X6176- ILL-S217 I-Jan dr T : r n sin P7 carr
I
4 "tic r
141 46 25
7_ -:-7 21
9 6
32
12 57 - >272 31 152 _ _ 158
A
105- -.--70 206 156-,/ 125
Y 31
23 16 :-225
r
272
N.T.S.
1-1-a/L I
"ed.,
^lay 1 i
/ i
i
n
V ):./ ' ..N
-- �• �! P° r i
p�
I.,,. .•-......._.,.---
.- ~-V ;•-. Project site
•
4485 - •..—
J 1• 655
i
LL
3100
N
I
15L
a)
In .o
/y
p- 1
.
2875 /
I
f
102 ,
/
�`
--•--- 16225
7_. . �95 211 \ - ' SR-104
Y I
0
7 780 _ _ 1010
20225
654--_ - -643 19
1
11 Y r
40_ , .-9
41
xxxx-average daily traffic
10
r roc -pm peak hour volume
2013 ESTIMATED DAILY & WEEKDAY PM PEAK HOUR VOLUMES
WITH PROJECT
Geralyn Reinart, P.E. FIGURE 6 TalaPoint Page
15Denny Way, Jefferson County,WA. F-6
Seattle,WA.A. 98109109
Z 'd ZB-v6- ILL-SZb IJaC d4,T : Tn nn c7 parr
71 22
11- ..%\---,-518 ESA -�4
$ a
55 86_ 1 ._90
12 46 _ >220 19
90 :.-52 'I' 127- 108
16
41
r
26 20--.. t.-`-178
4y
239
N.T.S.
12 i
I-
�2aJ, I i
/ / :
. t
d. �•.. " &pts
e p�
C ---_• $. ,_. --- Project site
1 § l
li
J
i
N
CLm •
11
i
> 1
N
: t
i
i
i
133 . - i
9_ f'-- --124 I \ ... -
135 • SR-104
t
0
6 874 - 1027
I
1210- _- 1202 18
j' p
2 1 -12
14 ,:-roc -peak hour volume
2013 ESTIMATED WEEKEND PEAK HOUR VOLUMES
WITH PROJECT
Geralyn Reinart, P.E. FIGURE 6A Tale Point Page
159 Denny Way,#111 Seattle,WA. 98109 Jefferson County,WA. F-6A
6T 'd ass- TLL-sat, t.aa9 d9S :2,i An P2 Darr
I