AMENDMENT FACE SHEET
Loan Number: PC12-951-052
Amendment Number: C
Washington State Department of Commerce
PUBLIC WORKS BOARD
Construction Loan Contract
1. Contractor 2. Contractor Doing Business As (optional)
Jefferson County N/A
623 Sheridan st
Port Townsend, WA 98368
3. Contractor Representative (only if updated) 14. Public Works Board Representative (only if updated)
N/A N/A
5. Original Contract Amount 6. Amendment 7. New Contract Amount
Amount
$10,000,000.00 N/A N/A
8. Amendment Funding Source 9. Amendment Start Date 10. Contract End Date
Federal: ❑ State: 0 Other: ❑ N/A: ❑ Amendment Execution Date June 1, 2046
11. Federal Funds (as applicable): Federal Agency: CFDA Number:
N/A N/A N/A
12. Amendment Purpose:
The purpose of this amendment is to correct a processing error that caused the contract completion dates to be
incorrectly displayed in the contract document.
The Board, defined as the Washington State Public Works Board, and Borrower/Contractor acknowledge and accept
the terms of this Agreement/Contract As Amended and attachments and have executed this Contract on the date below
to start as of this date of execution. The rights and obligations of both parties to this Agreement/Contract As Amended
are governed by this Agree me nt/Co ntract Amendment and the following other documents incorporated by reference:
Declarations Page, Amendment Terms and Conditions including all attachments. A copy of this Agreement/Contract
Amendment shall be attached to and made a part of the original Agreement/Contract between the Board and the
Borrower/Contractor. Any reference in the original Contract to "Agreement" or "Contract' shall mean the "Agreement As
AmPnrpri" nr'T nnfrarf Ac Amcnrinrl " rncnnMivoly
FOR THE BORROWER/CONTRACTOR
Signature '
d+l Feer Kiev -
Print Name
Title
Date
FOR &USLIC WORKS BOARD
Scott Hutsell, Public Works Board Chair
Date
APPROVED AS TO FORM ONLY
This 18th Day of December. 2008
Rob McKenna
Attorney General
Signature on File
Kathryn Wyatt
Assistant Attorney General
Jefferson County Page 1 Loan End Date Amendment
PC12-951-052 5/11/2017 All Programs
AMENDMENT TERMS AND CONDITIONS
Washington State Department of Commerce
PUBLIC WORKS BOARD
Construction Loan Contract
Contractor/Borrower: Jefferson County
Contract Number: PC 12-951-052
Amendment Number: C
The Public Works Board (or its successors), a department of the State of Washington, (hereafter referred to as
the 'Board") and the Contractor, listed on the Face Sheet, agree to amend the declared loan by modifying the
contract completion dates in the following sections to reflect the term and completion date as set for below.
Contract Face Sheet:
(Item 8: Contract End Date)
Contract End Date: June 1, 2046,
Part 1 Special Terms and Conditions:
1.14. Rate and Term of Loan
(2nd sentence modified to read as follows).-
The
ollows):The term of the loan shall not exceed 35 years, with the final payment due June 1, 2046.
1.17. Repayment
(2nd paragraph, 3rd sentence is modified to read as follows):
The final payment shall be on or before June 1, 2046, of an amount sufficient to bring the loan balance to
zero.
Jefferson County
PC 12-951-052
Page 2
5/11/2017
Loan End Date Amendment
All Programs
Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, Public Works Director/County Engineer,
Agenda Date: May 22, 2017
Subject: Public Works Board Loan Amendment - Port Hadlock Sewer
Statement of Issue: A loan Amendment with the Public Works Trust Fund Board (PWTFB) for
the Port Hadlock Wastewater System project.
Analysis/Strategic Goals/Pro's Ft Con's: Jefferson County was awarded a loan of $10,000,000
by the PWTFB in 2012 for development of the Port Hadlock Wastewater System, which has an
estimated startup cost of approximately $45,000,000 for the Core ft Rhody service areas. The
County has used approximately $1,676,155 of the loan combined with an EPA grant of
$970,000 to complete the plans and specifications for the wastewater treatment plant and
wastewater re -use facility and to complete permitting and land acquisition. A loan extension
for 18 months was approved in February 2017 to allow the County time to seek grants and
appropriations from State and Federal sources that would allow the project to advance. The
Public Works Board recently discovered an error in their document. The contract end date
should state June 1, 2046 instead of July 1, 2046. The PWTFB has requested that the County
sign the attached Amendment.
Fiscal Impact/Cost Benefit Analysis: This Amendment is for time only and so there is no new
fiscal impact.
Recommendation: Please sign all three (3) original documents where indicated and return to
Public Works for further processing.
Department Contact: Monte Reinders, Public Works Director (360) 385-9160
Reviewed By:
p Morley, u y Adm isVat Date
Leslie Locke
From: Tina Anderson
Sent: Thursday, May 18, 2017 10:21 AM
To: Leslie Locke
Subject: FW: PW Board Loan
Monte's response to the Amendment :
From: Monte Reinders
Sent: Thursday, May 18, 2017 9:47 AM
To: Tina Anderson <TAnderson@co.jefferson.wa.us>
Subject: RE: PW Board Loan
That's what the State sent me to correct their mistake. I would just go with it.
From: Tina Anderson
Sent: Wednesday, May 17, 2017 4:59 PM
To: Monte Reinders <MReinders@co.iefferson.wa.us>
Subject: PW Board Loan
Monte,
Leslie called from BOCC inquiring about the Amendment on the PW Board Loan agenda item.
It is Amendment C. She has record of Amendment A from February. Is there a B?
Tina Anderson, Administration 111
Jefferson County Public Works
623 Sheridan Street
Port Townsend, WA. 98368
360-385-9208
All e-mail sent to this address has been received by the Jefferson County e-mail system and is therefore subject to
the Public Records Act, a state law found at RCW 42.56. Under the Public Records law the County must release this
e-mail and its contents to any person who asks to obtain a copy (or for inspection) of this e-mail unless it is also
exempt from production to the requester according to state law, including RCW 42.56 and other state laws.
1