HomeMy WebLinkAbout080717_ca09Department of Public Works
Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, Public Works Director/County Engineer
Agenda Date: August 7, 2017
Subject: Authorization of Change Order #1 and #2 with Shold Excavating, Inc.
Rick Tollefson Memorial Trail, Phase I Project,
Co. Rd. No. 850100, CR1815
Statement of Issue:
Authorization of Change Order #1 and #2 for the Rick Tollefson Memorial Trail, Phase I
Project, CR1815 with Shold Excavating, Inc. in the amount of $26,450.80.
Analysis/Strategic Goals/Pros £t Cons:
These two change orders are necessary to pay for required changes for the farm road
relocation on the Bellow property, private utilities relocation on the Anderson property, a
pedestrian bridge deck construction method change, and increased landscaping quantities.
Fiscal Impact/Cost Benefit Analysis:
The cost of this change order is $26,450.80 and 7 working days.
Recommendation:
Public Works recommends that the Board authorize Change Order No. 1 and No. 2 and
return two signed originals of each to Public Works for further processing.
Department Contact: John Wayand, Project Manager, 385-9377
Y*'--< �>/,�7
p Morle unty Adminis ator
JEFFERSON COUNTY
Sheet 1 of 2
DEPARTMENT OF PUBLIC WORKS
Date: 7/20/2017
CHANGE ORDER NO. 1: PARTS 1,2, AND 3
Ordered by County Engineer under terms of
Section I - 04. 4 of the Standard Specifications
Changc proposed by Contractor
To: Shold Excavating, Inc.
P.O. Box 179
Endorsed by: Shold Excavating, Inc.
121 Pomwell Road
�,Fa/Am
Port Hadlock, WA. 98339
Signature
- /,cQ r�
Project Title:
title
Consent given by Surety: (when required)
Contract No. CR1815
By:
Rick Tollefson Memorial Trail, Phase I
Attorney-in-fact
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
This contract is revised as follows:
X Section l - 04. 4 of the Standard Specifications
PART 1 -
• Raise the Relocated Farm Road profile elevation by constructing additional quantities of the existing bid items at
unit bid prices as follows:
Item 5 Roadway Excavation incl. Haul, $6.00 CY
Item 8 CL IV Rein£ Conc. Cult'. Pipe 12 In. Diam., $44.00 LF
Item 13 Gravel Borrow incl. Haul, $15.00 TON
Item 15 Crushed Surfacing Base Course, $23.00 TON
-
Item 32 Construction Geotextile for Underground Drainage, $1.40 SY
• Estimated cost increase is $8,411.80.
• Change in Contract Time: 2 additional Working Days
X Section l - 04. 4 of the Standard Specifications
PART 2
• Relocate private waterline and septic drain line per the following new contract items as follows:
Item 48 Private Waterline Relocation, $2,500.00 L.S.
-
Item 49 Private Septic Drain Line Relocation, $600.00 L.S.
-
• Estimated cost increase is $3,100.00
• Change in Contract Time: 2 additional Working Days
X Change proposed by Contractor
PART 3
• Item 12 Prefabricated Pedestrian Bridge, 1 EA.
The construction method for the concrete decking for the Prefabricated Pedestrian Bridge is changed from precast concrete
deck to cast-in-place concrete deck.
The contract Special Provisions are changed as follows:
Special Provision 6-03.3 Construction Requirements
Prefabricated Pedestrian Bridge
Replace the first sentence with thefollowing:
The Contractor shall design, furnish, and erect, a fully engineered steel prefabricated pedestrian bridge with cast-in-place
concrete decking, including precast concrete abutments, subgrade preparation below the abutments and substructure, in
in accordance with this Special Provision and the details shown in the Plans.
Geometric and Design Requirements
Replace the first two sentences of item 3. with the following sentences:
3. The bridge shall be furnished with stay-in-place galvanized steel floor beams suitable for placement of cast-in-place
concrete decking. The floor beams shall be designed to carry the dead load of the cast-in-place concrete decking, plus a
construction load of 20 PSF uniform load or a 150 pound concentrated load on a F-0" wide section of deck.
Replace the first two sentences of item 7. with the following sentences:
7. Cast-in-place concrete deck design and construction shall be performed by the bridge manufacturer and shall meet the
requirements for Class 4000 concrete as defined in Standard Specification 6-02. The cast-in-place concrete deck shall have
a non-slip surface finish.
Submittals
Replace the last sentence under the Fabrication Submittals with the following sentence:
The prefabricated pedestrian bridge and precast concrete abutments will be inspected by the WSDOT State Materials
Laboratory, Fabrication Inspection Department.
Special Provision 6-03.5 Payment:
Replace the lasst paragraph with the following paragraph:
The unit contract price for "Prefabricated Pedestrian Bridge" shall include all associated costs for designing, manufacturing,
transportation and delivery, and installing the bridge, including but not limited to the prefabricated bridge, cast-in-place
concrete deck, precast concrete abutments, sand drainage blanket, labor, equipment, and traffic control.
Plans:
All references to "precast deck" are changed to "cast-in-place deck".
• Estimated cost decrease is $2,500.00
• Original Unit Contract Price $115,800.00, New Unit Contract Price $113,300.00
• Change in Contract Time: 0 additional Working Days
Proj. Manager
ORIGINAL
CURRENT
X Approval required
CONTRACT
CONTRACT
ESTIMATED NET
ESTIMATED CONTRACT
AMOUNT
AMOUNT
CHANGE THIS ORDER
TOTAL AFTER CHANGE
X County Engineer
$557,319.00
$557,319.00
$9,011.80
$566,330.80
Approval Required
ORIGINAL
CURRENT
Change in contract time
New Contract time
CONTRACT TIME
CONTRACT TIME
this Change Order
(Working days)
(Working Days)
(Working Days)
(Working Days)
67 days
67 days
4 days
71 days
APPROVAL RECOMMENDED
tAP
Projec Mana r Date
County ngineer ate
:4'APPF
OVAL, ECOMMENDED
t
APPROVED
Engine
'ng ices Manager Date
Chair, Jefferson County Commissioners Date
0
JEFFERSON COUNTY
Sheet 1 of 2
DEPARTMENT OF PUBLIC WORKS
Date: 7/20/2017
CHANGE ORDER NO.2
Ordered by County Engineer under terms of
X Section I - 04. 4 of the Standard Specifications
Change proposed by Contractor
To: Shold Excavatine. Inc.
P.O. Box 179
Endorsed by: Shold Excavating, Inc.
121 Pomwell Road
Cont actor arm
Port Hadlock, WA. 98339
Signature
P7
/ f L 7f
Project Title:
Title
Consent given by Surety: (when required)
Contract No. CR1815
By:
Rick Tollefson Memorial Trail, Phase I
Attorney-in-fact
Endorsed by: Yamamoto Landscaping, Inc..
-
Subcontractor Firm Name
Signature
P 112
Title
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
This contract is revised as follows:
• Increase the proposal quantities of two existing contract items as follows:
Item 23 PSIPE Evergreen Tree, from 10 EA. to 26 EA., $150.00 EA.
Item 24 PSIPE Plug Plant, from 379 EA. to 2050EA., $9.00 EA.
Estimated cost increase is $17.439.00
• Change in Contract Time: 3 additional Working Days
Prod. Manager
ORIGINAL
URRENT
X Approval required
CONTRACT
CONTRACT
ESTIMATED NET
ESTIMATED CONTRACT
AMOUNT
AMOUNT
CHANGE THIS ORDER
TOTAL AFTER CHANGE
X County Engineer
$557,319.00
$566,330.80
$17,439.00
$583,769.80
Approval Required
ORIGINAL
CURRENT
Change in contract time New Contract time
CONTRACT TIME
CONTRACT TIME
this Change Order
(Working days)
(Working Days)
(Working Days) (Working Days)
67 days
71 days
3 day 74 days
APPROVAL RECOMMENDED
'
7--)
APPROVED
—
Project A fanqger Date
County Engineer Date
�AP:A ECOMMENDED
APPROVED
Engineer ices Manager Date 1
Chair, Jefferson County Commissioners Date