HomeMy WebLinkAboutWashington State Recreation and Conservation Office (RCO), Amendment No. 1 - 022618WASHINGTON STATE „(
Recreation and �• �
Conservation Office--lmen►Y�p\`►edment to Project Agreement
Project Sponsor: Jefferson County Project Number: 15-1192R
Project Title: Salmon Creek Bridge Construction, West Uncas Amendment Number: 1
Amendment Type:
Cost Change
Amendment Description:
To add funds $145,472 salmon state funds.
Project Funding:
The total cost of the project for the purpose of this Agreement changes as follows:
RCO - PSAR
RCO - SALMON ST PROJ
Project Sponsor
Total Project Cost
Admin Limit
A&E Limit
Agreement Terms
Old Amount
Amount %
$788,800.00 85.00%
$0.00 0.00%
$139,200.00 15.00%
$928,000.00 100%
$0.00 0.00%
$118,986.00 14.71%
New Amount
Amount %
$788,800.00 73.48%
$145,472.00 13.55%
$139,200.00 12.97%
$1,073,472.00 100%
$0.00 0.00%
$137,638.08 14.71%
In all other respects the Agreement, to which this is an Amendment, and attachments thereto, shall
remain in full force and effect. In witness whereof the parties hereto have executed this Amendment.
State Of Washington
Recreation and Conservation Office
BY: r
Kaleen Cottingham
TITLE: Director
DATE: Z_ / /*
Pre -approved as to form:
BY: /S/
Assistant Attorney General
Jefferson County
DATE:
PSAR Project Cost Change Amendment
State Buildina Construction Account RCW 77.85. WAC 420
AMENAGR1.RPT
Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Philip Morley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineer
Agenda Date: February 26, 2018
Subject: PSAR Project Cost Change Amendment
Salmon Creek Bridge - West Uncas Road, Project No. 18019341,
County Road No. 500209, RCO Project No. 15-1192
Statement of Issue: Execution of PSAR (Puget Sound Acquisition and Restoration
fund) Project Cost Change Amendment for the Salmon Creek Bridge - West Uncas Road
project, County Project No. 18019341.
Analysis/Strategic Goals/Pro's Et Con's: In 2017 Jefferson County applied for
additional funding under RCO grant #15-1192R. RCO grant #15-1192R provides funding
for design and construction of the proposed Salmon Creek Bridge. The additional
funding was needed in order to address required design changes and an associated
increase in the estimated construction cost.
Fiscal Impact/Cost Benefit Analysis: The amendment will add $145,472 in RCO
funds. The project is funded at 85% by the RCO, with the remaining 15% funded by a
combination of a $100,000 NFPP (National Fish Passage Program) grant and the County
Road Fund.
Recommendation: Public Works recommends that the Board execute the three (3)
originals of the Amendment and return two (2) originals to Public Works for further
processing.
Department Contact: Mark Thurston, P.E., Project Manager, 385-9160.
Reviewed By:
Hip More ounty Adminis ator Date