HomeMy WebLinkAbout821093003 Stormwater Mgmt EXHIBIT 6
Draft Environmental Impact Statement
PORT LUDLOW WASTEWATER
TREATMENT SYSTEM EXPANSION
~'.
Co-lead Agencies:
Washington Department of Ecology
and
Jefferson County
July 16-, 1986
Booth Gardner Andrea Beatty Riniker
Governor
Director
SUMMARY
Objective~ Purpose~ and Need
Objective
Ludlow Utilities Company, a subsidiary of Pope Resources is the
project proponent.. The objective of the project is to adequately deal
with the need for wastewater collection and treatment for the Port Ludlow
area (see Figure 1) in the manner meeting the highest reasonable stan-
dards of environmental protection, long-range planning, engineering
excellence, social acceptability, and cost-effectiveness.
Purpose
The existing wastewater collection and treatment system at Port
Ludlow serves a total of 422 residential and commercial units. The plant
provides secondary treatment, disinfection using a chlorination process,
and discharges treated effluent through an outfall into Port Ludlow Bay,
adjacent to the site. The plant had been violating effluent limitations
established in the National Pollutant Discharge Elimination System (NPDES)
permit until improvements were made in 1984. The improvements have
enabled the plant to consistently meet effluent limits for BOD (organic
matter), TSS (solids) and fecal coliform (bacteria). There also appears
to be capacity in the improved plant for up to 70 additional units,
making the total projected capacity of the plant 492 units.
Need
Based on existing commitments, Ludlow Utilities Company is obligated
to provide treatment for a total of 1,206 connections. In addition,
completion of a new development in the South Bay area would result in a
total of 1,868 connections that would require service by the Port Ludlow
Wastewater Treatment Plant (WWTP). Based on existing commitments and the
future development for the Port Ludlow area, it is necessary to increase
the capacity of, or to develop an alternative to, the wastewater treat-
ment facility to continue meeting secondary treatment standards. This
project is needed to allow for planned development while protecting the
water quality of Ludlow Bay.
Proposed Action
The proposed action is for an expansion of the existing wastewater
collection and treatment facility and extension of the plant outfall.
The proposed action is divided into two phases involving both treatment
plant expansion and improvements to the conveyance system. If
disinfection were inadequate, colifo'rm levels could exceed Class AA
criteria within portions of the bay. Adequate disinfection by increased
chlorination could cause recommended chlorine residual levels in the
vicinity of the outfall to be exceeded. No substantial decreases in
dissolved oxygen, or increases in turbidity, would be expected within
the bay.
-1
The proposed treatment method is contact stabilization. This method
of secondary treatment can be constructed on the existing treatment
plant site; it is in widespread use and would provide the flexibility
needed to handle the seasonally fluctuating wastewat~r flows. The lift
stations connecting the South Bay community with the treatment plant
would be upgraded to handle increased flows. Lift stations #3 and #4
would be rebuilt at their existing locations. A new lift station #1
would be located north of the marina and would pump wastewater through a
force main that parallels Port Ludlow Road to the treatment plant. The
plant and all lift stations would meet the Department's criteria for
reliability. The plant outfall would also be extended 3000 feet to the
north as a part of the proposed action.
Alternatives
A variety of possible solutions to fulfill the need for additional
wastewater treatment capability in Port Ludlow Bay were examined. Four
different types of alternatives were considered: 1) facility size,
2) location, 3) treatment process, and 4) outfall location. Based on
available information and the proponent's objectives, the possible alter-
natives were evaluated using engineering, economic and environmental
considerations.
Facility Size
Evaluation of alternative facility sizes to meet the demand for
wastewater treatment in the Port Ludlow area indicates that both the no
action alternative and a smaller facility would not provide sufficient
secondary treatment for the planned development. Both the regional
facility and the smaller facility would not provide a significant reduc-
tion in water quality impacts, but would result in a greater user cost.
The increased costs would either be borne by residential property owners
along Ludlow Bay Road and/or in the Swansonville/Mats Mats area, or it
would be borne by state and federal taxpayers. The no action and the
smaller facility also would not fulfill the proponent's objective.
Location
Evaluation of alternative facility location involved a comparison of
a single facility at the existing site, a single facility at a new site
and a split facility. Construction of a new facility at a new location
would result in greater environmental impacts due to upland construction
but would not result in any reduction of water quality impacts. Construc-
tion and land acquisition costs would be substantially greater.
A split facility using the existing WWTP would involve both
upgrading the existing facility and constructing a 'new facility. Similar
to only constructing an all new facility, this alternative would have
greater construction impacts in upland areas not now developed and
greater construction costs.
A split facility at two new sites would involve the construction of two
entirely new wastewater treatment facilities and reconstruction of the
'..~' -~ .... ; ~:.,.co~leGtion~,and.~ conveyance facilities,~-. The,~ construction~.and..,land~. ...... ~
acq~isition'~osts associated with this alternative would be 'exCeSsive.
-4-
Treatment Processes
Several different secondary treatment options have been evaluated,
including: complete mix activated sludge treatment, contact stabiliza-
tion treatment, oxidation ditch treatment, and land treatment. Opera-
tional options considered include;timing effluent discharges with
favorable tides, ultraviolet disinfection in lieu of chlorination and
anaerobic sludge digestion in lieu of aerobic digestion.
· The complete mix activated sludge treatment is the most versatile
and widely used biological process in wastewater treatment, and typically
removes 85-95% of organics (Biological Oxygen Demand or BOD) and sus-
pended solids. New construction would be required for all unit processes
except sludge digestion and thickening.
· The contact stabilization treatment method (proposed action) is a
modification of the complete mix activated sludge treatment method. This
method would reduce organics (BOD) and suspended solids by as much as 90%
to 95%. The contact stabilization method also requires new construction
for all unit processes except sludge digestion and thickening. The
treatment process can handle widely fluctuating loading better than a
complete mix activated sludge system but requires additional operator
attention.
· The oxidation ditch treatment operates in an extended aeration
mode and does not require primary treatment. New construction would be
required for all unit processes except the primary clarifier, sludge
digestion and thickening. The facility is larger than the previous two
discussed and would require the acquisition of adjacent lands. One of
the advantages of the oxidation ditch treatment method is the ease of
operation relative to the complete mix and contact stabilization treat-
ment methods.
· Land treatment of wastewater involves the use of plants, the soil
.
surface, and the soil matrix for wastewater treatment After a number
of candidate sites were assessed, the Hood Canal tree farm was selected
for detailed evaluation. Wastewater would be collected in the existing
system and conveyed southwest along existing roads to the tree farm site.
A large storage lagoon would be used for storage of wastewater during
periods when wastewater flows exceed the hydraulic loading rate of the
soils. Although land treatment would have greater terrestrial impacts,
it would reduce the water quality impacts to the bay.
· Anaerobic digestion is one of several methods available for
stabilization (decomposition of organic matter and solids reduction) of
solids removed in the wastewater treatment process. Anaerobic digestion
was eliminated from consideration at Port Ludlow due to the high cost
and site constraints.
· Rather than continuously discharging into Port Ludlow Bay,
effluent could be stored during slack water and flood tidal conditions.
This alternative would require construction of a 200,000 to 300,000
gallon reservoir offsite and associated pump and pipeline facilities.
~...~t~ ~Wh~thia~i% ~rojected %o~ result, in a five-fold increase in dilution,
increasing dilution is to modify the outfall.
-5--
· Ultraviolet (lA?) light disinfection has been reported to be an
effective method of disinfection having no apparent toxicity to aquatic
animals· The reliability of this process is questionable, however,
especiallv at a small facility. Given the need to provide very reliable
disinfection, chlorination was selected over UV disinfection. The chlor-
ination system and outfall will be designed to mitigate potential adverse
environmental impacts to sensitive aquatic species from chlorination.
· Tertiary treatment of wastewater involves treatment beyond secon-
dary levels aimed at removal of nitrogen, phosphorus, or suspended
solids. Based on the results of the water quality investigation of Port
Ludlow Bay~ the need for tertiary treatment could not be demonstrated.
Receiving water quality benefits of tertiary treatment were considered
minimal compared to the high cost and tertiary treatment of wastewater
was eliminated from further consideration.
Outfall Location
Three outfall options were considered' extending the existing
outfall 400 feet east further into Port Ludlow Bay, extending the
existing outfall 3,000 feet north to the edge of Port Ludlow Bay, and
extending the outfall beyond Tala Point into Admiralty Inlet.
Impacts associated with the outfall options are primarily related to
water quality in Admiralty Inlet and Port Ludlow Bay. Careful evaluation
of the discharge sites was required to determine any effects of the dis-
charge on clam beds at ColVos Rock and the general water quality in
Ludlow Bay, Admiralty Inlet and Hood Canal. An analysis of currents and
circulation in Port Ludlow Bay indicates that flushing at a site 400 feet
east of the existing outfall would provide suitable dilution for effluent
from an expanded treatment plant. Extending the outfalt 3,000 feet to
the north would not provide a major improvement in water quality within
the bay However, several minor water quality improvements are asso-
ciated with this northern outfall and it has been identified as the
proposed action. A preliminary assessment suggests that a portion of the
effluent from any discharge in the vicinity of Tala Point would tend to
be carried into Port Ludlow Bay; the remainder would be dispersed direct-
ly into Admiralty Inlet or Hood Canal. Placement of the outfall at Tala
Point would be expected to result in a reduction in effluent concentra-
tion within Port Ludlow Bay compared with the existing outfa]l site. In
all alternatives, however, the predicted effluent concentrations ~'~thin
Port Ludlow Bay are very
±O~ .
Impacts
Both construction (short-term) and operation (long-term) impacts
associated with the proposed action are summarized ,below. Impacts are
presented by elements of the natural and built environments.
Natural Environment
Earth. Short-term: The proposed action calls for site expansion
and-.~~ve~ents"to .%he exi'stin~dTP"tha~woutd+~eq~ire excavation-for~i,-
~ .
-6-
new treatment components and trenching for new sewer lines. Construction
activities would result in an increased potential for erosion and
sedimentation from storm runoff. The outfall would also involve some
nearshore, intertidal, and subtidal sediment disturbance.
Long-term: Allow for this area to continue to be developed in
accordance with the Comprehensive Plan
Air. Short-term: While under construction, the WWTP improvements
would r--~sult in a temporary deterioration of the ambient air quality.
Vehicular traffic resulting from ingress and egress of construction
vehicles would increase ambient levels of carbon monoxide, hydrocarbons,
and photochemical oxidants (sulphur and nitrogen oxides).
Long-term: Sludge hauling would increase from an average of
one trip per week to five trips per week at full usage of the plant
(about 2030). There would be a corresponding increase in vehicle
emissions. Increased operational capacity may increase obtrusive odors
emanating frOm the plant.
Water. Short-term: Construction of the outfall pipe would
increase turbidity in the immediate area.
Long-term: The allowable discharge of pollutants would
increase as follows'
Discharge at
Present Capacity (Estimate)
Flow 100,000 gallons/day 380,000 gallons/day
BOD 19 lbs/day 95 lbs/day
SS 15 lbs/day 95 lbs/day
Fecal Coliform 50 per 100 ml <200 per 100 ml
Chlorine 1.5 lbs/day 3.2 lbs/day
Nitrogen 21 lbs/day 79 lbs/day
Total daily loads of individual effluent constituents and effluent
volumes as a whole would increase over current plant loads. However,
more reliable treatment and better initial dilution are expected to
improve water quality conditions in the vicinity of the outfall compared
to 1984 conditions. Better mixing with larger bay volumes and less
likelihood of inner bay transport of diluted effluent by north wind
episodes are also expected. Effluent is not expected to cause any Class
AA violations within the bay. Projected increases in BODs and ammonia
would not significantly affect DO levels within the bay. Fecal coliform
levels are expected to be more consistently at a level having no
significant impact on water column and shellfish concentrations.
Nitrogen load contributions of the treatment plant into the inner bay
during the summer could be increased from 0.3% to 1.6% on average, and
from 3.0% to 13.5% during an extreme condition. A proportional increase
in algae productivity could be stimulated by this increase in nitrogen.
..... However, 1984 field study data suggest that algae densities are low in
--7--
the inner bay because of short residence times. No noticeable decreases
in water column transparency are expected from the estimated increases
in algae productivity. Typical and worst-case turbidity conditions in
the dilution zone of-the outfall would improve by being consistently
low. Chlorine residuals would be decreased in the effluent and reduce
the chance of toxic conditions for aquatic life in the vicinity of the
outfall. Ammonia levels would slightly increase in the mixing zone, but
are expected to be below levels considered toxic to aquatic life.
Construction activities would temporarily cause Class AA turbidity
violations.
Plants and Animals. Short-term: During construction the presence
of equipment, human activity, and noise could cause birds and mammals to
avoid the area. Since the existing treatment plant is within an already
disturbed site, its expansion would not result in the direct loss of
additional habitat.
Extension of the new outfall pipeline to the north discharge point
would disrupt the subtidal soft-bottom habitat over an area 15 feet wide
and 3,000 feet long. The biological community in the immediate area of
the construction would be eliminated, including some geoducks. Minor
impacts to marine birds and mammals could occur from habitat loss due to
elimination or disturbance of subtidal areas during outfall construction;
these habitat losses should be offset by recolonization along the outfall
pipeline.
Long-term- The expanded wastewater treatment capacity would
allow for maximum residential buildout as presently planned for the Port
Ludlow area. Such a buildout is likely to result in loss of habitat and
increased recreational boating. If boating wastewater is not properly
disposed of it could increase fecal coliform bacteria levels in Port
Ludlow Bay shellfish.
Treatment process upsets could result in potential impacts to marine
organisms.
Built Environment
~oise. Short-term- Construction noise generated from backhoes,
graders, air compressors, and trucks would occur over the 12-month
construction period. '
Long-term: Operational activities of the WYTP and lift
stations would increase noise levels slightly in their immediate areas.
Operational noise sources include blowers, pumps, mechanical operatiOns
and service trucks. ,
Risk of Upset. Power failure, equipment failure, or flooding events
could result in e~cessive water volumes in the WWTP and piping system.
Under such events, wastewater would be given primary treatment and
disinfected before being discharged into the bay.
.
-8-
Water. Short-term: Short-term water quality impacts'may be caL~sed
by treatment plant, outfall, and conveyance facilities construction, and
impacts would be limited to turbidity caused by soil erosion and sedimen-
tation in the immediate vicinity of construction activities. Mitigating
measures to reduce these construction impacts are present under the earth
element. Impacts related to outfall construction would be short-term
increases in turbidity. Timely and efficient in-water construction, as
well as use of construction techniques that minimize disturbance of the
substrate, would reduce impacts.
Plants and Animals. Short-term: None.
Long-term: Disturbance around the existing treatment plant
would be landscaped and hydroseeded. Subtidal soft-bottom habitats would
be replaced with a hard surface pipeline and ballast. These hard
surfaces would allow marine organisms to become established. Minimal
hard surface habitat is presently available in the bay; therefore, the
proposed outfall expansion could result in a net increase of organisms
available for marine birds and mammals. Other mitigating measures for
the outfall include limiting construction to May and June to avoid
out-migrant juvenile salmonids.
Built Environment
Noise. Short-term: None.
Long-term: Noise levels would be reduced and would not exceed
50 dBA at the property line of the facilities by using quiet electric
motor pumps and designing equipment housing structures to muffle and
reduce noise levels. Pumps would be housed underground.
Risk of Upset. Short-term' Wastewater will continue to be treated
to secondary levels during construction. No plant bypassing or
reduction in treatment will occur while the new plant is being built.
Long-term: Emergency power generation, with automatic
switchover equipment, would be installed. In accordance with Ecology's
reliability standards, multiple treatment units would be provided to
minimize the loss of treatment efficiency should one of the process
components f~il. Backup pumps would be installed and available for
immediate use should primary pumps fail. Handling, storage, and use of
chlorine gas would be in accordance with state and federal requirements;
alarms, sensors, and emergency equipment would be provided. Electronic
telemetry is provided for all lift stations.
Land Use. Short-term: Should construction of the treatment plant
require removal of existing screening vegetation, a vegetative buffer
would be replanted.
Long-term: Perimeter landscaping and plantings would visually
screen the W~P from adjacent residences.
Recreation. Short-term' None.
Long-term' Efforts to continue to encourage boaters to use the
wastewater pump-out facilities provided by the marina will be made in
order to minimize flushing of tanks directly into the bay. .
Public Services and Utilities. Short-term: None.
·
Long-term: The water service for the community is supplied by
an existing, privately-owned facility and is designed to serve the
expanding needs of the Port Ludlow community. The Port Ludlow community
is a recreational/residential development with a lower-than-usual number
of full-time occupants. Therefore, the service requirements are less than
for a conventional residential development. The needs for additional
public services and utilities also are substantially reduced for this
reason.
Unavoidable Adverse Impacts
Short-term: Site expansion would require excavation, trenching,
and backfill. Construction activities would result in temporary erosion,
sedimentation, and increased water turbidity. During construction,
temporary increases of suspended particulate levels would also occur.
Increased vehicular traffic under operational conditions would increase
ambient levels of carbon monoxide, hydrocarbons, and photochemical
oxidants. A small amount of terrestrial wildlife would be affected.
Construction of the outfall pipeline could have a short-term effect on
marine bird and mammal use in the area.
Long-term~ The increased discharge of pollutants will have an
adverse impact though it will not be measurable. The mitigating
measures of increased treatment plant reliability and relocation of the
outfall should more than offset the increase in pollutant loading. A
long term receiving water monitoring program will be incorporated into
Port Ludlow's NPDES permit to provide assurance the plant is not
impacting water quality.
Section IV
AFFECTED ENVIRONMENT, SIGNIFICANT IMPACTS, MITIGATING ~fEASURES
Section IV of this EIS presents the scoping, affected environment,
significant impacts, mitigating measures, and unavoidable adverse impacts
for each element of the environment identified during the scoping
process. The elements of the environment are divided into two groups:
the natural environment and built environment. The affected environment
is described as existing conditions of the project site and vicinity.
Significant impacts that would or could occur are described with
sufficient detail to allow assessment of their severity. Mitigating
measures are described that would reduce or eliminate environmental
impacts; all unavoidable adverse impacts, those without mitigation, are
identified.
SCOPING
"Scoping" is the term used to determine the appropriate topics to be
addressed in an Environmental Impact Statement.
Washington administrative laws require lead agencies (in this case,
Jefferson County and the Department. of Ecology) to narrow the focus of
every EIS to the "probable significant adverse impacts and reasonable
alternatives, including mitigation measures" (WAC 197-11-408).
To ensure that every EIS is concise, yet addresses the significant
environmental issues, the lead agencies must execute a scoping process
with the following objectives in mind:
The promotion of interagency cooperation and public participation by
inviting various governmental agencies, affected tribes, and the
general citizenry to suggest appropriate contents of the EIS;
· Identification of reasonable alternatives to the proposed project
and probable significant adverse environmental impacts;
·
· Elimination from detailed study those impacts that are not
significant; and
· Coordination with other agencies to identify and integrate, where
feasible, environmental studies required for other governmental
approvals.
With those objectives in mind, on January 23, 1985, the Department
of Ecology issued a formal "Determination of Significance and Request for
Comments on Scope of the EIS." The Scoping Notice described the main
features of the proposed project; the cooperative environmental review
arrangement between the State, County and applicant; the apparent
governmental permits and licenses required; and that the lead agencies
had identified water quality as the main issue of concern. The notice
-39-
also invited agencies, affected tribes, and members of the public to
comment on the scope of the EIS, alternatives, mitigation measures,
probable significant adverse impacts, and licenses or approvals that may
be required. The deadline for comments was set for February 15, ]985.
As announced in the Scoping Notice, as well as in local newspapers,
a Public Scoping Meeting was held at 7:30 p.m., February 7, 1985, in the
Conference Center at Port Ludlow. The meeting was conducted by the
Department of Ecology. Oral testimony was recorded and additional
written remarks were invited prior to the February 15th deadline. Some
fifteen letters were received subsequent to the Public Scoping Meeting.
On February 27, 1985, the Department of Ecology, Jefferson County,
the applicant, and the applicant's consultant met to determine in what
manner each of the elements of the EIS would be addressed. On February
28, 1985, Department of ECology distributed a memorandum identifying the
range of ElS topics as a result of the Public Scoping Meeting, written
comments, and additions from Department of Ecology and Jefferson County
staffs. Elements of the environment and the associated issues are
summarized as follows.
Element of the Environment Associated Issues
I. NATURAL ENVIRONMENT
A. Earth ·'physical land disturbance
· cut and fill requirements
· erosion and sedimentation during
construction
B. Air · construction dust
· increased traffic
· obtrusive odors
C. Water · physical oceanographic (currents and
circulation) conditions of bay
· biological conditions (nutrients,
algal blooms, chlorine, turbidity)
· normal and worst-case scenario
· effects of construction
· effects on shellfish
D. Plants and Animals · effects to marine birds and mammals
· effects to marine invertebrates and
fisheries
E. Energy and Natural · not applicable
Resources
II. BUILT ENVIRON~IENT
A. Environmental Health · increased noise levels
._ · risk of upset
· public health effects
-40-
~Elevations range from about 360 to 480 feet above sea level located on a
broad north/south ridge separating the lowland on the east from Thorndyke
Creek Canyon on the west. Access is limited to Highway 104 that runs
east/west through the north half of the area and a logging road near the
center of the area.
Geology/Soils
__
The geology of the. Port Ludlow area includes basaltic bedrock of the
Crescent Formation and surface deposits of glacial and alluvial
sediments. The soils that have formed on these deposits include the
Alderwood-Sinclair association and the Olete-Hoodsport association
(McCreary, 1975). The Alderwood-Sinclair associations are moderately
well drained, strongly sloping to steep, gravelly soils underlain by
compact glacial till. The Olete-Hoodsport associations consist of well
drained and moderately well drained, strongly sloping to steep, very
gravelly soils underlain by basalt or compact glacial till.
The North Bay service area consists primarily of Alderwood soils.
These soils have an impermeable substratum (glacial till) at a depth of
20 to 40 inches that restricts groundwater movement. A perched
groundwater condition typically occurs in these soils during the winter
months. The South Bay service area includes moderately well drained
soils of the Olete series. These soils are underlain by basalt bedrock
at a depth of 20 to 30 inches.
At the treatment facility, dense to very dense glacial till was
observed in the cut slopes made to construct the existing upper and lower
benches at the treatment facility (Converse Consultants, Inc., 1985).
Till is a homogeneous mixture of clay, silt, sand and gravel with
occasional boulders. The till was consolidated by the weight of glacial
ice and is commonly referred to as "hardpan." Occasional lenses of fine
to medium grained sand occur within the till.
The soils occurring in the area considered for the land treatment
alternative have formed in glacial till and glacial outwash material (see
Figure 10). The upland area (Site 2) consists of Dabob and Sinclair
soils that formed in glacial till. These are moderately well drained
soils with a very slowly permeable cemented horizon within 20 to 40
inches of the surface. Runoff is slow to medium on moderate slopes (less
than 15%) and medium to rapid on steep slopes (15-30%), and the hazard of
erosion is slight to moderate. A perched water table is often found on
top of the cemented till layer during the rainy season.
Soils of the lowland area (Site 1) have formed in the coarse grained
glacial outwash material and have been identified as Everett, Carlsborg,
and Indianola soils. These are somewhat excessively drained soils with
rapid permeability. Runoff is slow and the hazard of erosion is slight
to moderate. Based on this evaluation, these lowland soils have a
greater capacity for hydraulic assimilation, due to their more rapid
drainage capabilities.
-45-
IMPACTS
Proposed Action
Site expansion and improvements for the existing WWTP would require
excavation for the aeration basins, cl. arifiers, and outfall and diffuser
pipe. Estimates for the treatment plant excavations are 12,000 cubic
yards. Most of the excavated material would require off-site disposal.
New material for backfill and drainage control, and concrete aggregate
would need to be obtained from a quarry. Site construction activities
would result in an increased potential for erosion and sedimentation from
storm runoff. Control measures could reduce the impact of off-site~
erosion and sedimentation.
If earthwork construction is not conducted 'during the dryer summer
months, the glacial till soil on the site would be easily disturbed and
impossible to properly compact. When wet, disturbed soils are highly
susceptible to erosion.
Conveyance facility improvements would involve new force main
pipelines. This would require trenching and backfilling and would result
in some sedimentation to off-site areas. Off-site hauling and disposal
of some excavated material could be required. Treated sludge would be
applied to a remote Pope Resources tree farm site approximately five miles
south of the WWTP. The stabilized sludge will be used to enhance tree
growth and will be applied at rates consistent with specific soil types,
vegetation cover and ground slope. A similar site nearby has recently
been approved by the Jefferson County Health Department for the City of
Winslow. Its soil characteristics and suitability for sludge application
have been evaluated by Brown and Caldwell (1985).
Under the proposed action, installation of 3,000 feet of outfall
discharge pipe would require excavation of about 1,500 cubic yards of
nearshore and intertidal beach sediment. Short-term turbidity increases
would occur during excavation and backfill for the outfall pipe. No
long-term impacts would be expected to occur.
Al'ternatives
Treatment Facility 'Size: Retain Existin$ Facility (No Action)
The "no action" alternative would not result in clearing and grading
activities associated with treatment plant improvements. New sewer
service area expansion may not occur and new sewer lines would not be
installed. New developments, however, may be served by individual
on-site or community systems, provided that the site conditions are
suitable. In this case, construction impacts associated with clearing
and grading activities would occur on an individual and isolated basis.
Due to steep slopes, slow permeability and shallow perched'water table,
most soils in the Port Ludlow area have severe limitations for septic
drainfields and would likely not meet health department requirements.
-47-
Treatment Facility Location' Split Facilitv~ Existing and New Site
Construction of a new wastewater treatment facility would have
impacts from site grading and clearing activities, and soil erosion
potential similar to construction of the proposed action. The actual
impacts could be greater or less, depending on the characteristics of the
site selected on the south shore and the overall area affected. Often
construction on an undeveloped site results in more extensive clearing
and grading activities. In the south shore area, the potential to affect
the beach and nearshore area exists. A new site also would require a
greater overall extent of new force mains and conveyance lines from the
service areas to the new facility. Construction of a second outfall
pipeline would likely result in more extensive impacts to the aquatic
environment as an estimated 9,000 feet of pipe would be required to reach
an acceptable outfall location.
Treatment Process: Land Treatment
The land treatment alternative would require trenching for
approximately 3.5 miles of pipeline, excavation for several lift
stations, and extensive site clearing, grading, and excavation for the
primary treatment lagoon systems. In addition, shallow excavations would
be required for the effluent application pipelines. The influent
transmission pipeline would require some ripping or blasting of basalt
bedrock for trench excavations.
The total area required for a land application site is based on the
nitrogen uptake of native vegetation. Nitrogen uptake was calculated
using the known uptake of Douglas fir (refer to the Engineering Report,
Appendix A, Seton, Johnson &Odell, 1986) and the percolation rate
through the root zone, assuming a reduction of nitrogen concentration
from 60 mg/1 to 5 mg/1.
The upland area (Site 2) soils appear to have greater limitations
related to lower hydraulic assimilative capacity than the lowland (Site
I) soils. Because of soil characteristics and requirements for large
land areas, effluent irrigation may not be practical on these upland
soils. The lowland area soils appear to have the most favorable
characteristics for year-round effluent irrigation; however, their
rapidly drained nature could result in inefficient effluent purificatien
resulting in groundwater contamination.
Conservative assumptions have been used in estimating land area re-
quirements for effluent irrigation on these soils. The general
conclusion is that the gravelly outwash soils of the lowland site are
limited by nitrogen loading rates; approximately 200 acres of land would
be needed in these soils to fulfill treatment requirements. In the
upland glacial till soils, hydraulic limitations dictate a need for
600-700 acres for treatment.
Due to its potential health hazard, nitrogen contribution to the
groundwater is of concern. The nitrate concentration in treated effluent
averages 60 mg/1 (14 mg/1 as nitrogen). State standards for nitrates in
w -- water sources is 10 mg/1. The nitrates fro~ wastewater are very
-48-
soluble and are readily leached through the soil, thereby potentially
contaminating groundwater sources.
Phosphorus is considered the major nutrient and the limiting factor
in contributing to the eutrophication of surface water bodies (Welch,
1978). Phosphorus absorption onto the soil particles is the major
mechanism for phosphorus removal. Variations in phosphorus retention are
dependent on loading rates, permeability, depth to water table, and
groundwater movement characteristics. The lowland §ravelly outwash soils
would have low phosphorus absorption capacity.
Nitro§eh and phosphorus present in septic tank drainfields are con-
verted by microbial activity in the presence of oxy§eh from anaerobic to
aerobic conditions. Nitro§eh in the form of nitrates is soluble and
readily carried into the groundwater, where dilution is the only
effective means of reducing its concentration. Phosphorus, on the other
hand, is absorbed onto the soil particles and is precipitated with soil
sediments such as iron, aluminum and calcium. With extended use
phosphorus absorption capacity in soils can be reduced and it may
subsequently enter the groundwater. The nutrient characteristics of land
irrigated with wastewater would be similar to nutrient characteristics
from drainfields. Due to the estimated lower land area requirement,
preliminary calculations support the conclusion that the lowland outwash
soils are suitable for effluent land application.
For design purposes, a more detailed field investigation of actual
soil characteristics would be needed to verify U.S. Soil Conservaticun
SerVice mapping and to develop a detailed delineation of individual soil
series. Refinement of land area requirements could then be made along
with recommendations and specifications for wastewater irrigation system
siting.
In order to assure that the soils remain suitable to receive appli-
cation and meet requirements of the disposal permit, a monitoring program
would be established. Monitoring information would be provided to the
Washington State Department of Ecology and Jefferson County Health
Department. It is also important to note that use of the land treatment
alternative would eliminate the need for an effluent outfall and those
aquatic environmental impacts associated with the proposed action would
not occur.
Treatment Process' U!travioie% (UV) Disinfection
Disinfection through use of b~ light would have no impact on earth
or soils.
Outfall Location: Expand Existins to South Discharge Point
The effluent outfall pipe would require excavation of about 150
cubic yards of nearshore and intertidal beach sediment to bury the
pipeline. Short-term turbidity increases would occur during excavation
and backfilling for the outfall pipe. No long-term impacts would occur.
MITIGATING MEASURES
Proposed Action
Site development for expansion of the existing WWTP would include
interim drainage measures to control erosion and sedimentation during
construction. Measures could consist of vegetative controls, structural
controls, and best management practices.
Vegetative controls could consist of preservation of existing vege-
tation, temporary seeding, and planting of permanent landscape vegetation
strips in graded and cleared areas. Vegetative controls are the first
line of defense in preventing erosion by protecting the soil surface from
raindrop impact and overland flow of storm runoff. Vegetative buffers
reduce runoff velocities and act as a filter in trapping sediment.
Structural controls could consist of sedimentation ponds and
sediment barriers. These controls are not as effective as vegetative
controls, but provide an additional measure to capture sediment before it
leaves the construction site.
Good construction management and planning are key elements in
controlling erosion from the construction site. Management decisions
that could be employed during site development include the following:
Immediately upon completion of the grading operation in an area,
seed it with an appropriate vegetative mix to limit erosion.
· Avoid exposing soils during periods when the highest potential for
erosive rainfall could occur.
· Develop and carry out a regular maintenance schedule for structural
controls.
Appropriate engineering design and safeguards for foundation excava-
tions, and sewer line placement should be conducted with the supervision
of a soils engineer. Subsurface explorations and recommendations for
shoring, drainage, water control, and clearing and grading design
measures should be provided by a qualified soils engineer prior to
issuance of construction permits. Building siting should be in uniform
sei!s.
Retaining walls and shorings should be used for cuts exceeding four
feet to prevent sloughing or sliding. Adequate subdrains should be
provided. To further protect against shoreline erosion, approximately
500 cubic yards of riprap would be placed along the high-tide line in
front of the WWTP.
Secondary treatment and discharge would result in an estimated
sludge production of 1,000 gpd at 4% solids. Sludge would be used as a
fertilizer for the commercial tree farm operated by Pope Resources.
-50-
Alternatives
Treatment Facility Size: Retain Existing Facility (No Action) and
Treatment Facilitv Location: Split Facility~ Existing and New Site
Mitigating measures similar to those for the proposed action are
proposed for these two alternatives. It is important to note that any
individual drainfields constructed under the no action alternative would
not require a grading permit. Thus, any mitigating measures to reduce
erosion due to construction would only occur under an individual and
voluntary effort.
Outfall Location: Expand Existing to South Discharge Point
No mitigating measures are proposed.
Treatment Process: Land Treatment
Along with operational experience and an accurate determination of
effluent constituent concentrations, a detailed site monitoring program
would serve as an important mitigating measure for the land treatment
alternative. It would provide a basis for evaluating the need for
corrective measures (e.g., increased land area or adjustments in
irrigation scheduling) prior to creating potentially adverse impacts on
groundwater. Emphasis of this program would be on the unsaturated soil
zone and nitrite-nitrogen leaching losses.
With its internal drainage and absence of groundwater development,
the lowland area appears well suited for land application of treated
effluent. The lowland area, however, is possibly a recharge area for a
more regional groundwater system (Seton, Johnson & Odell, 1986). There-
fore, delineation of groundwater flow conditions and careful monitoring
would be necessary.
Drainage and runoff conditions in the upland area (Site 2) may
constitute a potential threat to surface water, e.g., Thorndyke Creek.
Application area setbacks to minimize potential surface water impacts
would substantially reduce the available application area by as much as
70%. ~ile application rates and techniques can be used to mitigate
impacts, the sensitivity of receiving waters (Port Ludlow Bay and
Thorndvke ~av) relegates the u~!and are~ to least favorable status.
UNAVOIDABLE AD\~RSE iMPACTS
Proposed Action
Site expansion would require excavation for the new facility and
trenching of new sewer lines; excavation estimates are 12,000 cubic
yards. Excavated materials would be disposed off-site. New backfill,
drainage control, and concrete aggregate would be obtained from a quarry.
During the construction period, temporary erosion and sedimentation would
occur.
The outfal] discharge pipe would require excavation of about 300
cubic yards of nearshore and intertidal beach sediment. Short-term,
temporary turbidity increases would result from this activity.
Alternatives
Treatment Facility Size: Retain Existing Facility (No Action)
Excavation for individual septic systems would result in temporary
erosion and sedimentation. These earth impacts would be isolated, small
in size, and occur at various times and locations.
Treatment Facility Location: Split Facility, Existing and New Site
Expanding the existing facility and developing a new facility at a
new site would result in unavoidable adverse impacts to the earth
environment similar to the proposed action. The extent of impact,
however, would differ at the two locations. Excavation impacts at the
existing site would be less as the extent of expansion is less than the
proposed action. Impacts at a new site location would be greater than
the proposed action as excavation of an undeveloped site would likely be
extensive.
New force main pipelines would require trenching and backfilling
that could result in temporary erosion and sedimentation.
Treatment Process: Land Treatment
Excavation for 3.5 miles of pipeline, lift stations, and the primary
treatment lagoon, including some riprapping and blasting, would result in
temporary erosion and sedimentation. Adverse impacts could result from
accumulation of phosphorus in the soil and nitrogen in the groundwater,
although the extent, if any, of this occurrence would not be known until
a monitoring system was est@blished. As previously mentioned, the use of
this alternative would not require outfall construction.
Treatment Process: lKz Disinfection
No unavoidable adverse impacts are anticipated.
Outfall Location: Extend Existin~ to $¢,~th Discharge Point
The outfall discharge pipe would require excavation of about 150
cubic yards of nearshore and intertidal beach sediment. Short-term,
temporary turbidity increases would result from this activity.
-52-
AiR QUALITY
AFFECTED ENVIRONMENT
Air pollution control and enforcement in the Port Ludlow area, and
all of Jefferson, Clallam, Grays Harbor, Mason, Pacific and Thurston
Counties, is the responsibility of the Olympic Air Pollution Control
Authority. This Authority was formed in 1968 and maintains a number of
monitoring stations throughout the control area. Major pollutants
monitored by the Authority are carbon monoxide, nitrogen oxides, ozone,
sulfur dioxide, suspended particulates, lead, and arsenic. Not all of
these pollutants are monitored at every station.
No monitoring station is located in the immediate project vicinity.
The only monitoring station located in Jefferson County is located 15
miles north of Port Ludlow at Port Townsend. In 1983, the annual
geometric mean value for suspended particulates (the only pollutant
monitored at this station) was 29 ~g/ms, well below the federal standard
of 75 ~g/ms and the state standard of 60 ~g/ms. There are no identified
particulate emissions from point sources in the project vicinity.
Particulate emissions from nonpoint sources are primarily attributed to
dust from construction activities and smOke from the use of fireplaces
and wood stoves.
Other pollutants, such as hydrocarbons, nitrogen oxides, and photo-
chemical oxidants from vehicle and boat emissions likely exist in
relatively minor amounts throughout the Port Ludlow area. Relatively
high ozone concentrations occur throughout the Puget Sound area and are
considered a regional problem. Other major sources of pollutants
throughout the control area include mills, veneer dryers, and sand and
gravel companies.
Operation of the existing WICFP may generate obtrusive odors.
Hydrogen sulfide and ammonia are basic elements of sewage and are
generated as a by-product under anaerobic conditions that occur within 20
minutes if sewage is left unoxygenated. Anaerobic conditions may occur
at lift stations during abnormal pumping conditions and at the treatment
plant during unregulated aerobic treatment. Hydrogen sulfide and ammonia
odors generally dissipate within a few hundred feet of the source.
IMPACTS
Proposed Action
Air quality impacts associated with this project would result
principally from three activities' construction, vehicles, and
operation. While under construction, the treatment plant improvements
would result in a temporary deterioration of the ambient air quality.
The use of heavy equipment (backhoe, dump truck, etc.) would likely
increase suspended particulate levels (dust). Vehicular traffic
resulting from ingress and egress of construction vehicles and sludge
hauling transport trucks, as well as probable increases in population as
-53-
vacant lots are developed, would increase ambient levels of carbon
monoxide, hydrocarbons, and photochemical oxidants (sulphur and nitrogen
oxides). As the W%~P reaches ultimate design capacity, obtrusive odors
may increase. Hydrogen sulfide and ammonia odor sources include: bar
screen, aerated grit chamber, sludge, and aeration basin. Odors could be
associated with the transportation of the sludge by truck along its route
and at the sludge utilization site.
Alternatives
Treatment Facility Size: Retain Existing Facility (No Action)
Under this alternative, the existing conditions would continue to
prevail. New lot development would be curtailed; therefore, no new con-
struction would take place and associated increases in suspended partic-
ulates would be minimal.
Treatment Facility Location: Split Facility~ Existing and New Site
Under this alternative, a new site location would result in
operational and vehicular impacts similar to the proposed action. Due to
more site modification and a longer construction period, this option
would create greater construction impacts. The air quality impacts
associated with construction would be dispersed between the two sites.
Treatment Process: Land Treatment
Construction of pipelines, lift stations, and the primary treatment
lagoon would result in temporary increases in suspended particulates.
The majority of the construction activities would be conducted outside of
the developed area of Port Ludlow. The land treatment.process would
reduce the level of oxygen in the sludge and thus increase the hydrogen
sulfide and ammonia by-products. These by-products, characterized as
obtrusive odors, would have little adverse effect as no residents are
located in the immediate area of the land application s~te. It is
estimated the land treatment alternative would require hauling sludge to
a landfill about once every five years. This is not expected to have an
adverse impact on air quality.
Treatment Process: t~ Disinfection
This type of disinfection ~ould have no effect on air quality~ The
use of b~ disinfection would eliminate any chlorine odors generated under
the proposed action.
Outfall Locatfon: Extend Existing to South Discharge Point
Outfall alternatives would have no impact on air quality.
-54-
MITIGATING MEASURES
Proposed Action
Impacts to air quality could be reduced by implementing mitigating
measures. Fugitive dust generated during construction could be mitigated
through the use of control measures, including watering or oiling of
dusty areas and turning off idling equipment. Increased treatment plant
capacity and careful operation by a certified licensed operator would
eliminate obtrusive odors. If odors do persist at the treatment plant,
odor control devices may be installed. Odors from sludge could be reduced
by discing and applying oxidizing agents, such as potassium permanganate.
Alternatives
Treatment Facility Size: Retain Existin~ Facilitv (No Action)
No mitigating measures are suggested.
Treatment Facility Location: Split Facility~ Existing and New Site
Mitigating measures proposed with this alternative are the same as
the proposed action.
Treatment Process: Land Treatment
Mitigating measures to reduce construction impacts are the same as
the proposed action.
Treatment Process: Aerobic Digestion
Since no air quality impacts are likely to occur under this
alternative, no mitigating measures are suggested.
Treatment Process: b%' Disinfection
Since no air quality impacts are likely to occur under this
alternative, no mitigating measures are suggested.
Outfal! Locaticn' Ex?and Existing to South Discharge Point
Since no air ebalitv impacts are likely to occtzr under this
alternative, no mitigating measures arc suggested.
b~AVOIDABLE ADVERSE IMPACTS
Proposed Action
During the construction period, temporary increases of suspended
particulate levels will occur. Vehicular traffic resulting from ingress
and egress of construction vehicles and sludge hauling transport trucks,
as well as increases in population as vacant lots are developed, would
increase ambient levels of carbon monoxide hydrocarbons and photochemical
oxidants. _
'
Alternatives
Treatment Facility Size' Retain Existing Facility (No Action)
Minimal increases of suspended particulates would occur as
individual septic systems are constructed. Obtrusive odOrs may increase
as the existing WWTP reaches its full capacity.
Treatment Facility Location' Split Facilit¥~ Existing and New Site
Unavoidable construction impacts, similar to those described in the
proposed action, would occur. Increased vehicular traffic would occur as
a result of new lot development and hauling of sludge from the existing
and new facility sites.
Treatment Process: Land Treatment
Unavoidable construction impacts would result in similar effects as
the proposed action. Obtrusive odors are likely to occur; however, their
adverse effect on residents is unlikely.
Treatment Process' Aerobic Digestion
No unavoidable adverse impacts are anticipated.
Treatment Process' Ih? Disinfection
No unavoidable adverse impacts are anticipated.
Outfall Location: Expand ExistinG to South Discharge Point
No unavoidable adverse impacts are anticipated.
-56-
WATER
AFFECTED ENVIRONMENT
Physical Settin$
Port Ludlow Bay is a 2.2-square-mile J-shaped area that opens into
Admiralty Inlet near the northern most portion of Hood Canal (see Figure 2).
The bay begins at the mouth of Ludlow Creek and extends 3.5 miles to
the bay's entrance where a low headland protrudes into the bay from the
north shore. The entrance to Port Ludlow Bay is defined by an imaginary
line that extends northerly from Tala Point to the area of Colvos Rocks
and then west through Snake Rock to the mainland. Figure 11 delineates
the bay's boundary, as well as the areas referred to as the inner and
outer bay.
The eastern approach to the bay, between Tala Point and Colvos
Rocks, is characterized by a submerged sill having an average depth of
24 feet mean sea level (MSL). This sill forms a submerged basin open to
the north. The average depth of the opening between Colvos Rocks and
Snake Rock is 82 feet (MSL). From this point, the bottom of the basin
slopes upward for a distance of 0.5 mile to a depth of 50 to 60 feet.
From here, the depth of the bay remains fairly uniform between 50 and 60
feet throughout most of its length to within 0.5 mile of Ludlow Creek.
The innermost 0.5 mile of the bay has an average depth of 16 feet (MSL).
The Port Ludlow k~TP is located on the western shoreline, midway up
the bay. The W~P outfali extends approximately 400 feet from the
western shoreline and discharges through a single port. Water depth at
the existing discharge point is 13 feet at mean lower low water (MLLW)
(see Figure 11).
Currents and Circulation
Various methods were employed to determine the current and
circulation patterns in Fort Ludlow Bay. Detailed description of those
studies is provided in two documents (Harper-Owes, 1985a, Harper-Owes et
al, 1986). In the first study a drogue (parachute-type device) was used
to estimate current velocities and to reveal the general pattern of cir-
culation in the bay. Submers~b!e current ~,-~eters were also used to
measure current velocities at various depths. In the second study,
surface drifters were used at two proposed outfall sites to determine
surface currents under various wind conditions; current meter reading
were also taken. Flushing rates (the time it takes to replace portions
or the entire volume of the bay's water with new water from Admiralty
Inlet) were determined in both cases by the use of the Salt Balance
Equation. This method allows calculations of flushing rates by comparing
the relative salt content of waters inside and outside the bay. Results
of the salt balance equation were consistent with drifter and drogue
study observations. The use of all these methods enables the dominant
processes controlling the current and circulation patterns and flushing
characteristics of Port Ludlow Bay to be described.
-57-
.~rFECTED EhWIROM~iENT
This section was prepared from a site visit conducted in April ]985,
information provided in the existing Port Ludlow South Bay Community EIS
(Jefferson County, 1975), marine bird censuses completed by Wahl, et al.
(1983), and existing literature on wildlife resources of the Pacific
Northwest. Marine biological resources of the Port Ludlow area in the
vicinity of the existing ~fP outfall were inventoried through a litera-
ture review and field surveys conducted in March 1985 and April 1986 (see
Figure ]8). In addition, staff of the Washington Department of Fisheries
(WI)F) were interviewed for updated information on commercially important
resources. Appendix A presents a detailed discussion of the marine
biological resources based on literature review, field survey, and
interviews. The Port Ludlow area was surveyed for marine bird use during
December 1982 and February ]983 (Wahl, et al., ]983) and as part of this
ElS during March 1985.
Terrestrial Vegetation and Wildlife
The ~P is located along the western shoreline of Port Ludlow' Bay.
There are n~erous residential dwellings and condomini~s located along
the shoreline around the bav. The surrounding upland area is a mixture
of deciduous and coniferous forest with riparian habitat along the
streams. Dominant tree and shrub species ~n~lude red alder, black
cottonwood, Douglas fir, western hemlock, western red cedar, salal, sw~rd
ferns, Oregon grape, and sa!monberry. The area provides habitat for ~
wide variety of wildlife. The following species are known to occur en
the upland habitat surrounding the ~P' deer, coyotes, squirrels,
skunks, raccoons, weasels, beavers, mice hawks ~ '~ woodpeckers
upland game birds, and nmmerous song birds.
The existing facility is located on a quarter acre site bordered by
a residential neighborhood to the west and north, ccndomini~s to the
south, and Port LUdlow Bay to the east. The entire site is fenced.
Approximately one-third of the site is covered by impervious surfaces.
There are steep banks (up to 40 feet high on the northern boundary: su~~-
rounding the treatment fac ]~tv mh~c-~ c-~r,~~ ere ~ab~iy~d ~v ~? .......
horsetails, blackberz-ics, ~:-:-ar.~, ~azm:.nz~c :-ic~ anJ ~ ~' b:' .
There are several patches :,f ~,-foot tall yoang red a]oer s~ools at the
top of the banks. Seversl 3-foot ta]_] j,,~Sper trees have been planted
along the roadway. Along the sou'chern bank, several sword fern plants
are growing. Outside the fence line, to the south, are dense young red
alder trees up to 30 feet tall.
The overall wildlife value of the Y~P site is limited by the
following factors: the small size, the amount of urban development and
roadways surrounding the site, the fact that the site is totally fenced,
and the lack of vegetative diversity. The site does not provide the
necessary life requirements of food, shelter, and cover for most
terrestrial wildlife.
.
-82-
Crows are probably the only common wildlife visitor to the WWTP.
Approximately 20 crows were observed at the sewage pond. Other common
birds typically associated with urban areas that could be using the site
are robins, starlings, swallows, rock doves, sparrows, and gulls.
Few mammals are likely to reside in the project area. Shrew, moles,
and mice could inhabit the landscaped areas of the semi-flat portions of
the site. Most likely, raccoons could be found feeding on invertebrates
along the shoreline, outside of the fenced area.
Marine Birds and Mammals
Marine birds and mammals are commonly found in Port Ludlow Bay
throughout the entire year. Marine bird abundance is generally higher in
the fall and winter and lowest in summer, because few species breed in
the Puget Sound area. Bird species richness is generally higher in
protected areas of Puget Sound, such as Port Ludlow Bay, than in open
water (Long, 1983). The Port Ludlow area was ranked 19 out of 28 in
importance for marine bird habitat in the lower Puget Sound and Hood
Canal areas (Wahl, et al., 1983) '
Approximately 44 species of marine and shorebirds, out of 80 common
species (Long, 1983) that regularly occur in Puget Sound, have been
observed in Port Ludlow Bay. This includes two loon species, four grebe
species, two cormorant species, great blue heron, 16 duck species, seven
gull species, four alcid species, and nine shorebird species. In April
1985, the most common species observed were white-winged and surf
scoters, western and horned grebes, American wigeons, glacous-winged
gulls, red-breasted mergansers, and greater scaups. The total number of
birds observed in December 1982, February 1983, and April 1985 are
presented in Table 3.
Table 6
T,~T~r NLPIBERS ~Y _i?~q . ..
v.^~ ,v,,-N=&RiN~ R_ _ OBSERi.~D IN POPT LUDLOW BAY
Daze' December i982 February i983 April 1985
Area Sampled' (!.' mi-) (0.3 mi2) ( 1.5 mi~)
F~'l i LY
Loon ~ 9 5
Grebe 147 2! 77
Cormorant 17 2 2
Great blue heron 1 0 0
Duck 625 19 127
Gull 47 51 35
Alcid 17 11 13
Total 855 113 259
Large numbers of birds are found in areas where prey species concen-
trate, such as tidal fronts and eddies .... ~s occurs in passages such as
at the mouth of Port Ludlow Bay. Diving birds (e.g., grebes, loons,
Brandt's cormorants, scorers, marbled murrelets, rhinoceros auklets, and
common murres) that feed on small fish and invertebrates are the most
common species. Dabbling ducks (e.g., American wigeons, mallards) and
shorebirds (e.g., sandpipers, killdeers) are common in the intertidal
areas where they feed on exposed surfaces. Great blue herons wade along
the tide line feeding on fish. Gulls are found in all these habitats.
Harbor seals commonly occur in Port Ludlow Bay. A commonly used
haul out site is located north of Port Ludlow Bay (Natural Heritage Data
Program, 1985). River otters also have been observed in Port Ludlow Bay
(Natural Heritage Data Program, 1985). Although they have not been
reported, several other marine mammals species could use these waters,
including' California sea lions, Stellar's sea lions, minke whales,
killer whales, grey whales; harbor porpoises, and Dali's porpoises.
Whales and porpoises usually forage in open water and rarely use
intertidal or shallow subtida! habitats.
The present WWTP outfall into Port Ludlow Bay does not appear to
affect marine invertebrates or fish resources of the area (see Marine
Invertebrate and Fisheries sections). Since the aquatic resources have
not been affected, it is presumed no subsequent effect on marine bird and
mammal use has occurred.
Threatened and Endangered Species
Bald eagles, a threatened species, have been observed year-round in
the Port Ludlow area. Eagles are probably feeding on waterfowl, fish,
and marine birds. There are large trees available for roosting all along
the shoreline of Pert. Ludlow Bay. There .~re two bald eagle's nests and
an osprey nest located !ess than a mile from the project site (Natural
Heritage Data Program, 19851).
Plankton
The planktonic assemblage %hat would probably be most affected by
the proposed project ~ou!d be the phytoplankton. The only known study on
nutrients and chlorophyll a levels in ?oru Ludlow Bay was conducted by
Harpe--~w~~ ...... ~!~~'~,~...., ' ?ki~' ~tudv ~,'~ _..,~,,~._ theft nut~ier~t~ ~ :;!'re£en and
· ' . '~--' ~he ?cr~ Ludlow Bay phv~oplankton are
nearby Admiralty inlet
limited by nitrogen levels. Harper-Owes also found the existing effluent
apparently has little effect on nutrient levels, even under worst case
situations. This is presumably due :o relatively rapid flushing rates
and large dilutions.
In addition to relatively low nutrient levels in Port Ludlow Bay,
Harper-Owes also recorded a lack of substantial suspended algal growth
relative to areas in Admiralty Inlet. Port Ludlow Bay is a comparatively
clear, well-flushed bay. These conditions encourage growth of attached
benthic plants rather than suspended phytoplankton (Harper-Owes, 1985).
-85-
Marine Benthic Habitats
The intertidal and subtidal marine habitats in the vicinitv of the
Port Ludlow WWTP outfall are predominantly sand and si]tv sand
substrates. Occasional areas of harder substrate are present, mostly in
the form of boulders or patches of mixed coarse sand, gravel, and
cobbles. The sandy sediment gradually becomes more rocky to the north,
where the upper and middle portions of the beach are mixed coarse habitat
consisting of gravel, cobbles, and boulders in a Sandy matrix. The most
important habitat in Port Ludlow Bay is probably the extensive eelgrass
beds (Zostera marina and ~. japonica) prevalent throughout the lower
intertidal and upper subtidal areas. No extensive beds of benthic algae,
such as kelp, are reported in Port Ludlow Bay.
Marine Plants
The extensive eelgrass beds in Port Ludlow Bay form a distinct
biological habitat. An introduced species of eelgrass, ~. japonica,
forms a bed with occasional small interrupting patches of bare sand 800
yards to the south and ] 000 yards north of the existing outfal] Den-
.sities of the intertidal beds are approximately 280 plants per square
meter. The width of the beds range from about 6 to over 60 feet with an
average width of 44 feet. The ~. japonica is replaced in the shallow
subtidal by narrow beds of ~. marina, the native eelgrass.
A dense cover of sea lettuce (U2va 2actuca) is present at the top of
the underwater slope and extends shoreward to the lower edge of the
eelgrass bed. This algae covers approximately 50 to 100 percent of the
bottom. Interspersed with the sea lettuce is the red algae Neo~ardhieiia
baileFi. The sand under and between the sea lettuce and red algae is
covered with brown filamentous diatoms.
Marine Invertebr.ates
The intertidal beaches along the Tala Point shore opposite the
existing ~r~F outfaii are_~u~ct~ to large amounts of mebile sand and
fresh water, apparently originating from the bluffs behind the beaches.
In addition to normal conditions of desiccation, temperature variations,
and wave shock, the stresses imposed on the intertidal biological
comm. uni~y by the s~nd and fresh water .apFe~~ tc~ have significantly
inhibited the development of kigh abundan.::e and diversity i~ the
intertidal assemblages. Only where t. he movement of sand and the flows of
fresh water are reduced does the diversity and abundance of animals
living within the sediment approach expected normal levels.
The clam genus ~acoma is specifically adapted to these conditions,
and is well represented in Port Ludlow Bay. Also present in Port Ludlow
Bay are mobile polychaete worms, occasional horse clams (Tresus sp.), and
two tube worms, Spiochaetopte~us costarum and Diopatra ornata; none of
these species are plentiful (Appendix A). On the South Bay shore, across
the bay from the marina, a small patch of sulphur bacteria was noted on
the sandy substrate below MLLW. These bacteria are generally found at
sites of buried decomposing materials, such as an animal carcass or
leachate from a failiug septic tank.
-86-
At a few locations on both beaches, hard substrate composed of
rocks, debris, and pilings are present. The biological community on
these hard substrate materials appears to be heavily influenced by the
predominate sand and fresh water and by the effects of logs floating in
the bay. Normal encrusting assemblages in Port Ludlow Bay, however, are
similar to those found throughout Puget Sound in small embayments on
stable substrates. For instance, on an old shipwreck opposite the Port
Ludlow resort, a well-established encrusting assemblage of barnacles and
blue mussels was observed in March 1985. The adults and juveniles
comprising this assemblage indicate that the community has been covering
this substrate for a number of years.
The subtidal animal community is much more diverse and abundant than
the intertidal, a common situation in Puget Sound. Seapens, burrowing
anemones, small hermit crabs, and sand shrimp characterize the deeper
areas at the outer end of the proposed outfall corridor (Appendix A). In
shallower water, at the level of the existing outfall, the subtidal
animal community is characterized by small snails associated with the
macroalgae, nudibranchs, and abundant burrowing shrimp. Chitons, tube
worms, whelks, sea cucumbers, nudibranchs, and seastars were observed on
the rocks associated with the existing sewer pipeline (Appendix A). No
invertebrate populations capable of supporting a substantial fishery were
observed, nor have any been reported in existing literature (Appendix A).
At the base of the submerged slope, a population of geoduck clams
(Panope ~enerosa) is present with an estimated density of 326 to 365 per
900 square feet (this unit is used in WI)F surveys). The geoducks are
restricted to depths below approximately -25 feet (MLLW) throughout the
outer bay area. Surveys conducted by W~F found no commercially important
geoduck populations or other hardshell clams in Port Ludlow Bay (Appendix
A). The~ observed geoduck population may be extensive enough to be
commercially harvestable.
The nearest co~merciat!y important shellfish (hardsheil clam,
geoduck, and oyster) beds are located between Tala Point and Colvos
Rocks. These have been commercially harvested for up to 15 years,
producing an average $!,000 pounds annually (Goodwin, 19~5; Hoyser,
1985). In !984, this average harvest was ~orth about $!2 000 (Ward,
1985; Hoyser, 1985).
Because of ~he ]~,-i< cf an~.' s!~'~if~'~ ~he]l~i~n re~c~.rcc-s west of
~ala ro ~ iht aha Ccl',cs ':-,ceiL2 LA :i~r% _kiLl.'-.' c,~','~
is probahiv not affecting any fiskers: resources. ?}~e szudy by Harper-
Owes (!985) found that residual chlorine levels potentially harmful to
the biological ¢omaunity are limited to = circle with a radius of about
120 to 200 feet around the existing outfall. The o~tfal! is located too
far from the substantial clam beds at Colvos Rocks to affect any fisheries.
Prior to recent ~w~P improvements and during periods of high recrea-
tional boating activity, the effluent discharge from the W~P and the
wastewater discharge from recreational boaters contributed about equally
to the high fecal coliform counts in the bay (Harper-Owes, 1985). After
WWTP improvements, water quality studies indicated that fecal coliform
-87-