HomeMy WebLinkAboutFinal 18.40 2018 DCD Li-LoJefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 1/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
Chapter 18.40
PERMIT APPLICATION AND REVIEW PROCEDURES/SEPA IMPLEMENTATION
Sections:
Article I. Types of Project Permits
18.40.010 Purpose.
18.40.020 Procedures for processing project development permit applications.
18.40.030 Determination of proper type of procedure.
18.40.040 Project permit application framework.
18.40.050 Joint public hearings (other public agency hearings).
18.40.060 Legislative enactments.
18.40.070 Legislative enactments not restricted.
18.40.080 Exemptions from project permit processing.
Article II. Project Permit Applications (Type I – IV)
18.40.090 Preapplication conference.
18.40.100 Development permit application.
18.40.110 Submission of acceptance of application determination of completeness – Additional information and
project revision.
18.40.120 Referral and review of development permit applications.
18.40.130 Scope of project review.
18.40.140 Project consistency.
Article III. Public Notice Requirements
18.40.150 Public notice – Generally.
18.40.160 Notice of application – When required.
18.40.170 Notice of application – Time of issuance.
18.40.180 Notice of application – SEPA exempt projects.
18.40.190 Notice of application – Contents.
18.40.200 Notice of application – SEPA integration.
18.40.210 Notice of application – Mailing, publication, and posting requirements.
18.40.220 Notice of application – Public comment.
18.40.230 Notice of public hearing.
18.40.240 Additional public notice requirements – Type III preliminary plat actions.
18.40.250 Optional additional public notice.
Article IV. Project Review and Approval Processes
18.40.260 Administrative approvals without notice (Type I).
18.40.270 Administrative approval subject to notice (Type II).
18.40.280 Hearing examiner review and decision (Type III decisions and appeals of Type II decisions).
18.40.290 Board of county commissioners action (Type IV decisions).
18.40.300 Procedures for public hearings.
18.40.310 Reconsideration.
18.40.320 Final decision.
Article V. Appeals
18.40.330 Administrative appeals.
18.40.340 Judicial appeals.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 2/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
Article VI. Unified Development Code Interpretation
18.40.350 Purpose.
18.40.360 Submission requirements.
18.40.370 Administrator’s decision.
18.40.380 Time limitation and enforcement.
18.40.390 Appeals of administrator’s interpretations.
18.40.400 Judicial appeal.
Article VII. Site Plan Approval Advance DeterminationsRepealed.
18.40.410 Purpose.
18.40.420 Scope.
18.40.430 Application requirements.
18.40.440 Application review.
18.40.450 Approval criteria.
18.40.460 Duration of approval.
18.40.470 Limitations on approval.
18.40.480 Modifications to an approved site plan.Repealed
Article VIII. Conditional Uses
18.40.490 Purpose.
18.40.500 Scope.
18.40.510 Application submittal and contents.
18.40.520 Conditional use permit types – Review processes.
18.40.530 Approval criteria for all conditional uses.
18.40.540 Additional conditions.
18.40.550 Use of property before final decision.
18.40.560 Effective period – Expiration.
18.40.570 Modification of a conditional use permit.
18.40.580 Conditional use permit to run with the land.
18.40.590 Permit suspension or revocation.
18.40.600 Assurance device.
Article IX. Variances (Minor and Major)
18.40.610 Purpose.
18.40.620 Scope.
18.40.630 Application submittal and contents.
18.40.640 Variance types – Review processes.
18.40.650 Approval criteria.
18.40.660 Additional conditions.
18.40.670 Limitation on authority.
18.40.680 Effective period – Expiration.
18.40.690 Assurance device.
Article X. State Environmental Policy Act (SEPA) Implementation
18.40.700 Authority.
18.40.710 Purpose.
18.40.720 Responsible official – Decision-making authority.
18.40.730 Lead agency determination and responsibilities.
18.40.740 Initiation of SEPA review – Limitations on actions during review.
18.40.750 Categorically exempt actions – Use of existing documents and analyses.
18.40.760 Analysis of nonexempt project and nonproject actions.
18.40.770 Substantive authority.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 3/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
18.40.780 Public notice and comment.
18.40.790 Public hearings and meetings.
18.40.800 Environmentally sensitive areas.
18.40.810 Appeals.
Article XI. Development Agreements
18.40.820 Purpose.
18.40.830 General requirements.
18.40.840 Development standards to be addressed.
18.40.850 Procedures.
18.40.860 Effect.
Article I. Types of Project Permits
18.40.010 Purpose.
Articles I through VI of this Unified Development Code are a mechanism for implementing the provisions of
Chapter 36.70B RCW (the Local Project Review Act) regarding compliance, conformity, and consistency of
proposed projects with the Jefferson County Comprehensive Plan and development regulations.
(1) Given the extensive investment that public agencies and a broad spectrum of the public have made and will
continue to make in Jefferson County’s Comprehensive Plan and development regulations, it is essential that project
review start from the fundamental land use planning choices made in the Comprehensive Plan and regulations. If the
Comprehensive Plan or regulations identify the type of land use, specify density and identify and provide for the
provision of public facilities needed to review the proposed development and site, these decisions, at a minimum,
provide the foundation for further project review unless there is a question of code interpretation. The project review
process, including the environmental review process under Chapter 43.21C RCW and the consideration of
consistency, should start from this point and should not reanalyze these land use planning decisions in making a
permit decision, unless the county finds that the Comprehensive Plan and regulations do not fully foresee site-
specific issues and impacts identified through land use project application review.
(2) Comprehensive plans and development regulations adopted by the county under Chapter 36.70A RCW (the
Growth Management Act), sub-area plans, and environmental policies, laws and rules adopted by the county, the
state, and the federal government address a wide range of environmental subjects and impacts. These provisions
typically require environmental studies and contain specific standards to address various impacts associated with a
proposed development (e.g., building size and location, drainage, transportation requirements, and protection of
environmentally sensitive areas). When the county applies these existing requirements to a proposed project, some
or all of a project’s potential environmental impacts may be avoided or otherwise mitigated. Through the integrated
project review process described in Articles I through V of this chapter, the administrator will determine whether
existing requirements, including the applicable regulations or plans, adequately analyze and address a project’s
environmental impacts. Project review generally should not require additional studies and mitigation under Chapter
43.21C RCW where existing regulations adequately address a proposed project’s probable significant adverse
environmental impacts. Development regulations enable project review through the application of established
scientific standards, required studies and standard mitigation measures. [Ord. 8-06 § 1]
18.40.020 Procedures for processing project development permit applications.
For the purpose of project permit processing under this code, all development permit applications shall be classified
as one of the following: Type I, Type II, Type III, or Type IV. Legislative decisions are classified as Type V actions
and are addressed in Chapter 18.45 JCC. Exemptions from the requirements of project permit application processing
are set forth in JCC 18.40.080. [Ord. 8-06 § 1]
18.40.030 Determination of proper type of procedure.
(1) Determination by the Administrator. The administrator shall determine the proper procedure for all development
applications. If there is a question as to the appropriate type of procedure, the administrator shall resolve it in favor
of the higher numbered procedure type, except as specifically authorized for discretionary conditional use permits
under JCC 18.40.520(2).
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 4/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) Optional Consolidated Permit Processing. An application that involves two or more procedures may be
processed collectively under the highest numbered procedure required for any part of the application or processed
individually under each of the procedures identified by this code. The applicant may determine whether the
application shall be processed collectively or individually. If the application is processed under the individual
procedure option, the highest numbered type procedure must be processed prior to the subsequent lower numbered
procedure.
(3) Decision-maker(s). The board of county commissioners is the highest decision-maker, followed by the hearing
examiner and the administrator. Joint public hearings with other agencies shall be processed in accordance with JCC
18.40.050.
(4) Administrator. Upon issuance of a determination of completeness as described in JCC 18.40.110, the
administrator shall assign a project planner to the project who will coordinate and be responsible for all phases of
development application administration.
(5) SEPA Review. Project review conducted pursuant to the State Environmental Policy Act (SEPA), Chapter
43.21C RCW, shall occur concurrently with project review. The SEPA review process, including all public
comment procedures, is set forth in Article X of this chapter. Nothing contained in Articles I through V of this
chapter shall be construed as restricting the need for full environmental review in accordance with Articles VI-C
through VI-K of Chapter 18.15 JCC, and Article X of this chapter. [Ord. 8-06 § 1]
18.40.040 Project permit application framework.
Table 8-1. Permits – Decisions
Type I1 Type II Type III Type IV Type V
Septic permits Classification of unnamed
and discretionary uses under
Article II of Chapter 18.15
JCC
Reasonable economic use
variances under JCC
18.15.220
Final plats
under Chapter
18.35 JCC
Special use permits, such as
for siting Essential Public
Facilities under JCC
18.15.110
Allowed uses not requiring
notice of application (e.g.,
“Yes” uses listed in Table 3-1 in
JCC 18.15.040, building
permits, etc.)
Release of six-year FPA
moratorium for an individual
single-family residence under
JCC 18.20.160
PRRDs under Article VI-M
of Chapter 18.15 JCC and
major amendments to PRRDs
under JCC 18.15.545(3)
Final PRRDs
under Article
VI-M of
Chapter 18.15
JCC
Jefferson County
Comprehensive Plan
amendments under Chapter
18.45 JCC
Minor amendments to planned
rural residential developments
(PRRDs) under JCC 18.15.545
Cottage industries under JCC
18.20.170
Shoreline substantial
development permits for
secondary uses, and
conditional and variance
permits under the Jefferson
County Shoreline Master
Program (SMP)
Amendments to
development regulations
including amendments to
this UDC and the Land Use
Districts Map
Home businesses approved
under JCC 18.20.200
Short subdivisions under
Article IV of Chapter 18.35
JCC
Plat alterations and vacations
under JCC 18.35.030(3)
Amendments to the
Jefferson County SMP
Temporary outdoor use permits
under JCC 18.20.380
Binding site plans under
Article V of Chapter 18.35
JCC
Long subdivisions under
Article V of Chapter 18.35
JCC
Subarea and utility plans and
amendments thereto
Stormwater management
permits under JCC 18.30.070
Administrative conditional
use permits under JCC
18.40.520(1) [i.e., listed in
Table 3-1 in JCC 18.15.040
as “C(a)”]
Discretionary conditional use
permits under JCC
18.40.520(2) [i.e., listed in
Table 3-1 in JCC 18.15.040
as “C(d)”] where required by
administrator
Development agreements
and amendments thereto
under Article XI of this
chapter
Road access permits under JCC
18.30.080
Discretionary conditional use
permits under JCC
18.40.520(2) [i.e., listed in
Table 3-1 in JCC 18.15.040
as “C(d)”] unless Type III
Conditional use permits under
JCC 18.40.520(3) (i.e., uses
listed in Table 3-1 in JCC
18.15.040 as “C”)
Master plans for master
planned resorts
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 5/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
Type I1 Type II Type III Type IV Type V
process required by
administrator
Sign permits under JCC
18.30.150
Minor variances under JCC
18.40.640(1)
Major variances under JCC
18.40.640(2)
Boundary line adjustments
under Article II of Chapter
18.35 JCC
Shoreline substantial
development permits for
primary uses under Jefferson
County SMP
Wireless telecommunications
permits under JCC 18.20.130
and Chapter 18.42 JCC
Minor adjustments to approved
preliminary short plats under
JCC 18.35.150
Wireless telecommunications
permits under JCC 18.20.130
and Chapter 18.42 JCC
Major industrial development
conditional use approval
under Article VIII of Chapter
18.15 JCC
Forest practices release of a
moratorium under Chapter
18.20 JCC
Minor amendments to approved
preliminary long plats under
JCC 18.35.340
Small-scale recreation and
tourist (SRT) uses in SRT
overlay district under JCC
18.15.572.
Plat alterations under JCC
18.35.670.
Appeals of enforcement
actions under Chapter 18.50
JCC
Site plan approval advance
determinations under Article
VII of this chapter and
boundary line agreements under
Article VIII of Chapter 18.35
JCC
Exemptions under the Jefferson
County SMP
Revisions to permits issued under the Jefferson County SMP
1 If not categorically exempt pursuant to SEPA, Type I projects shall be subject to the notice requirements of JCC 18.40.150
through 18.40.220 and Article X of this chapter (the SEPA integration section).
Table 8-2. Action Types – Process
Project Permit Application Procedures (Types I – IV) Legislative
Type I Type II Type III Type IV Type V
Recommendation
made by:
Project planner Project planner Project planner N/A Planning commission1
Final decision
made by:
Administrator Administrator Hearing examiner Board of county
commissioners
Board of county
commissioners
Notice of application: No Yes Yes No N/A
Open record
public hearing:
No Only if
administrator’s
decision is appealed,
open record hearing
before hearing
examiner
Yes, before hearing
examiner, prior to
permit decision by
the hearing examiner
No Yes, before planning
commission to make
recommendation to board
of county commissioners
Closed record
appeal/final decision:
No No No N/A Yes, or board of county
commissioners could hold
its own hearing
Judicial appeal: Yes Yes Yes Yes Yes2
1Type V land use actions are subject to review and recommendation by the planning commission. However, utility plans
and moratoria and interim zoning controls adopted under RCW 36.70A.390 are not subject to review and consideration
by the planning commission.
2Pursuant to RCW 36.70A.250 and 36.70A.280, the Western Washington Growth Management Hearings Board
(WWGMHB) is authorized to hear and determine petitions alleging that the county is not in compliance with the
requirements of Chapter 36.70A RCW, Chapter 90.58 RCW as it relates to the adoption of the Shoreline Master
Program, or Chapter 43.21C RCW as it relates to plans, development regulations, or amendments, adopted under RCW
36.70A.040 or Chapter 90.58 RCW. Direct judicial review may also be obtained pursuant to RCW 36.70A.295.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 6/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
If not categorically exempt pursuant to SEPA, Type I projects shall be subject to the notice requirements of JCC
18.40.150 through 18.40.220 and Article X of this chapter (the SEPA integration section).
SUMMARY OF DECISION-MAKING
Type I: In most cases, administrative without notice. However, if a Type I permit is not categorically exempt under SEPA, then,
administrative with notice.
Type II: Administrative with notice. Final decision by administrator unless appealed. If appealed, open record hearing and final
decision by hearing examiner.
Type III: Notice and open record public hearing before the hearing examiner. Final decision by hearing examiner. Appeal to
superior court.
Type IV: Closed record decision by board of commissioners during a regular public meeting. Type IV decisions are purely
ministerial in nature (see Article IV of Chapter 18.35 JCC).
Type V: Except for utility plans, notice and public hearing before planning commission, with planning commission
recommendation to board of commissioners. Notice of public hearings provided prior to final legislative decisions (see
Chapter 18.45 JCC).
[Ord. 8-06 § 1]
18.40.050 Joint public hearings (other public agency hearings).
(1) Administrator’s Decision to Hold Joint Public Hearings. The administrator may combine any public hearing on a
project permit application with any hearing that may be held by another local, state, regional, federal, or other
agency on the proposed action, as long as the hearing is held within the county and the requirements of subsection
(3) of this section are met.
(2) Applicant’s Request for a Joint Hearing. The applicant may request that the public hearing on a permit
application be combined as long as the joint hearing can be held within the time periods set forth in this chapter. In
the alternative, the applicant may agree to a particular schedule if additional time is needed in order to complete the
hearings.
(3) Prerequisites to a Joint Hearing. A joint public hearing may be held with another local, state, regional, federal or
other agency and the county, as long as:
(a) The other agency is not expressly prohibited by statute from doing so;
(b) Sufficient notice of the hearing is given to meet each of the agencies’ adopted notice requirements as set
forth in statute, ordinance or rule; and
(c) The agency has received the necessary information about the proposed project from the applicant in enough
time to hold its hearing at the same time as the local government hearing. [Ord. 8-06 § 1]
18.40.060 Legislative enactments.
(1) Decision. The following decisions are legislative, and are not subject to the procedures in this chapter, unless
otherwise specified:
(a) Unified Development Code text, and land use district amendments (i.e., Land Use Map amendments);
(b) Area-wide rezones to implement county policies contained within the Jefferson County Comprehensive
Plan and amendments thereto;
(c) Adoption of the Jefferson County Comprehensive Plan and any plan amendments;
(d) Shoreline master program adoption and amendments; and
(e) All other master land use, subarea, functional and/or utility plans and amendments thereto.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 7/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) Procedures. Except as otherwise provided in this chapter, the procedures for the legislative decisions specified in
this chapter are set forth in Chapter 18.45 JCC. [Ord. 8-06 § 1]
18.40.070 Legislative enactments not restricted.
Nothing in this chapter shall limit the authority of the county to make changes to the Jefferson County
Comprehensive Plan as part of an annual revision process, this Unified Development Code or any of the county’s
other development regulations, or to undertake any other legislative actions. [Ord. 8-06 § 1]
18.40.080 Exemptions from project permit processing.
(1) Applicability. Whenever a permit or approval in the Jefferson County Unified Development Code has been
designated as a Type II, III or IV permit, the procedures set forth in Articles I through IV of this chapter shall be
followed in project permit processing. The following permits or approvals are specifically excluded from the
procedures set forth in this chapter:
(a) Landmark designations;
(b) County road vacations; and
(c) As authorized under RCW 43.21C.031 (2)(a), public works projects identified as planned actions in the
Jefferson County Comprehensive Plan or any amendments thereto. Planned actions are those public or private
projects specifically identified by county ordinance or resolution adopted after environmental review conducted
in conjunction with the adoption or annual amendment of the Comprehensive Plan.
(2) Exemptions. If categorically exempt under SEPA, Chapter 432.321C RCW, Type I permits shall not be subject
to the following provisions contained in this chapter1:
(a) The notice of application requirements of JCC 18.40.150 through 18.40.220;
(b) Except as provided in RCW 36.70B.140, optional consolidated project permit review processing under JCC
18.40.030(2);
(c) Joint public hearings under JCC 18.40.050; and
(d) A single report stating that all decisions and recommendations made as of the date of the report on all
project permits included in the consolidated permit process that do not require an open public record
predecision hearing and any recommendations on project permits that do not require an open record predecision
hearing, as further set forth in RCW 36.70B.060(5).
(3) Notice of Decision. Unless the applicant waives the time deadlines in writing, all Type I permits shall be
processed within 120 calendar days after the applicant files a complete application, subject to JCC 18.40.110. [Ord.
8-06 § 1]
Article II. Project Permit Applications (Type I – IV)
18.40.090 Preapplication conference.
(1) Purpose. Preapplication conferences provide a prospective applicant and the county the opportunity to determine
if and how the regulations (e.g., environmentally sensitive areas and SEPA) may apply, an opportunity to acquaint
the applicant with the requirements of the Jefferson County Unified Development Code, and to discuss, if
applicable, how the applicant may modify the scope and design of the project to reduce or avoid restrictions which
may be imposed by the county.
(2) When Required. Preapplication conferences are required for all Type II, Type III, Type IV and Type V project
applications and Type I project applications proposing impervious surfaces of 10,000 square feet or more and/or
non-single-family structures of 5,000 square feet or more. Additionally, preapplication conferences are required for
industrial, commercial, and critical area stewardship plan applications. The administrator may exercise discretion
not to require a preapplication conference if the administrator determines that the conference information is self-
evident, already transmitted, or would not add value to the subsequent application. Preapplication conferences for
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 8/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
all other types of applications are optional, and requests for conferences will be considered by the administrator on a
time-available basis.
(3) Scheduling and Conceptual Design Review. The conference shall be held within 15 calendar days of the request
and payment of the fee set forth in the Jefferson County fee ordinance. The preapplication conference for a new
personal wireless facility shall be scheduled at such time the applicant demonstrates that the required notice in JCC
18.42.070 (2) was mailed to all other wireless providers licensed to provide services within Jefferson County. Upon
payment of the fee, the applicant shall submit to DCD a preliminary sketch or conceptual design that illustrates the
applicant’s generalized ideas of the proposal. This should include approximate lot lines, general topography of the
site, suggested vehicle access to the site, and provision of utilities. Final drawings are discouraged at this
preapplication stage. Additionally, the applicant shall identify all land uses on adjacent properties and all platted and
opened roads serving the site.
(4) Information Provided to Applicant. At the conference, the administrator shall provide the applicant with:
(a) A list of the requirements for a completed application;
(b) A general summary of the procedures to be used to process the application;
(c) The references to the relevant code provisions or development standards that may apply to the approval of
the application; and
(d) A list of any applicable hourly review fees that may be charged by one or more county agencies upon the
filing of a project permit application with the county.
(5) Assurances Unavailable. It is impossible for the conference to be an exhaustive review of all potential issues.
The discussions at the conference or the information provided by the administrator shall not bind or prohibit the
county’s future application or enforcement of all applicable laws and regulations. No statements or assurances made
by county representatives shall in any way relieve the applicant of his or her duty to submit an application consistent
with all relevant requirements of county, state and federal codes, laws, regulations and land use plans. [Ord. 3-13 §
1]
18.40.100 Development permit application.
(1) Information Required for All Applications. Applications for project permit decisions shall be submitted upon
forms provided by the administrator. A project permit application is complete when it meets the submission
requirements of this section. An application shall consist of all materials required by the relevant section of this code
or other applicable county ordinance or regulation, and shall also include the following general information:
(a) A completed project permit application form, including a SEPA checklist unless categorically exempt from
SEPA;
(b) A verified statement by the applicant that the property affected by the application is in the exclusive
ownership of the applicant, or that the applicant has submitted the application with the written consent of all
owners of the affected property, and proof of ownership of the property;
(c) Identification of a single contact person or entity to receive determinations and notices required by this
code;
(d) A legal description of the site, including the Jefferson County assessor’s parcel number;
(e) Payment of Tthe applicable fee as set forth in the Jefferson County fee ordinance;
(f) For each building permit necessitating potable water, evidence of available and adequate water supply and,
if applicable, compliance with the requirements established by the Jefferson County department of health for
the provision of water; evidence may be in the form of a water right permit from the Department of Ecology, or
another form sufficient to verify the existence of an adequate water supply;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 9/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(g) Evidence of septic approval, a valid pending septic application, or sewer availability and, if applicable,
compliance with the requirements established by the Jefferson County department of health for wastewater
disposal;
(h) A site plan, showing the location of all proposed lots and points of access and identifying all easements,
deeds, restrictions or other encumbrances restricting the use of the property, if applicable. All information
should be accurate, legible and generally should be drawn to a scale no smaller than one inch equals 50 feet for
a plot larger than one acre and no smaller than one inch equals 25 feet for a plot one acre or smaller; and
(i) Identification of other local, state and federal permits required for the proposal, to the extent known by the
applicant.
(2) Commercial, Industrial, Multifamily and Small-Scale Recreational and Tourist Uses – Additional Application
Requirements. In addition to the general information required under subsection (1) of this section, all building
permit applications involving commercial, industrial, multifamily, and small-scale recreational and tourist uses listed
in Table 3-1 in JCC 18.15.040 shall include a site plan prepared by a civil engineer, architect or landscape architect
licensed in the state of Washington that includes or graphically depicts the following information:
(a) Compass direction and graphic scale;
(b) Total gross acreage;
(c) Proposed and existing structures including building envelopes and building setback lines;
(d) Distances between all proposed and existing buildings;
(e) All proposed or existing uses;
(f) The layout of an internal vehicular and pedestrian circulation system, including proposed ingress and egress
for vehicles and roadway widths, and additional right-of-way if required on substandard roads;
(g) The location of significant geographic features on the site and immediately adjoining properties;
(h) Corner grades and existing contours of topography at five-foot contour intervals;
(i) Proposed development or use areas;
(j) Property lines, adjoining streets, and immediately adjoining properties and their ownership;
(k) Existing and proposed grades and volume and deposition of excavated material;
(l) A preliminary drainage plan;
(m) Locations of all existing and proposed utility connections;
(n) Parking spaces and driveways;
(o) Proposed landscaping; and
(p) The location and extent of wetlands, floodplains and other environmentally sensitive areas.
(3) Additional Application Requirements. In addition to the information required under subsections (1) and (2) of
this section, the administrator may require additional information or studies in order for the application to be
considered complete. Such information may include, but is not necessarily limited to, the following:
(a) A phasing plan, acreage of phases, and time schedule, if the site is intended to be developed in phases;
(b) Enumeration of the number of persons that will reside in a dwelling(s);
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 10/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(c) Documentation of the date and method of segregation for the subject property verifying that the lot or lots
were not created in violation of the subdivision (i.e., either short or long) laws in effect at the time of creation,
or identifying whether the lots were created prior to the advent of Chapter 58.16 RCW in 1937 (now codified in
Chapter 58.17 RCW);
(d) A recorded survey of the subject property in order to verify property boundaries and setback measurements.
(4) Application Requirements in Other Applicable Regulations. Applications for the following land use permits must
satisfy JCC 18.40.100(1), (2) and, if required, (3), and the following provisions of this Unified Development Code
and applicable county ordinances and regulations:
(a) Building permits under the Jefferson County building code, Chapter 15.05 JCC, or its successor ordinance;
(b) On-site septic systems pursuant to Chapter 8.15 JCC;
(c) Reasonable economic use variance permits under JCC 18.15.220;
(d) Planned rural residential developments (PRRDs) under Article VI-M of Chapter 18.15 JCC;
(e) Cottage industries under JCC 18.20.170;
(f) Home businesses under JCC 18.20.200;
(g) Temporary outdoor use permits under JCC 18.20.380;
(h) Stormwater management permits under JCC 18.30.070;
(i) Sign permits under JCC 18.30.150;
(j) Boundary line adjustments under Article II of Chapter 18.35 JCC;
(k) Short plats under Article III of Chapter 18.35 JCC;
(l) Long plats under Article IV of Chapter 18.35 JCC;
(m) Binding site plans under Article V of Chapter 18.35 JCC;
(n) Site plan approval advance determinations under Article VII of Chapter 18.40 JCC;
(o) Written exemptions, shoreline substantial development permits for primary and secondary uses, and
shoreline conditional use and variance permits under the Jefferson County Shoreline Master Program;
(p) Wireless telecommunications permits under JCC 18.20.130 and Chapter 18.42 JCC; and
(q) Plat alterations under Article VII of Chapter 18.35 JCC.
All application requirements identified in other code sections that supplement or supersede the requirements of this
chapter shall be met before an application is deemed complete.
(5) Waivers. The administrator may waive any specific submittal requirements determined to be unnecessary for
review of any application. In such event, the administrator shall document the waiver in the project file or project
log. [Ord. 8-06 § 1]
18.40.110 Submission of acceptance ofDetermination of complete application determination of
completeness – Additional information and project revision.
(1) Determination of Completeness. Within 28 calendar days after receiving a project permit application the
administrator shall mail a determination to the applicant that states either that:
(a) The application is complete; or
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 11/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(b) The application is incomplete and information necessary to make the application complete.
(2) Identification of Other Agencies with Jurisdiction. To the extent known by the county, other agencies with
jurisdiction over the project permit application shall be identified in the county’s determination of completeness.
(3) Incomplete Application Procedure – Appeal.
(a) If the applicant receives a determination that the application is incomplete or that additional information is
required, the applicant shall have 90 calendar days to submit the necessary information to the administrator, or
to appeal the decision to the hearing examiner in accordance with the procedures for Type II projects. Within
14 calendar days after the applicant has submitted the additional information, the administrator shall again
make the determination described in subsection (2) of this section.
(b) If the applicant refuses to submit additional information, does not request additional time to submit the
required information within the 90-calendar-day period, or does not appeal the decision, the application will be
considered abandoned and therefore withdrawn and the applicant shall forfeit the application fee. The
department of community development shall not be responsible for notifying the applicant of an impending
expiration.
(4) County’s Failure to Provide a Determination of Completeness. A project permit application shall be deemed
complete under this section if the administrator does not provide a written determination to the applicant that the
application is incomplete as provided in subsection (1) of this section. Notwithstanding a failure to provide a
determination of completeness, the administrator may request additional information as provided in subsection (6) of
this section.
(5) Date of Acceptance of Application. A project permit application is complete for purposes of this section when it
meets the submission requirements in JCC 18.40.100, as well as any additional submission requirements contained
in other applicable provisions of this code. This determination of completeness shall be made when the application
is sufficient for continued processing even though additional information may be required or project modifications
may be undertaken after submittal. When the project permit application is determined to be complete, the
administrator shall accept it and note the date of acceptance in the project file. Upon providing a determination of
completeness, the administrator shall assign the project to a project planner.
(6) Additional Information. The administrator’s determination of completeness shall not preclude the administrator
from requiring additional information, that the applicant correct plans or perform studies at any time if new
information is required for project review, or if there are substantial changes in the proposed action.
(a) Any period during which the administrator has requested the applicant to correct plans, perform required
studies, or provide additional information shall be excluded from the 120-day time period or other applicable
time period set forth in JCC 18.40.320.
(b) The time period for requiring additional information shall be calculated from the date the administrator
notifies the applicant of the need for additional information until the earlier of:
(i) The date the administrator determines whether the information satisfies the request for information; or
(ii) Fourteen calendar days after the date the information has been provided to the administrator.
(7) Effect of Project Permit Application Revisions – Substantial Revisions. If, in the judgment of the administrator,
the content of an application is so substantially revised by an applicant, either voluntarily or to conform to applicable
standards and requirements, that such revised proposal constitutes a substantially different proposal than that
originally submitted, the administrator shall deem the revised proposal to be a new application.
(a) In reaching a decision whether a revision is substantial, the administrator shall consider the relative (to the
application in its initial form) and absolute magnitude of the revision, the environmental sensitivity of the site,
any changes in location of significant elements of the project and their relation to public facilities, surrounding
lands and land uses and the stage of review of the proposal.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 12/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(b) Lesser revisions that would not constitute substantial revisions during early stages of review may be
substantial during later stages due to the reduced time and opportunity remaining for interested parties to
review and comment upon such changes.
(c) Written notice of such determination of substantial revision shall be provided to the applicant and all parties
of record, including the reasons for the administrator’s decision.
(d) A determination that any revision is substantial shall result in the time periods mandated by this chapter
starting from the date at which the revised project application is determined to be complete. The revised project
application shall be subject to all laws, regulations and standards in effect on the date of the determination of
completeness of the substantial revision. [Ord. 8-06 § 1]
18.40.120 Referral and review of development permit applications.
Upon acceptance of a complete application, the administrator shall do the following:
(1) Transmit a copy of the application, or appropriate parts of the application, to each affected agency and county
department for review and comment, including those agencies responsible for determining compliance with state
and federal requirements. The affected agencies and county departments shall have 14 calendar days to comment,
except that state agencies shall have 28 days to comment on special reports per Article VI-D, Environmentally
Sensitive Areas District (ESA), of Chapter 18.15 JCC et al., including habitat management plans and wetland
mitigation plans. Affected agencies and county departments are presumed not to have comments if not submitted
within the 14-calendar-day period, or 28-calendar-day period, as above; provided, that the administrator may grant
an extension of time if needed. Additionally, in the event that the state agency or agencies involved communicate
verbally or in writing intention to waive the opportunity to submit comments, the corresponding state agency
comment period shall terminate and be so noted in the case file.
(2) Applications for developments and planned actions subject to the State Environmental Policy Act (SEPA),
Chapter 43.21C RCW, shall be reviewed in accordance with the policies and procedures contained in Article X of
this chapter. SEPA review shall be conducted concurrently with development project review. The following are
exempt from concurrent review:
(a) Projects categorically exempt from SEPA; and
(b) Components of planned actions previously reviewed and approved in the Jefferson County Comprehensive
Plan or amendments thereto to the extent permitted by law and consistent with the SEPA determination for the
planned action.
(3) If a Type II or III procedure is required, DCD shall provide for notice and/or hearing as set forth in Article III of
this chapter. [Ord. 8-06 § 1]
18.40.130 Scope of project review.
(1) Fundamental land use planning choices made in the Jefferson County Comprehensive Plan, subarea plans, this
Unified Development Code and any other applicable development regulations shall serve as the foundation for
project review. The review of a proposed project’s consistency with this Unified Development Code under JCC
18.40.140, other applicable development regulations, or in the absence of applicable regulations, the adopted
Jefferson County Comprehensive Plan or subarea plan(s), shall incorporate the data collected under this section.
(2) During project review, the administrator or any subsequent reviewing body (e.g., the hearing examiner) shall
determine whether the items listed in this subsection are defined in this Unified Development Code or any other
applicable development regulations applicable to the proposed project or, in the absence of applicable regulations,
the adopted Jefferson County Comprehensive Plan or subarea plan(s). At a minimum, such regulations or plans shall
be determinative of the:
(a) Type of land use permitted at the site, including uses that may be allowed under certain circumstances, such
as planned rural residential developments and conditional uses, if the criteria for their approval have been
satisfied;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 13/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(b) Density of residential development; and
(c) Availability and adequacy of public facilities identified in the Jefferson County Comprehensive Plan, if the
plan provides funding of these facilities.
(3) During project review, the administrator shall not re-examine alternatives to or hear appeals on the items
identified in subsection (2) of this section.
(4) The administrator may determine that the requirements for environmental analysis and mitigation measures in
this Unified Development Code and other applicable regulations provide adequate mitigation for some or all of the
project’s specific probable significant adverse environmental impacts to which the requirements apply. In making
this determination the administrator shall:
(a) Determine if the applicable regulations require measures that are sufficient to adequately address site-
specific, probable significant adverse environmental impacts identified through project application review; and
(b) Determine whether additional studies are required and/or whether the project permit application should be
conditioned with additional mitigation measures.
(5) Nothing in this section shall be construed as limiting the authority of the county to approve, condition, or deny a
project as provided in this Unified Development Code or any other development regulations adopted under the
authority of Chapters 36.70A and/or 43.21C RCW, including project review under Articles VI-D through VI-I of
Chapter 18.15 JCC, and Article X of this chapter. [Ord. 8-06 § 1]
18.40.140 Project consistency.
(1) A proposed project’s consistency with this Unified Development Code or other development regulations adopted
under Chapter 36.70A RCW or, in the absence of applicable development regulations, the appropriate elements of
the Jefferson County Comprehensive Plan or subarea plan adopted under Chapter 36.70A RCW shall be determined
by consideration of:
(a) The type of land use;
(b) The level of development such as units per acre or other measures of density;
(c) Infrastructure, including public facilities and services needed to serve the development; and
(d) The character of the development.
(2) In determining consistency, the determinations made pursuant to JCC 18.40.130 shall be controlling.
(3) For purposes of this section, the term “consistency” shall include all terms used in this chapter and Chapter
36.70A RCW to refer to performance in accordance with this chapter and Chapter 36.70A RCW, including, but not
limited to, compliance, conformity, and consistency.
(4) Nothing in this section requires documentation, dictates procedures for considering consistency, or limits the
administrator from asking more specific or related questions with respect to any of the four main categories listed in
subsections (1)(a) through (1)(d) of this section.
(5) For purposes of assisting in determining consistency with the UDC for a particular project permit, the
administrator shall also utilize review of the site plan submittal required by JCC 18.40.100 (1)(h) to ensure
compliance with the requirements of Chapters 18.20 and 18.30 JCC. [Ord. 8-06 § 1]
Article III. Public Notice Requirements
18.40.150 Public notice – Generally.
(1) Public notice is not required for Type I projects that are categorically exempt from SEPA. If not SEPA exempt,
Type I projects are subject to the notice of application and SEPA notice requirements set forth in JCC 18.40.160
through 18.40.220 and Article X of this chapter.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 14/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) Public notice of the notice of application and of the open record predecision public hearing, if any, is required for
all Type II and Type III actions. Published notice is not required for closed record public meetings before the county
commissioners (i.e., Type IV approvals of long plats and PRRDs), because no new testimony or evidence is allowed
at such meetings or hearings. Mailed notice of closed record public hearings shall be provided to all parties of
record.
(3) Public notice is not required for other Type IV actions because no public hearing is held.
(4) Public notice of Type V legislative actions must be published as described in Chapter 18.45 JCC and as required
by state law.
(5) The applicant shall be responsible for all costs of public notice. [Ord. 8-06 § 1]
18.40.160 Notice of application – When required.
The administrator shall issue a notice of application on projects requiring SEPA review and all Type II and Type III
project permit applications. [Ord. 8-06 § 1]
18.40.170 Notice of application – Time of issuance.
The administrator shall issue the notice of application within 14 calendar days of issuing the determination of
completeness. If an open record predecision public hearing is required for the requested project permit(s), the notice
of application shall be issued at least 15 calendar days prior to the public hearing. [Ord. 8-06 § 1]
18.40.180 Notice of application – SEPA exempt projects.
A notice of application shall not be required for project permits that are categorically exempt under SEPA, unless a
public comment period or an open record predecision hearing is required. A notice of application shall be required
for all Type II projects, regardless of whether such projects are exempt from SEPA. [Ord. 8-06 § 1]
18.40.190 Notice of application – Contents.
The notice of application shall include the following:
(1) The name and address of the applicant or the applicant’s representative;
(2) The date of application, the date of the notice of completion for the application, and the date of the notice of
application;
(3) The street address location of the project or, if unavailable, a description of the subject property reasonably
sufficient to inform the public of its location, which may include a vicinity location (map), the location in reference
to roadway intersections, or a written description (rural route box or subdivision lot and block alone are not
sufficient);
(4) A description of the proposed project action, use or development and a list of project permits included in the
application and, if applicable, a list of any additional studies requested under JCC 18.40.110(6);
(5) The identification of state, federal or other permits required by other agencies with jurisdiction not included in
the application, to the extent known by the county;
(6) The identification of existing environmental documents that evaluate the proposed project, and the location of
where the application and any studies can be reviewed;
(7) The name and phone number of the contact project planner;
(8) A statement of the limits of the public comment period, which shall be 14 calendar days following the date of the
notice of application (or 20 or 30 calendar days if the application involves a permit under the Jefferson County
Shoreline Master Program, as further set forth in JCC 18.40.220);
(9) Statements of the right of any person to comment on the application, receive notice of and participate in any
hearings, request a copy of the decision once made, and any appeal rights;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 15/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(10) A statement of the preliminary determination, if one has been made at the time of the notice of application, of
the proposed project’s consistency with applicable development regulations and of those development regulations
that will be used for project mitigation, as provided in RCW 36.70B.040 and JCC 18.40.140;
(11) Pursuant to WAC 197-11-355, a statement on the first page of the notice of application that:
(a) The optional DNS process of WAC 197-11-355 is being used;
(b) This may be the only opportunity to comment on the environmental impacts of the proposal;
(c) The proposal may include mitigation measures under applicable development regulations, and the project
review process may incorporate or require mitigation measures regardless of whether an EIS is prepared; and
(d) A copy of the subsequent threshold determination may be obtained upon request, and will be mailed to any
person commenting upon the notice of application. In addition, the notice of application shall list the conditions
being considered to mitigate environmental impacts, if a mitigated DNS is expected;
(12) The date, time, place and type of hearing, if applicable, and if scheduled prior to the date of the notice of
application;
(13) A statement of when and where a copy of the application, all supporting documentation and evidence relied
upon by the applicant, and applicable development regulations may be available for public inspection;
(14) A statement that a copy of the staff report will be available for inspection at no cost to the public at least seven
calendar days prior to the public hearing (if applicable); and
(15) Any other information the administrator determines appropriate. [Ord. 8-06 § 1]
18.40.200 Notice of application – SEPA integration.
Except for a determination of significance (DS), the county may not issue its threshold determination until the
expiration of the public comment period on the notice of application. If the county has made a determination of
significance under Chapter 43.21C RCW concurrently with the notice of application, the notice of application may
be combined with the threshold determination and the scoping notice for a draft environmental impact statement
(DEIS). However, nothing in this chapter prevents a DS and scoping notice from being issued prior to the notice of
application. [Ord. 8-06 § 1]
18.40.210 Notice of application – Mailing, publication, and posting requirements.
(1) Published Notice. The administrator shall publish notice in the official county newspaper at least once. Published
notice shall include the project’s road or street address or location, project description, type(s) of permit(s) required,
comment period dates, and location where the complete application and notice of application may be reviewed.
(2) Posting. The applicant shall post a notice of application on the property as follows:
(a) A single notice board shall be placed at the midpoint of the site road frontage or as otherwise directed by the
county for maximum visibility, where it is completely visible to vehicle traffic and pedestrians.
(b) Additional notice boards may be required where the site does not abut a public road, for a large site that
abuts more than one public road, or the administrator determines that additional notice boards are necessary to
provide adequate public notice.
(c) Notice boards shall be constructed and installed in accordance with any specifications promulgated by the
county.
(d) Notice boards shall be maintained in good and legible condition by the applicant during the notice period,
be in place at least 15 calendar days prior to the date of the hearing, and be removed within 15 calendar days
after the end of the notice period.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 16/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(e) The applicant prior to the hearing or final comment date shall submit an affidavit of posting to the
administrator. If the affidavit is not filed as required, any scheduled hearing or date by which the public may
comment on the application will be postponed in order to allow compliance with this notice requirement.
(3) Mailing.
(a) The administrator shall send a notice of application by mail to the applicant, the owners of the subject
property (if different from the applicant), and to all owners of property within 300 feet of any portion of the
exterior boundaries of the subject property. The DCD shall be responsible for preparation of the list of adjacent
property owners; provided, that the administrator retains the authority to require the applicant to supply and
certify the list of adjacent property owners in circumstances where the information is not readily available to
the county. DCD shall obtain addresses for mailed notice shall from the county’s geographic information
system (GIS) or real property tax records. The administrator shall make a notation in the file affirming mailing
of notice to all persons entitled to notice under this chapter.
(b) All public notices shall be deemed to have been provided or received on the date the notice is deposited in
the mail or personally delivered, whichever occurs first. Failure to send notice by mail shall not invalidate such
proceedings where the owner appears at the hearing or receives actual notice. [Ord. 8-06 § 1]
18.40.220 Notice of application – Public comment.
(1) Length of Comment Period. The comment period shall be not less than 14 calendar days, nor more than 30 days
from the date of the notice of application (RCW 36.70b.110(2)(e), except as may otherwise be provided for: a 15-
day comment period for an open record predecision hearing pursuant to RCW 36.70B.110(3), commenting on
preliminary plat applications (i.e., 20 days pursuant to RCW 58.17.095 (2)), for commenting on scoping and draft
and final environmental impact statements pursuant to WAC 197-11-408 and 197-11-500 and Article X of this
chapter, and for commenting on permits under the Jefferson County Shoreline Master Program (SMP) (see
subsection (2) of this section).
(2) Comment Periods for Permits Under the Jefferson County Shoreline Master Program (SMP). The content of
notice under the SMP shall be identical to the notice set forth in JCC 18.40.190 except that:
(a) The public may provide comments on a shoreline development permit application for 30 calendar days after
the notice of application (notice for shoreline permits is longer than the comment period for other Type II and
III permits pursuant to RCW 90.58.140(4)); and
(b) The public comment period shall be 20 calendar days for a shoreline permit for limited utility extensions or
for construction of a bulkhead or other measures to protect a single-family residence and its appurtenant
structures from shoreline erosion (see RCW 90.58.140(11)); and
(c) A notice of application for a shoreline substantial development permit shall notify the public of the 20-day
or 30-day comment period.
(3) Comments may be mailed, E-mailed, personally delivered or sent by facsimile. Comments shall be as specific as
possible.
(4) The administrator will receive public comments during regular business hours any time up to and during the
open record hearing, if any, or if there is no predecision hearing, prior to the decision on the project permit.
(5) The county may not issue a decision or recommendation on the project permit(s) until the expiration of the
public comment period on the notice of application. [Ord. 8-06 § 1]
18.40.230 Notice of public hearing.
Notice of public hearing shall be provided not less than 10 calendar days prior to the hearing. If the notice of
application does not specify a hearing date, a separate notice of public hearing shall be provided. For Type III
projects, the notice of a threshold determination under SEPA may be combined with the notice of public hearing .
Notice under this section shall be accomplished as follows:
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 17/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(1) Published Notice. The administrator shall publish a notice of public hearing in the official county newspaper at
least one time. This notice shall include (and republish if necessary) the appropriate information from JCC
18.40.190.
(2) Mailed Notice. The administrator shall send a notice of public hearing to all of the persons entitled to notice, as
described in JCC 18.40.210(3), including any person who submits written or oral comments on the notice of
application.
(3) Posted Notice. Posted notice of the public hearing is required for all Type III project permit applications, which
shall be posted as set forth in JCC 18.40.210(2). In addition, notice of Type III preliminary plat actions and proposed
subdivisions must be given as set forth in JCC 18.40.240. [Ord. 8-06 § 1]
18.40.240 Additional public notice requirements – Type III preliminary plat actions.
In addition to the notice for Type III actions above, pursuant to Chapter 58.17 RCW, additional notice for
preliminary plats and proposed subdivisions shall be provided as follows:
(1) Notice of the filing of a preliminary plat application of a proposed subdivision located adjacent to or within one
mile of the municipal boundaries of a city or town utilities shall be given to the appropriate city or town officials,
pursuant to RCW 58.17.080 and 58.17.090.
(2) Notice of the filing of a preliminary plat application for a proposed subdivision located adjacent to the right-of-
way of a state highway or within two miles of the boundary of a state or municipal airport shall be given to the
Washington State Secretary of Transportation, who must respond as to the effect of the proposed subdivision on the
state highway or airport within 15 calendar days of such notice.
(3) Special notice of the hearing shall be given to adjacent landowners by any other reasonable method the county
deems necessary. Adjacent landowners are the owners of real property, as shown by the records of the county
assessor, located within 300 feet of any portion of the boundary of the proposed subdivision. If the owner of the real
property which is proposed to be subdivided owns another parcel or parcels of real property which lie adjacent to the
real property proposed to the subdivided, mailed notice shall be given to owners of real property located within 300
feet of any portion of the boundaries of such adjacently located parcel(s). [Ord. 8-06 § 1]
18.40.250 Optional additional public notice.
(1) As optional methods of providing public notice of any project permits, the county may:
(a) Notify the public or private groups with known interest in a certain proposal or in the type of proposal being
considered;
(b) Notify the news media;
(c) Place notices in appropriate regional or neighborhood newspapers or trade journals;
(d) Place public notice in agency newsletters or send notice to agency mailing lists, either general lists or lists
for specific proposals or subject areas;
(e) Mail to neighboring property owners; or
(f) Place notices on the Internet.
(2) The county’s failure to provide the optional notice as described in this section shall not be grounds for
invalidation of any permit decision. [Ord. 8-06 § 1]
Article IV. Project Review and Approval Processes
18.40.260 Administrative approvals without notice (Type I).
The administrator may approve, approve with conditions, or deny (with or without prejudice) all Type I permit
applications which are categorically exempt from SEPA without notice (see Tables 8-1 and 8-2 in JCC 18.40.040,
and JCC 18.40.080(2)). Type I projects that are not categorically exempt under SEPA shall be subject to the notice
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 18/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
of application and comment period provisions of JCC 18.40.150 through 18.40.220, and the SEPA notice
requirements of Article X of this chapter. The administrator’s decision under this section shall be final on the date
issued, and may not be appealed to the hearing examiner. [Ord. 8-06 § 1]
18.40.270 Administrative approval subject to notice (Type II).
(1) The administrator may approve, grant preliminary approval, approve with conditions, or deny (with or without
prejudice) all Type II permit applications, subject to the notice and appeal requirements of this article and Article III
of this chapter. The administrator shall issue written findings and conclusions supporting all Type II decisions.
(2) Type II administrative decisions shall become final subject to the following: an applicant or party of record may
appeal the decision to the hearing examiner for an open record hearing, as further set forth in Article V of this
chapter. [Ord. 8-06 § 1]
18.40.280 Hearing examiner review and decision (Type III decisions and appeals of Type II decisions).
(1) The hearing examiner shall review and make findings, conclusions and a decision on all Type III permit
applications and appeals of Type II decisions.
(2) For Type III actions, the administrator shall prepare a staff report on the proposed development or action
summarizing the comments and recommendations of county departments, affected agencies and special districts, and
evaluating the development’s consistency with this Unified Development Code, adopted plans and regulations. The
staff report shall include proposed findings, conclusions and recommendations for disposition of the development
application. The staff report shall include and consider all written public comments on the application.
(3) Upon receiving a recommendation from the administrator or notice of any other matter requiring the hearing
examiner’s attention (e.g., an appeal of a Type II administrative decision), the hearing examiner shall perform the
following actions as appropriate:
(a) Hold an open record predecision hearing on a Type III permit application and make a decision after
reviewing the recommendation of the administrator; or
(b) Hold an open record appeal hearing and make a decision on the following matters:
(i) Appeals of Type II administrative decisions;
(ii) Appeals of administrative interpretations made under Article VI of this chapter;
(iii) Appeals of SEPA threshold determinations made pursuant to Article X of this chapter (other than
determinations of significance); and
(iv) Other matters not prohibited by law.
(4) The hearing examiner shall conduct a public hearing on all Type III development proposals and appeals of Type
II administrative decisions for the purpose of taking testimony, hearing evidence, considering the facts germane to
the proposal or appeal, and evaluating the proposal or appeal for consistency with this Unified Development Code,
adopted plans and regulations. Notice of the hearing examiner hearing shall be in accordance with JCC 18.40.230.
As applicable, all appeals of administrative interpretations made under Article VI of this chapter, and appeals of
SEPA threshold determinations made under Article X of this chapter (other than determinations of significance
(DS)) shall be considered together with the decision on the project application in a single, consolidated public
hearing.
(5) In addition to the approval criteria listed elsewhere in this Unified Development Code, the hearing examiner
shall not approve a proposed development unless he/she first makes the following findings and conclusions:
(a) The development adequately mitigates impacts identified under Articles VI-D through VI-I of Chapter
18.15 JCC (i.e., environmentally sensitive areas) and Article X of this chapter (i.e., SEPA implementing
provisions);
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 19/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(b) The development is consistent with the Jefferson County Comprehensive Plan and meets the requirements
and intent of this Unified Development Code;
(c) The development is not detrimental to the public health, safety and welfare;
(d) For subdivision applications, findings and conclusions shall be issued in conformance with Chapter 18.35
JCC and RCW 58.17.110.
(6) In the hearing examiner’s decision regarding Type III actions and appeals of Type II administrative decisions,
the hearing examiner shall adopt written findings and conclusions.
(a) The hearing examiner’s decision following closure of an open record predecision public hearing on a Type
III action shall include one of the following actions:
(i) Approve;
(ii) Approve with conditions;
(iii) Deny without prejudice (reapplication or resubmittal is permitted); or
(iv) Deny with prejudice (reapplication or resubmittal is not permitted for one year).
(b) A hearing examiner’s decision following an open record appeal hearing on a Type II administrative
decision, on a SEPA threshold determination on a Type II administrative decision, or on a SEPA threshold
determination on a Type III permit decision shall include one of the following actions:
(i) Grant the appeal in whole or in part;
(ii) Deny the appeal in whole or in part; or
(iii) If appropriate, in a proceeding involving a SEPA appeal of a threshold determination consolidated
with the hearing on a Type III permit application, continue the open record public hearing pending SEPA
compliance.
(c) The hearing examiner decision shall be issued within 10 working days unless a longer period is agreed upon
by the hearing examiner and the applicant. [Ord. 8-06 § 1]
18.40.290 Board of county commissioners action (Type IV decisions).
(1) The board of county commissioners shall make a decision after reviewing Type IV actions during a regularly
scheduled meeting.
(2) In its decision, the board of county commissioners shall make its decision by motion, resolution or ordinance, as
appropriate. [Ord. 8-06 § 1]
18.40.300 Procedures for public hearings.
Public hearings (including open record appeals of Type II decisions and open record predecision hearings on Type
III permit applications) shall be conducted in accordance with the hearing examiner’s rules of procedure and shall
serve to create or supplement an evidentiary record upon which the hearing examiner will base his/her decision. In
cases where scientific standards and criteria affecting project approval are at issue, the hearing examiner shall allow
orderly cross-examination of expert witnesses presenting reports and/or scientific data and opinions. The hearing
examiner may address questions to any party who testifies at a public hearing. The hearing examiner shall open the
public hearing and, in general, observe the following sequence of events:
(1) Staff presentation, including submittal of any administrative reports. The hearing examiner may ask questions of
the staff;
(2) Applicant presentation, including submittal of any materials. The hearing examiner may ask questions of the
applicant;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 20/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(3) Testimony or comments by the public germane to the matter;
(4) Rebuttal, response or clarifying statements by the staff and the applicant;
(5) The evidentiary portion of the public hearing shall be closed and the hearing examiner shall deliberate on the
matter before him/her;
(6) Pursuant to RCW 36.70.970, each final decision of the hearing examiner shall be in writing and shall include
findings and conclusions, based on the record, to support the decision. Such findings and conclusions shall also set
forth the manner in which the decision would carry out and conform to the Jefferson County Comprehensive Plan,
this Unified Development Code and any other applicable county development regulations. Each final decision of the
hearing examiner, unless the applicant and hearing examiner mutually agree to a longer period in writing, shall be
rendered within 10 working days following conclusion of all testimony and hearings. [Ord. 8-06 § 1]
18.40.310 Reconsideration.
A party of record at a public hearing may seek reconsideration only of a final decision by filing a written request for
reconsideration with the hearing examiner within five business days of the date of the final written decision. The
request shall comply with JCC 18.40.330(5)(b). The hearing examiner shall consider the request without public
comment or argument by the party filing the request, and shall issue a decision within 10 working days of the
request. If the request is denied, the previous action shall become final. If the request is granted, the hearing
examiner may immediately revise and reissue his/her decision or may call for argument in accordance with the
procedures for closed record appeals. Reconsideration should be granted only when an obvious legal error has
occurred or a material factual issue has been overlooked that would change the previous decision. [Ord. 8-06 § 1]
18.40.320 Final decision.
(1) Finality. All administrative interpretations made pursuant to Article VI of this chapter and Type II and III project
permit decisions under this code shall be final unless appealed pursuant to Article V of this chapter.
(2) Finding and Conclusions. Each final decision of the hearing examiner and, in the case of certain Type V
decisions, as more fully set forth in Chapter 18.45 JCC, the board of county commissioners shall be in writing and
shall include findings and conclusions based on the record.
(3) Notice of Final Decision.
(a) Except for those permits exempted under JCC 18.40.080, upon issuance of the final decision, the
administrator shall provide a notice of decision that includes a statement of all determinations made under
SEPA and the procedures for administrative appeal, if any, of the permit decision. The notice of decision may
be a copy of the report or decision on the project permit application. It shall also state that affected property
owners may request a change in valuation for property tax purposes notwithstanding any program of
revaluation fully set forth in RCW 36.70B.130.
(b) A copy of the notice of decision shall be mailed, emailed, or hand delivered to the applicant, any person
who, prior to the rendering of the decision, requested notice of the decision, and to all persons who submitted
substantive written comments on the application. The notice of decision shall be posted and published as set
forth in JCC 18.40.210(1) and (2), and shall be provided to the Jefferson County assessor.
(4) Timing of Notice of Final Decision. The final decision on a development proposal shall be made within 120
calendar days from the date of the determination of completeness unless:
(a) Certain days are excluded from the time calculation pursuant to subsection (5) of this section;
(b) The application involves a shoreline permit application for limited utility extensions (RCW
90.58.140(13)(b)) or construction of a bulkhead or other measures to protect a single-family residence and its
appurtenant structures from shoreline erosion. In those cases, the decision to grant or deny the permit shall be
issued within 21 calendar days of the last day of the comment period specified in JCC 18.40.220(2);
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 21/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(c) The application involves a preliminary long plat application under Article IV of Chapter 18.35 JCC. In such
cases, the application shall be approved, disapproved, or returned to the applicant for modification or correction
within 90 days from the date of the determination of completeness; or
(d) The application involves a final short plat application under Article III of Chapter 18.35 JCC, or a final long
plat application under Article IV of Chapter 18.35 JCC. In such cases, the application shall be approved,
disapproved or returned to the applicant within 30 days from the date of the determination of completeness.
(5) Calculation of Time Periods for Issuance of Notice of Final Decision. In determining the number of calendar
days that have elapsed since the determination of completeness, the following periods shall be excluded:
(a) Any period during which the applicant has been requested by the county to correct plans, perform studies,
or provide additional information. The period shall be calculated as set forth in JCC 18.40.110(6)(b).
(b) If substantial project revisions are made or requested by an applicant, the 120 calendar days will be
calculated from the time the county determines the revised application is complete and issues a new
determination of completeness.
(c) All time required for the preparation of an environmental impact statement (EIS) following a determination
of significance (DS) pursuant to Chapter 43.21C RCW.
(d) Any period for open record appeals of project permits under JCC 18.40.330; provided, however, that the
time period for the hearing and decision shall not exceed a total of 90 calendar days.
(e) Any extension of time mutually agreed upon by the county and the applicant.
(f) Any time required for the preparation of an administrator’s code interpretation pursuant to Article VI of this
chapter.
(6) The time limits established in this chapter do not apply if a project permit application:
(a) Requires an amendment of the Jefferson County Comprehensive Plan or this Unified Development Code; or
(b) Requires approval of the siting of an essential public facility as provided in RCW 36.70A.200.
(7) Notice to Applicant. If the county is unable to issue its final decision on a project permit application within the
time limits provided for in this chapter, it shall provide written notice of this fact to the project applicant. The notice
shall include a statement of reasons why the time limits have not been met and an estimated date for issuance of the
notice of decision.
(8) Effective Date. The final decision of the administrator, hearing examiner, or board of county commissioners
shall be effective on the date stated in the decision, motion, resolution or ordinance; provided, however, that the
appeal periods shall be calculated from the date of the decision, as further provided in JCC 18.40.330 and 18.40.340.
[Ord. 8-06 § 1]
Article V. Appeals
18.40.330 Administrative appeals.
In the absence of a specific right of appeal authorized under this UDC, there shall be no right to administrative
appeals.
(1) Type I Permits. Decisions of the Administrator on Type I permits and decisions regarding the appropriate permit
process to be used for discretionary conditional use permit applications (i.e., “C(d)” uses listed in Table 3-1 in JCC
18.15.040) under JCC 18.40.520, are not appealable to the hearing examiner. However, administrative code
interpretations may be appealed as set forth in Article VI of this chapter.
(2) Type II Permits.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 22/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(a) The administrator’s final decision on a Type II permit application may be appealed by a party of record to
the hearing examiner for an open record appeal hearing as further set forth in JCC 18.40.280. The responsible
official’s SEPA determination of nonsignificance (DNS) or mitigated determination of nonsignificance
(MDNS) may also be appealed by a party of record to the hearing examiner for an open record appeal hearing.
Administrative appeals of a DS or draft or final EIS are not allowed.
(b) All appeals of Type II permit decisions must be in writing, conform with the procedures for appeal set forth
in subsection (5) of this section, and be filed within 14 calendar days after the notice of decision is issued.
Appeals of environmental determinations under SEPA, except for a determination of significance (DS), shall be
consolidated with any open record hearing on the project permit. (See RCW 36.70B.110(6)(d)).
(3) Type III Permits.
(a) The responsible official’s DNS or MDNS may be appealed to the hearing examiner by the applicant or
anyone commenting on the environmental impacts of the proposal (as further set forth in JCC 18.40.780). The
appeal must be in writing, in conformance with subsection (5) of this section, and be filed within 14 calendar
days after the threshold determination is issued as set forth in subsection (4) of this section. Appeals of
environmental determinations under SEPA shall be consolidated with any open record hearing on the project
permit. (See RCW 36.70B.110(6)(d)). Administrative appeals of a DS or draft or final EIS are not allowed.
(4) Calculation of Appeal Periods. The appeal periods shall be calculated as of the date the notice of decision is
published or, for appeals involving a SEPA determination, from the date the decision is issued pursuant to WAC
197-11-340(2)(d).
(5) Procedure for Appeals.
(a) A notice of appeal shall be delivered to the administrator by mail or by personal delivery, and must be
received by 4:00 p.m. on the last business day of the appeal period, with the required appeal fee pursuant to the
Jefferson County fee ordinance.
(b) The notice of appeal shall contain a concise statement identifying:
(i) The decision being appealed and the identification of the application which is the subject of the appeal;
(ii) The name, address, and phone number of the appellant and his/her interest in the matter;
(iii) Appellant’s statement describing standing to appeal (i.e., how he or she is affected by or interested in
the decision);
(iv) The specific reasons why the appellant believes the decision to be wrong. The appellant shall bear the
burden of proving the decision was wrong;
(v) The desired outcome or changes to the decision; and
(vi) A statement that the appellant has read the appeal and believes the contents to be true, signed by the
appellant.
(c) Any notice of appeal not in full compliance with this section shall not be considered. [Ord. 8-06 § 1]
18.40.340 Judicial appeals.
(1) Time to File Judicial Appeal. The applicant or any aggrieved party may appeal from the final decision of the
administrator, hearing examiner, or to a court of competent jurisdiction in a manner consistent with state law. All
appellants must timely exhaust all administrative remedies prior to filing a judicial appeal.
(2) Service of Appeal. Notice of appeal and any other pleadings required to be filed with the court shall be served by
delivery to the county auditor (see RCW 4.28.080), and all persons identified in RCW 36.70C.040, within the
applicable time period. This requirement is jurisdictional.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 23/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(3) Cost of Appeal. The appellant shall be responsible for the cost of transcribing and preparing all records ordered
certified by the court or desired by the appellant for the appeal. Prior to the preparation of any records, the appellant
shall post an advance fee deposit in an amount specified by the county auditor with the county auditor. Any overage
will be promptly returned to the appellant. [Ord. 8-06 § 1]
Article VI. Unified Development Code Interpretation
18.40.350 Purpose.
An interpretation of the provisions of this Unified Development Code is intended to clarify conflicting or ambiguous
wording, interpret proper classification of a use, or interpret the scope or intent of the provisions of this code;
provided, however, that interpretations of the provisions adopted under the Jefferson County building code, Chapter
15.05 JCC, or its successor ordinance, may not be requested under this article. An interpretation of the provisions of
this code may not be used to amend the code. Further, code interpretations are not considered a project permit action
subject to “typing” and the public notice requirements contained in Articles I through V of this chapter. [Ord. 8-06 §
1]
18.40.360 Submission requirements.
(1) Who May Request Interpretation. Any person may request a written interpretation of the provisions of this code.
Additionally, the administrator may issue an interpretation on the administrator’s own initiative.
(2) The administrator may require that any request that seeks interpretation of more than four UDC sections be
broken down into smaller requests, each requiring the standard fee. The administrator may limit the code
interpretation to what is deemed necessary to clarify the section and may decline responding to requests that are
deemed excessive or onerous or those that ask hypothetical questions.
(3) Submittal Requirements. Any person requesting an interpretation of this code shall submit a written request
specifying each provision of the code for which an interpretation is requested, why an interpretation of each
provision is necessary, and any reasons or materials in support of a proposed interpretation. The applicant shall pay
the fee set forth in the Jefferson County fee ordinance or an administrator’s interpretation.
(4) Factors for Consideration. In making an interpretation of the provisions of this code, the administrator should
consider the following, as applicable:
(a) The applicable provisions of this code, including its purpose and context;
(b) The implications of the interpretation for development within the county as a whole, including the precedent
the interpretation will set for other applicants; and
(c) Consistency with the Jefferson County Comprehensive Plan and other relevant ordinances and policies.
(5) Conflicts with Other Regulations. Where conflicts occur between the provisions of this code and the Jefferson
County building code, Chapter 15.05 JCC, or its successor ordinance, or other regulations of the county, the more
restrictive shall apply. If any conflict between the land use districts map and the text of this code ensue, the text of
this code shall prevail. [Ord. 8-06 § 1]
18.40.370 Administrator’s decision.
(1) The DCD administrator’s decision on a request for an interpretation shall include the name of the applicant, the
description of the subject proposal, the language of the provisions of this code subject to interpretation, the
explanation of the DCD administrator’s interpretation, and any other necessary information reasonably related to the
proposal.
(2) Response to Written Request. The DCD administrator shall mail a written response to any person filing a written
request to interpret the provisions of this code within 28 calendar days of having received the request; provided,
however, that when a request is made by a permit applicant while a project is pending and after a determination of
completeness has been issued, the permit applicant must agree to waive the time frame required under Article IV of
this chapter to allow for preparation of the interpretation, and any changes to the project that the interpretation might
require. [Ord. 8-06 § 1]
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 24/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
18.40.380 Time limitation and enforcement.
(1) Time Limitation. An interpretation of this code remains in effect unless and until rescinded in writing by the
administrator, or superseded by a formal amendment under JCC 18.45.090.
(2) Enforcement. An interpretation of this code issued in accordance with this article may be enforced in the same
manner that any provision of this code is enforced (see Chapter 18.50 JCC). All written interpretations of this code,
with a current index of such interpretations shall be maintained by DCD and made available for public inspection.
[Ord. 8-06 § 1]
18.40.390 Appeals of administrator’s interpretations.
When an interpretation is made in response to a written request pursuant to the provisions of this article, the person
filing the written request may appeal the decision of the administrator to the hearing examiner within 14 calendar
days of the decision using the process for appeals of Type II permit decisions as set forth in JCC 18.40.330. The fee
for such appeal shall be as set forth in the Jefferson County fee ordinance and must be paid by the appellant at the
time of filing the appeal. [Ord. 8-06 § 1]
18.40.400 Judicial appeal.
Appeals from the final decision of the hearing examiner shall be made to the Jefferson County superior court within
21 calendar days of the date the decision or action becomes final, as set forth in JCC 18.40.340. All appeals must
conform to the provisions of JCC 18.40.340, and are subject to the requirements set forth in that section. [Ord. 8-06
§ 1]
Article VII. Site Plan Approval Advance Determinations Repealed
18.40.410 Purpose.
The purpose of this article is to allow prospective buyers, owners or developers of land a means to obtain advance
determinations of the site requirements and constraints to particular parcels without undertaking the risk or expense
of applying for a “triggering” building or other development permit not requiring Type II, III, or IV land use
approval.. It is intended to reduce the cost of development and aid in the facilitation of predevelopment financing for
applicants. [Ord. 8-06 § 1]
18.40.420 Scope.
All “Yes” uses identified in Table 3-1 in JCC 18.15.040, or classified as such by the administrator pursuant to
Article II of Chapter 18.15 JCC, that require issuance of a building or septic permit are eligible to obtain site plan
approval advance determination. Advanced site plan approval may be granted without an accompanying building or
development permit only upon completion of an administrative review process to ensure consistency with the
performance standards of Chapter 18.20 JCC, the development standards of Chapter 18.30 JCC and other applicable
requirements of the UDC. The decision of the administrator regarding site plan review may be appealed only as part
of an appeal of an underlying building or other construction or development permit decision. [Ord. 8-06 § 1]
18.40.430 Application requirements.
Each application for site plan approval advance determination shall include the information required by JCC
18.40.100(1) and must identify the specific proposed use of the property for which the application is being
submitted. Any commercial, industrial, small-scale recreational and tourist use, or multifamily residential use listed
as a “Yes” use in Table 3-1 in JCC 18.15.040, or classified as such by the administrator, that seeks site plan approval
advance determination under this article shall also be subject to the additional application submittal requirements of
JCC 18.40.100(2) and the preapplication conference requirements of JCC 18.40.090. The administrator may require
additional information subject to the specific submittal requirements of JCC 18.40.100(3) and (4), where determined
by the administrator to be necessary for review of a site plan approval advance determination application. For the
purposes of meeting the requirements of this article, the application requirements of JCC 18.40.100(1)(g) shall be
interpreted to require the submittal of soil logs and other applicable information pursuant to WAC 246-272-11001
and the Jefferson County Code necessary to determine compliance with the Jefferson County health department
regulations regarding on-site septic disposal.
The administrator may waive specific submittal requirements determined to be unnecessary for review of a site plan
approval advance determination application. [Ord. 8-06 § 1]
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 25/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
18.40.440 Application review.
Review of applications for site plan review shall be as follows:
(1) Review Procedures. When the administrator determines that an application is technically complete, as defined in
JCC 18.40.110, the application shall be processed as a Type I permit under procedures specified in Article IV of this
chapter.
(2) Referral and Review of Application. The administrator shall transmit a copy of the application, or appropriate
parts of the application, to affected agencies and county departments for review and comment. [Ord. 8-06 § 1]
18.40.450 Approval criteria.
Site plans shall be approved upon showing that all of the following have been satisfied:
(1) The proposed site plan conforms to all applicable county, state and federal, land use, environmental and health
regulations and plans, including but not limited to the following:
(a) The Jefferson County Comprehensive Plan; and
(b) The provisions of this code, including any incorporated standards;
(2) Adequate provisions for utilities and other public services necessary to serve the needs of the proposed site plan
have been demonstrated, including open spaces, drainage ways, roads, and other public ways, potable water, sewage
disposal, fire flow and other improvements;
(3) The probable significant adverse environmental impacts of the proposed site plan, together with any practical
means of mitigating adverse impacts, have been considered such that the proposal will not have an unacceptable
adverse effect upon the quality of the environment, in accordance with the State Environmental Policy Act (SEPA)
implementing provisions contained within this chapter and Chapter 43.21C RCW;
(4) Approving the proposed site plan will serve the public use and interest and adequate provision has been made for
the public health, safety and general welfare. [Ord. 8-06 § 1]
18.40.460 Duration of approval.
Approval of the site plan shall be effective for five years from the date of original approval by the administrator. If a
building permit has not been issued within the five-year period, the site plan approval shall expire. An expired site
plan approval advance determination cannot be revived or extended except by new application that must meet all
then-existing criteria and conditions listed in this article. Knowledge of the expiration date and shall be the
responsibility of the applicant. The county will not provide notification prior to expiration. [Ord. 8-06 § 1]
18.40.470 Limitations on approval.
Approval of the site plan shall not guarantee the performance of specific site features or improvements (e.g., wells,
septic systems, stormwater drainage facilities, etc.) and any proposal granted a site plan approval advance
determination shall not be immune from changes in state or federal laws which are enacted or have an effective date
after the date of the site plan approval advance determination and which may affect the performance and
implementation of the site plan and associated use or activity. Any subsequent land division or boundary line
adjustment of a parcel or lot which has received site plan approval advance determination under this article shall
void such site plan approval and require a new site plan approval advance determination application. Approval of a
site plan under this section does not constitute authority to commence any development or building activity until
such time as final authorizing permits are issued (e.g., septic, wells, stormwater management, or building permits,
etc.). [Ord. 8-06 § 1]
18.40.480 Modifications to an approved site plan.
(1) Minor modifications to a previously approved site plan under this article may be requested by the applicant and
approved by the administrator subject to the provisions for Type I decisions; provided, that the modification does
not involve any of the following:
(a) A change of proposed land use to one other than that approved for the original site plan;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 26/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(b) The location or relocation of a road or street (excluding driveways, internal parking or access ways);
(c) An adjustment that crosses land use district boundaries where the administrator reasonably believes that the
adjustment is intended to serve as a rationale for a future site-specific land use district redesignation
application;
(d) The creation of an additional lot, tract or parcel;
(e) Would create a site plan for a parcel that does not qualify as a building site pursuant to this code;
(f) Would make the site plan inconsistent with any restrictions or conditions of approval for a recorded short
plantplat, long plat, boundary line adjustment, plat amendment or binding site plan.
(2) Before approving such an amendment, the administrator shall make written findings and conclusions
documenting the following conditions:
(a) The modification will not be inconsistent or cause the site plan to be inconsistent with the decision of the
county preliminarily approving the application;
(b) The modification will not violate the intent of the original conditions of application approval; and
(c) The modification will not cause the site plan approval advance determination to violate any applicable
county policy or regulation.
(3) Modifications that involve the circumstances described in subsection (1) of this section, or exceed the criteria set
forth in subsection (2) of this section, shall be processed as a new site plan approval advance determination
application. [Ord. 8-06 § 1]
Article VIII. Conditional Uses
18.40.490 Purpose.
The purpose of the conditional use permit process is to provide flexibility in the application of the use regulations
contained in this code in order to accommodate uses that may be appropriate in an established district under certain
circumstances, but inappropriate in the same district under others. At the time of application, a review of the
location, design, configuration, and potential impact of the proposed use shall be conducted by comparing the use to
the goals and policies established in the Jefferson County Comprehensive Plan and to adopted development
standards. This review shall determine whether the proposed use should be permitted by weighing the public need or
the benefit to be derived from the use against the impact that it may cause. [Ord. 8-06 § 1]
18.40.500 Scope.
This article shall apply to each application for a conditional use permit. Only those uses indicated by a “C(a),”
“C(d)” or “C” opposite the use in Table 3-1 in JCC 18.15.040 will be considered for a conditional use permit. [Ord.
8-06 § 1]
18.40.510 Application submittal and contents.
(1) The application for a conditional use permit shall be submitted to DCD on forms provided by the department,
along with the appropriate fees established under the Jefferson County fee ordinance. The application shall include
all materials required pursuant to JCC 18.40.100.
(2) The administrator may waive specific submittal requirements determined to be unnecessary for review of an
application. [Ord. 8-06 § 1]
18.40.520 Conditional use permit types – Review processes.
(1) Applications for uses listed as an administrative conditional use permit (i.e., “C(a)”) in Table 3-1 in JCC
18.15.040 shall be processed according to the procedures for Type II land use decisions established in Article IV of
this chapter.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 27/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) Applications for uses listed as discretionary conditional use permits (i.e., “C(d)”) in Table 3-1 in JCC 18.15.040
shall, at a minimum, be processed according to the procedures for Type II land use decisions established in Article
IV of this chapter. However, in accordance with this subsection, the administrator may on a case-by-case basis refer
a discretionary conditional use permit application to the hearing examiner to be processed according to the
procedures for Type III land use decisions established in Article IV of this chapter.
(a) Required Findings. Prior to referring an application for a use listed as “C(d)” in Table 3-1 in JCC 18.15.040
to the hearing examiner, the administrator shall make one or both of the following findings:
(i) In the exclusive, discretionary judgment of the administrator, the application involves potentially
significant issues relating to location, design, configuration, and potential impacts to surrounding
properties and the community that can be more appropriately considered and addressed through an open
public record pre-decision hearing before the Jefferson County hearing examiner; or
(ii) In the exclusive, discretionary judgment of the administrator, the application seeks approval of a use
involving complex legal issues necessitating special expertise in the decision-maker.
(b) Timing. The administrator shall may determine whether or not to refer an application to the hearing
examiner, for a public hearing, concurrent with the determination of completeness required under JCC
18.40.110(1), or after the public comment period has expired.
(c) Discretion of the Administrator. The administrator’s decision to refer an application to the hearing examiner
under this subsection to be processed as a Type III application shall be for the purpose of affording maximum
fairness in decision-making and procedural due process protection, and shall not affect the substantive
applicability of local, state or federal policies or law applicable to any permit application. The decision to refer
any application to the hearing examiner to be processed as a Type III application rests exclusively within the
discretion of the administrator.
(d) No Notice or Hearing Required. Because the administrator’s decision to refer (or not to refer) an application
for a use listed as “C(d)” in Table 3-1 in JCC 18.15.040 to the hearing examiner for a public hearing rests
solely in the administrator’s discretion, the county is not required to provide prior notice of the administrator’s
decision. The administrator shall not be required to hold a public hearing on such a decision. The decision of
the administrator made pursuant to this subsection (2) shall not constitute an appealable administrative
decision.
(3) Applications for uses listed as a “C” in Table 3-1 in JCC 18.15.040 shall be processed according to the
procedures for Type III land use decision established in Article IV of this chapter. [Ord. 8-06 § 1]
18.40.530 Approval criteria for all conditional uses.
(1) The county may approve or approve with modifications an application for a conditional use permit (i.e., uses
listed in Table 3-1 in JCC 18.15.040 as “C(a),” “C(d)” or “C”) if all of the following criteria are satisfied:
(a) The conditional use is harmonious and appropriate in design, character and appearance with the existing or
intended character and quality of development in the vicinity of the subject property and with the physical
characteristics of the subject property;
(b) The conditional use will be served by adequate infrastructure including roads, fire protection, water,
wastewater disposal, and stormwater control;
(c) The conditional use will not be materially detrimental to uses or property in the vicinity of the subject
parcel;
(d) The conditional use will not introduce noise, smoke, dust, fumes, vibrations, odors, or other conditions or
which unreasonably impact existing uses in the vicinity of the subject parcel;
(e) The location, size, and height of buildings, structures, walls and fences, and screening vegetation for the
conditional use will not unreasonably interfere with allowable development or use of neighboring properties;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 28/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(f) The pedestrian and vehicular traffic associated with the conditional use will not be hazardous to existing and
anticipated traffic in the vicinity of the subject parcel;
(g) The conditional use complies with all other applicable criteria and standards of this code Title and any other
applicable provisions of Jefferson County Code local code, or state or federal law; and more specifically,
conforms to the standards contained in Chapters 18.20 and 18.30 JCC;
(h) The proposed conditional use will not result in the siting of an incompatible use adjacent to an airport or
airfield;
(i) The conditional use will not cause significant adverse impacts on the human or natural environments that
cannot be mitigated through conditions of approval;
(j) The conditional use has merit and value for the community as a whole;
(k) The conditional use is consistent with all relevant goals and policies of the Jefferson County
Comprehensive Plan; and
(l) The public interest suffers no substantial detrimental effect. Consideration shall be given to the cumulative
effect of similar actions in the area.
(2) In instances where all of the above findings cannot be made, the application shall be denied.
(3) The administrator may consider applications for modifications of lawfully established conditional uses and
developments approved under this code and conditional uses in existence on December 18, 2000, when the
application proposes to bring the existing use substantially closer to compliance with the standards of this code. The
administrator may approve, conditionally approve, or deny the modification application. A site plan conforming to
the provisions of this chapter and Article II, Project Permit Applications (Type I – IV), of this chapter shall
accompany the application showing the location, size and type of modification proposed by the applicant.
(4) Modifications may be approved by the administrator under Type I review procedures; provided, that the
cumulative modifications of the approved use will not exceed the following limitations:
(a) The modification will not increase residential use by more than one unit, if allowed by the land use district;
(b) The modification will not increase the required amount of parking by more than 20 percent or 20 spaces
(whichever is less);
(c) The proposed modification will not expand the total square footage of all structures and/or outdoor use
areas, excluding parking, by more than 20 percent. In addition, the proposed expansion of the structure shall not
result in total size of the structure exceeding the maximum building size limits in Chapter 18.30 JCC;
(d) The modification will not change or modify any special condition imposed under any previous official
review;
(e) The modification will not significantly reduce the amount or location of required site screening;
(f) The modification will not expand an existing nonconforming use or structure, or render a conforming use or
structure nonconforming;
(g) The modification will not establish a new use;
(h) The modification will not expand a mining/site operation, mineral processing or mineral batching activity;
(i) In the determination of the administrator, the modification will not create or materially increase any adverse
impacts or undesirable effects of the project, or cause the use or structure to become inconsistent with the
Comprehensive Plan or the purpose of the land use class and district.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 29/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(5) All proposed uses, structures and site improvements (and modifications thereof) shall comply with the
development standards of this code.
(6) Any proposed modification that does not meet all the requirements of this subsection shall not be approved
through this process, but shall be reviewed through the current review procedures as outlined by this chapter.
(7) Decisions to administratively approve modifications shall be administered through a consistency review of
development permits in accordance with this code and any previous conditions of approval. [Ord. 8-06 § 1]
18.40.540 Additional conditions.
The county may impose additional conditions on a particular use if it is deemed necessary for the protection of the
surrounding properties, the neighborhood, or the general welfare of the public. The conditions may:
(1) Increase requirements in the standards, criteria or policies established by this code;
(2) Stipulate an exact location for the conditional use on the subject property as a means of minimizing hazards to
life, limb, property damage, erosion, landslides or traffic;
(3) Require structural features or equipment as a means of minimizing hazards to life, limb, property damage,
erosion, landslides or traffic; or
(4) Contain restrictions or provisions deemed necessary to establish parity with uses permitted in the same zone with
respect to avoiding nuisance generating features in matters of noise, odors, air pollution, wastes, vibration, traffic
and physical hazards. [Ord. 8-06 § 1]
18.40.550 Use of property before final decision.
No building permit shall be issued for any use involved in an application for approval for a conditional use permit
until the conditional use permit is approved and becomes effective. [Ord. 8-06 § 1]
18.40.560 Effective period – Expiration.
(1) A conditional use permit automatically expires and becomes void if the applicant fails to file for a building
permit or other necessary development permit within three years of the effective date (the date of the decision
granting the permit) of the permit unless the permit approval provides for a greater period of time.
(2) Extensions to the duration of the original permit approval are prohibited.
(3) The department of community development shall not be responsible for notifying the applicant of an impending
expiration. [Ord. 8-06 § 1]
18.40.570 Modification of a conditional use permit.
The county may modify an approved conditional use permit as follows: the county may delete, modify or impose
additional conditions upon finding that the use for which the approval was granted has been intensified, changed or
modified by the property owner or by person(s) who control the property without approval so as to significantly
impact surrounding land uses. A modification will be processed as a Type II land use decision pursuant to JCC
18.40.270. [Ord. 8-06 § 1]
18.40.580 Conditional use permit to run with the land.
A conditional use permit granted under this article shall continue to be valid upon a change of ownership of the site,
business, service, use or structure that was the subject of the permit application. No other use is allowed without
approval of an additional conditional use permit. [Ord. 8-06 § 1]
18.40.590 Permit suspension or revocation.
The county may suspend or revoke an approved conditional use permit pursuant to Chapter 18.50 JCC upon finding
that:
(1) The use for which the approval was granted has been abandoned for a period of at least one year;
(2) Approval of the permit was obtained by misrepresentation of material fact; or
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 30/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(3) The permit is being exercised contrary to the terms of approval. [Ord. 8-06 § 1]
18.40.600 Assurance device.
In appropriate circumstances, the administrator may require a reasonable performance or maintenance assurance
device, in a form acceptable to the county prosecutor, to assure compliance with the provisions of this code and the
conditional use permit as approved. [Ord. 8-06 § 1]
Article IX. Variances (Minor and Major)
18.40.610 Purpose.
The purpose of this article is to ensure that all persons and their property are guaranteed equal rights and
opportunities under similar circumstances. A variance is never to be used to endow certain persons or property with
special privileges denied to all others under similar circumstances. Variances may only be granted for dimensional,
area and bulk requirements (e.g., height, setbacks, yard size, lot coverage, frontage, floor area and the like) specified
by this code. [Ord. 8-06 § 1]
18.40.620 Scope.
This article shall apply to all applications for variances from the provisions of this code, except for reasonable
economic use variances and environmentally sensitive area buffer width reductions, which shall be governed by the
provisions of Article VI-D of Chapter 18.15 JCC. [Ord. 8-06 § 1]
18.40.630 Application submittal and contents.
(1) The application for a variance shall be submitted to DCD on forms provided by the department, along with the
appropriate fees established under the Jefferson County fee ordinance. The application shall include all materials
required pursuant to JCC 18.40.100.
(2) The administrator may waive specific submittal requirements determined to be unnecessary for review of an
application. [Ord. 8-06 § 1]
18.40.640 Variance types – Review processes.
The following are subject to this permit review process:
(1) Minor and Major Variances Distinguished.
(a) Minor variances include variances that would permit expansion of an existing building which would extend
no more than 10 percent beyond the dimensional, area and bulk requirements specified by this code. Minor
variances also include variances to allow expansion of an existing building that is nonconforming as to setback
or lot coverage requirements when the proposed expansion would not:
(i) Increase the nonconformity of the building; and
(ii) Result in any portion of the building or expansion being located closer to an abutting property line than
does the existing building at its nearest point to the property line.
(b) Major variances include all other variances (i.e., all variances not described in subsection (1)(a) of this
section).
(2) Minor Variances. Applications for minor variances shall be processed according to the procedures for Type II
land use decisions established in JCC 18.40.270.
(3) Major Variances. Applications for major variances shall be processed according to the procedures for Type III
land use decisions established in Article IV of this chapter. [Ord. 8-06 § 1]
18.40.650 Approval criteria.
A variance may be granted only if the applicant demonstrates all of the following:
(1) The variance will not constitute a grant of special privilege inconsistent with the limitation upon uses of other
properties in the vicinity and land use district in which the subject property is located;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 31/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) The variance is necessary because of special circumstances relating to the size, shape, topography, location or
surroundings of the subject property, to provide it with use rights and privileges permitted to other properties in the
vicinity and in the land use district in which the subject property is located;
(3) The granting of the variance will not be materially detrimental to the public welfare or injurious to the property
or improvements in the vicinity and land use district in which the subject property is located;
(4) The special circumstances of the subject property make the strict enforcement of the provisions of this code an
unnecessary hardship to the property owner;
(5) The special circumstances are not the result of the actions of the applicant; and
(6) The variance is consistent with the purposes and intent of this Unified Development Code. [Ord. 8-06 § 1]
18.40.660 Additional conditions.
In granting any variance, the decision-maker may prescribe appropriate conditions and safeguards to assure that the
purpose and intent of this code will not be violated. [Ord. 8-06 § 1]
18.40.670 Limitation on authority.
The administrator or hearing examiner (as applicable) may not grant a variance under this article for the following:
(1) The provisions of this code establishing allowed, conditional, discretionary and prohibited uses within the
various land use districts (i.e., Table 3-1 in JCC 18.15.040);
(2) The density provisions of this code;
(3) The procedural or administrative provisions of this code; or
(4) Any provision of this code which, by its terms, is not subject to a variance. [Ord. 8-06 § 1]
18.40.680 Effective period – Expiration.
(1) A variance approval automatically expires and becomes void if the applicant fails to file for a building permit or
other necessary development permit within three years of the date of the decision granting the variance unless the
variance approval provides for a greater period of time.
(2) Extensions to the duration of the original variance approval are prohibited.
(3) The department of community development shall not be responsible for notifying the applicant of an impending
expiration. [Ord. 8-06 § 1]
18.40.690 Assurance device.
In appropriate circumstances, the administrator or hearing examiner (as applicable) may require a reasonable
performance or maintenance assurance device, in a form acceptable to the prosecuting attorney, to assure
compliance with the provisions of this title and the variance as approved. [Ord. 8-06 § 1]
Article X. State Environmental Policy Act (SEPA) Implementation
18.40.700 Authority.
(1) This section contains county procedures and policies implementing the State Environmental Policy Act (SEPA)
(Chapter 43.21C RCW). Jefferson County adopts this article under RCW 43.21C.120, as amended, and WAC 197-
11-904.
(2) SEPA Rules – Adoption by Reference. The county hereby adopts by reference the SEPA rules, Chapter 197-11
WAC. The SEPA rules must be used in conjunction with this article. This article contains uniform usage and
definitions of terms under SEPA and the SEPA rules. The county adopts by reference the definitions in WAC 197-
11-700 et seq., as supplemented by Chapter 18.10 JCC. [Ord. 8-06 § 1]
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 32/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
18.40.710 Purpose.
The purpose of this article is to adopt regulations that implement SEPA, consistent with the SEPA rules. This is
accomplished by ensuring that:
(1) Environmental values are considered in making land use and agency decisions, and reasonable alternatives and
conditions are identified and implemented to mitigate (as provided in this article) the adverse environmental impacts
of proposed actions on the environment;
(2) Adequate and timely environmental information is gathered and provided to decision-makers, and procedural
delay and duplication is avoided; and
(3) Opportunity for public involvement is included in the decision-making process. [Ord. 8-06 § 1]
18.40.720 Responsible official – Decision-making authority.
(1) The responsible official shall be the administrator.
(2) For those proposals for which the county is the lead agency, the responsible official is vested with authority to
and shall make the threshold determination, determine an exemption (if any), supervise scoping and preparation of
any required environmental impact statement (EIS), administer the SEPA rules and this article, and perform any
other functions assigned to the “lead agency” or “responsible official” by the SEPA rules.
(3) The responsible official shall be responsible for the written comments of the county in response to a consultation
request:
(a) Prior to issuance of a threshold determination;
(b) For participation in scoping; or
(c) For review of a draft environmental impact statement (DEIS).
(4) The department of community development (DCD) shall maintain all documents required by SEPA rules and
make them available in accordance with Chapter 42.17 RCW (the Disclosure – Campaign Finances – Lobbying
Records Act). [Ord. 8-06 § 1]
18.40.730 Lead agency determination and responsibilities.
(1) The county department receiving application for or initiating a proposal that includes a non-exempt action shall
determine the lead agency for the proposal under WAC 197-11-050 and WAC 197-11-922 through 197-11-940,
unless lead agency has been previously established.
(2) When the county is lead agency, the responsible official shall supervise compliance with threshold determination
requirements. If an EIS is required, that official shall supervise preparation of the EIS.
(3) When the county is not lead agency, the county shall use and consider the determination of nonsignificance
(DNS), mitigated determination of nonsignificance (MDNS), or final environmental impact statement (FEIS) of the
lead agency in making decisions on the proposal. Unless required under WAC 197-11-600 no DNS or EIS in
addition to that issued by the lead agency shall be prepared. The county may, however, conduct supplemental
environmental review under WAC 197-11-600.
(4) If the county receives a lead agency determination that appears inconsistent with criteria contained in WAC 197-
11-922 through 197-11-940, it may object to the determination. Objection must be made to the agency that made the
determination and must be resolved within 15 calendar days of receipt of the determination, or the county must
petition the Department of Ecology for lead agency determination under WAC 197-11-946 within the 15-calendar-
day period. The responsible official may initiate any such petition on behalf of the county.
(5) Any county department making lead agency determination for a private proposal shall require sufficient
information to identify all other agencies with jurisdiction over the proposal. [Ord. 8-06 § 1]
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 33/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
18.40.740 Initiation of SEPA review – Limitations on actions during review.
(1) Initiation of Review. The county’s SEPA process begins when a permit application is submitted to the county, or
when the county proposes to take an official action as defined in WAC 197-11-704.
(2) Limitations on Actions during SEPA Process. Until the responsible official issues a final DNS or FEIS and the
SEPA appeal period has lapsed, the county shall not take any project action (issuing permits, approvals, etc.) on a
nonexempt project, or take any nonproject action (decisions on policies, plans, programs, etc.), that would have an
adverse environmental impact or would limit the choice of reasonable alternatives. [Ord. 8-06 § 1]
18.40.750 Categorically exempt actions – Use of existing documents and analyses.
(1) Categorically Exempt Levels.
(a) Except with the adoption of flexible threshold limits as set forth in subsection (1)(b) through (e) of this
section, Jefferson County adopts and incorporates by reference the categorical exemption levels set forth in
WAC 197-11-800..
(b) Pursuant to WAC 197-11-800(1)(c)(v), the maximum exempt level for any landfill or excavation activity in
Jefferson County shall be 500 cubic yards.
(c) Pursuant to WAC 197-11-800(1)(c)(ii), the maximum exempt level for the construction of a barn, loafing
shed, farm equipment storage building, produce storage or packing structure, or similar agricultural structure,
covering 30,000 square feet, and to be used only by the property owner or his or her agent in the conduct of
farming the property. This exemption shall not apply to feed lots.
(d) Pursuant to WAC 197-11-800(1)(c)(iii), the maximum exempt level for the construction of an office,
school, commercial, recreational, service or storage building with 12,000 square feet of gross floor area, and
with associated parking facilities designed for up to 40 automobiles.
(e) Pursuant to WAC 197-11-800(1)(c)(iv), the construction of a parking lot designed for 40 automobiles shall
be exempt.
(2) Categorically Exempt Actions. Actions categorically exempt under subsection (1) of this section do not require
review under this article or the preparation of an environmental impact statement, and may not be conditioned or
denied under SEPA, except as provided in WAC 197-11-305 and subsection (3) of this section.
(3) Use of Exemptions.
(a) The responsible official will determine the applicability of a categorical exemption. The determination by
the responsible official that a proposal is exempt from SEPA is final. None of the procedural requirements of
this article (except as provided in WAC 197-11-305 and this subsection) apply to an exempt proposal.
(b) If a proposal includes exempt and non-exempt actions, the responsible official shall determine the lead
agency pursuant to WAC 197-11-050.
(c) If a proposal includes exempt and non-exempt actions, the county may authorize exempt actions prior to
compliance with procedural requirements of this article, except as provided in subsections (3)(d) through (3)(g)
of this section.
(d) Consistent with WAC 197-11-070, 197-11-305 and 197-11-800, the county may not authorize the use of
exemptions for:
(i) Actions that are not exempt;
(ii) Any action that would have a probable significant adverse environmental impact;
(iii) A series of exempt actions that are physically or functionally related which together would result in a
probable significant adverse environmental impact for the overall project; or
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 34/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(iv) Any action that would limit choice of alternatives.
(e) The county may withhold approval of an exempt action that would lead to modification of the physical
environment when such modification would serve no purpose if nonexempt action(s) were not approved (see
WAC 197-11-305(1) (b)(i)).
(f) The county may withhold approval of exempt actions that would lead to substantial financial expenditures
by a private applicant when the expenditures would serve no purpose if the non-exempt action(s) were not
approved (see WAC 173-806-060).
(g) Actions identified as categorically exempt from SEPA under WAC 197-11-800 shall remain exempt under
SEPA even when located in one or more of the environmentally sensitive areas (ESAs) classified, designated
and mapped under Article VI-D of Chapter 18.15 JCC. However, the categorical exemptions listed in WAC
197-11-800 shall not apply when undertaken wholly or partly on lands covered by water, regardless of whether
or not such lands are mapped as ESAs. Proposals in areas subject to this subsection (3)(g) shall require
environmental review and a threshold determination, and may be conditioned or denied under this article (see
WAC 197-11-756, 197-11-800, and 197-11-908).
(4) Use of Existing Documents and Analyses. Procedures for the use, adoption, or incorporation of existing
documents and analyses are provided in WAC 197-11-600, 197-11-610, 197-11-630, and 197-11-635.
(5) Planned Actions.
(a) The county may, as part of its planning processes, elect to perform or have performed for it in advance of
any development proposal, the environmental review and analysis for certain actions and their probable
impacts. These “planned actions” must be so designated by ordinance or resolution adopted by the county after
the analysis of the actions and their impacts has been completed.
(b) Planned actions must be located in an urban growth area, a master planned resort (MPR), or a fully
contained community, and meet the additional requirements contained in RCW 43.21C.031 (2)(a).
(c) The analysis must be sufficient to identify and analyze all probable significant impacts and most
nonsignificant impacts of the actions, and to identify (and, optionally, provide) to a great extent the mitigation
necessary (i.e., the significant impacts must be “adequately addressed” in an environmental impact statement).
(d) As a result of the analysis in subsections (5)(a) and (5)(c) of this section, a development proposal being
prepared under a planned action does not require a threshold determination or the preparation of an
environmental impact statement, but is subject to a full environmental review of its impacts and full
requirements for mitigation as identified and specified by the review for the planned action in subsection (5)(c)
of this section.
(e) If the environmental review identifies additional impacts not addressed by the planned action, a checklist
and threshold determination shall be required. [Ord. 8-06 § 1]
18.40.760 Analysis of nonexempt project and nonproject actions.
The procedures and requirements in this article apply equally to project and nonproject actions.
(1) Submittal of Environmental Checklist.
(a) A completed environmental checklist shall be submitted with any application for a permit or approval not
specifically exempted as per JCC 18.40.750(1). However, a checklist is not required if the county and applicant
agree that an EIS is required, if SEPA compliance has been completed, or if SEPA compliance has been
initiated by another agency. The county shall use the checklist to determine lead agency and to make the
threshold determination if the county is lead agency.
(b) Applicants for private proposals shall complete the checklist, and the county shall provide assistance as
appropriate. For county proposals, the department initiating the proposal shall complete the checklist.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 35/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) Review of Project Impacts. The responsible official shall review the checklist, other information about a project,
and the applicable regulations to review the environmental impacts of the project and make a threshold
determination. In making this review the responsible official may determine:
(a) All of the project’s probable significant adverse environmental impacts have been adequately identified and
analyzed. If not, additional studies and analyses may be required;
(b) Some or all of the probable significant adverse environmental impacts have been adequately addressed and
mitigated in this UDC and other development regulations adopted by Jefferson County, the Comprehensive
Plan, or in other applicable local, state, or federal laws and rules by:
(i) Avoiding or otherwise mitigating the impacts; or
(ii) The county has designated as acceptable certain levels of service, land use designations, development
standards, or other land use planning required or allowed by the Growth Management Act (Chapter
36.70A RCW).
Where probable significant adverse environmental impacts have not been adequately mitigated, the responsible
official may condition the project with additional mitigation measures or deny the permit;
(c) To determine if the probable significant adverse environmental impacts have been addressed by an existing
rule or law of another agency with jurisdiction, the county shall consult orally or in writing with that agency
and may expressly defer to that agency. In making this deferral, the county shall base or condition its project
approval on compliance with that agency’s rules or laws;
(d) If the county bases or conditions its SEPA approval of the project wholly or in part on compliance with the
requirements or mitigation measures identified in subsections (2)(b)(i) and (2)(b)(ii), during project review the
county shall not impose additional mitigation under SEPA for those impacts so conditioned;
(e) Nothing in this subsection limits the authority of the county in its review or mitigation of a project to adopt
or otherwise rely on environmental analyses and requirements under other laws, as provided by SEPA.
(3) Threshold Determination. The “threshold determination” is the decision regarding whether there is a reasonable
likelihood that the project will have a probable significant adverse environmental impact on an element of the
environment. A threshold determination is required for any proposal that meets the definition of an “action” under
WAC 197-11-704 and is not categorically exempt, a planned action, or subject to WAC 197-11-600(3). The
responsible official shall make and publish the threshold determination for public comment as provided in JCC
18.40.780:
(a) Determination of Significance (DS). If a project may have a probable significant adverse environmental
impact, a DS shall be issued, and an EIS shall be required. In determining an impact’s significance, the
responsible official shall take into account the guidance in WAC 197-11-330 and 197-11-794, including:
(i) Locational, quantitative, and cumulative effects, severity and likelihood of the effects, and effects on
environmentally sensitive or special areas; and
(ii) Mitigation measures that will be implemented. The responsible official shall not balance whether
beneficial aspects of a proposal outweigh its adverse environmental impacts in determining significance.
(b) Determination of Nonsignificance (DNS). If a project will not have a significant adverse environmental
impact, a DNS shall be issued.
(c) Request for Early Indication of DS. Pursuant to WAC 197-11-350(2) and (6), submission of an
environmental checklist and prior to the responsible official’s threshold determination on a proposal, an
applicant may ask the responsible official to indicate whether it is considering a DS. If the responsible official
indicates a DS is likely, the applicant may clarify or change features of the proposal to mitigate the impacts that
led the responsible official to consider a DS likely. The applicant shall revise the environmental checklist as
may be necessary to describe the clarifications or changes. The responsible official shall make its threshold
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 36/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
determination based upon the changed or clarified proposal. If a proposal continues to have one or more
probable significant adverse environmental impacts, even with mitigation measures, an EIS shall be prepared.
The county’s indication under this section that a DS appears likely shall not be construed as a determination of
significance. Likewise, the preliminary discussion of clarifications or changes to a proposal shall not bind the
county to a mitigated DNS.
(4) Mitigated Determination of Nonsignificance (MDNS). The responsible official may issue a MDNS as provided
in this subsection and in WAC 197-11-350, based on conditions attached to the proposal by the responsible official
or on changes to or clarifications of the proposal made by the applicant.
(a) Mitigation measures that justify issuance of a MDNS shall be incorporated in the DNS shall be deemed
conditions of approval of the permit decision, and may be enforced in the same manner as any term or
condition of the permit. The county may incorporate implementation or enforcement provisions in the MDNS
and require performance guarantees.
(b) If the tentative county decision on a permit or approval does not include mitigation measures that were
incorporated in a MDNS, the county shall evaluate the threshold determination to assure consistency with
WAC 197-11-340(3)(a) (i.e., withdrawal of a DNS).
(5) The responsible official shall provide for prompt and coordinated review by government agencies and the public
on compliance with applicable environmental laws and plans, including mitigation for specific probable significant
adverse impacts arising from the project that have not been considered and addressed at the plan or development
regulation level. The county may clarify or change features in their own proposal, and may specify mitigation
measures in their DNSs, as a result of comments by other agencies or the public or as a result of additional agency
planning (see WAC 197-11-350).
(6) Durations of comment periods are as provided in JCC 18.40.780. At the end of the comment period the threshold
determination becomes final unless retained, modified, or withdrawn, and the appeal period begins.
(7) Preparation of EIS.
(a) Preparation of the draft environmental impact statement (DEIS) and final environmental impact statement
(FEIS) and supplemental environmental impact statement (SEIS) are the responsibility of the county under the
direction of the responsible official. Before the county issues an EIS the responsible official must be satisfied
that it complies with this article and with Chapter 197-11 WAC. When a DS is issued, an opportunity will be
provided to comment on the scope of the EIS that will be developed.
(b) The DEIS, FEIS or SEIS will be prepared by the county or by a consultant in accordance with county
procedures established for consultant selection. If the county requires an EIS for a proposal and the responsible
official determines that a consultant will prepare the EIS, the applicant shall be so notified immediately after
completion of the threshold determination.
(c) The county may require an applicant to conduct specific investigations and to provide information the
county does not possess. The applicant is not required to supply information for the purpose of EIS preparation
if such information is not required under this article.
(d) If a consultant is preparing an EIS, the responsible official shall assure that the EIS is prepared in a
responsible manner. The county shall:
(i) Initiate and coordinate scoping and ensure that the consultant receives all substantive information
submitted through the scoping process;
(ii) Assist the consultant in obtaining information from applicants; and
(iii) Direct the content and organization of the EIS.
(e) The responsible official shall maintain procedures for preparation of EISs in accordance with the above.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 37/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(8) The DNS and checklist, or FEIS, for non-exempt proposals shall accompany county staff recommendations to
any appropriate decision-making body (e.g., the hearing examiner).
(9) The county shall not take any action on the project permit application until the SEPA appeal period has lapsed.
(10) Any appeal of the final SEPA determination shall be heard as provided in JCC 18.40.810. [Ord. 8-06 § 1]
18.40.770 Substantive authority.
(1) The county may attach conditions to a permit or approval for nonexempt actions pursuant to WAC 197-11-660;
provided, that:
(a) The conditions are necessary to mitigate probable significant adverse environmental impacts identified in
environmental documents prepared pursuant to this code and Chapter 197-11 WAC;
(b) Such conditions are in writing;
(c) The mitigation measures included in such conditions are reasonable and capable of being accomplished;
(d) The responsibility to implement the mitigation measures are imposed only to the extent attributable to the
identified adverse environmental impacts of the applicant’s proposal, although voluntary additional mitigation
may occur;
(e) The county has considered whether the requirements of the Jefferson County Comprehensive Plan and
development regulations adopted to implement the Plan, as well as other local, state, and federal laws or rules,
provide adequate analysis of and mitigation for probable significant adverse environmental impacts of the
project proposal; and
(f) Such conditions are based on one or more policies in subsection (3) of this section.
(2) The county may deny a permit or approval for nonexempt actions pursuant to WAC 197-11-660; provided, that:
(a) A finding is made that approving the proposal would be likely to result in probable significant adverse
environmental impacts that are identified in an FEIS or final SEIS prepared pursuant to this code and Chapter
197-11 WAC;
(b) A finding is made that there are no reasonable mitigation measures capable of being accomplished that are
sufficient to mitigate the identified impact;
(c) The denial is based on one or more policies set forth in subsection (3) of this section.
(3) The county designates and adopts by reference the following county plans, ordinances and policies as the basis
for exercise of county authority pursuant to this article:
(a) The county adopts by reference the policies in the following Jefferson County plans and ordinances:
(i) The Jefferson County Comprehensive Plan, as now exists or may hereafter be amended;
(ii) The Jefferson County Shoreline Master Program, as now exists or may hereafter be amended;
(iii) This Unified Development Code, as now exists or may hereafter be amended;
(iv) The Jefferson County building code, Chapter 15.05 JCC, as now exists or may hereafter be amended;
(v) The Jefferson County flood damage protection ordinance, Chapter 15.15 JCC, as now exists or may
hereafter be amended;
(vi) The Jefferson County stormwater management ordinance, JCC 18.30.070, as now exists or may
hereafter be amended;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 38/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(vii) The Jefferson County Road, Traffic and Circulation Standards, as they now exist or may hereafter be
amended;
(viii) The Secretary of the Interior’s Standards for Rehabilitating Historic Buildings; and
(ix) All other county plans, ordinances, regulations and guidelines adopted after the effective date of this
Unified Development Code.
(b) The policies enumerated in RCW 43.21C.020.
(c) The county further designates and adopts the following policies as the basis for its exercise of authority
pursuant to this article. The county shall use all practicable means, consistent with other essential
considerations of state policy, to improve and coordinate plans, functions, programs and resources to the end
that the state and its citizens may:
(i) Fulfill the responsibilities of each generation as trustee of the environment for succeeding generations;
(ii) Assure for all people of the state of Washington and Jefferson County a safe, healthful, productive and
aesthetically and culturally pleasing surrounding;
(iii) Attain the widest range of beneficial uses of the environment without degradation, risk to health or
safety, or other undesirable and unintended consequences;
(iv) Preserve important historic, cultural and natural aspects of our national heritage;
(v) Enhance the quality of renewable resources and approach the maximum attainable recycling of
depletable resources; and
(vi) Achieve a balance between population and resource use, which will permit a high quality of life for all
residents of Jefferson County. [Ord. 8-06 § 1]
18.40.780 Public notice and comment.
(1) When the responsible official makes a threshold determination and issues a DNS or MDNS under WAC 197-11-
340(2), the responsible official shall use the “optional DNS process” pursuant to WAC 197-11-355. Under this
process, where the county is the lead agency for a project and the responsible official has a reasonable basis for
determining significant adverse environmental impacts are unlikely, it shall use a single integrated 14-day comment
period to obtain comments on the notice of application and the likely threshold determination for the proposal. There
will be no second comment period when the DNS or MDNS is issued.
(a) The notice of application shall contain the information regarding the optional DNS process as set forth in
JCC 18.40.190(11), and shall be noticed as set forth in JCC 18.40.210. The notice of application and
environmental checklist shall be sent to agencies with jurisdiction, the Department of Ecology, affected tribes,
and each local agency or political subdivision whose public services would be changed as a result of the
implementation of the proposal, as well as anyone requesting a copy of the environmental checklist for the
specific proposal.
(b) For Type II projects, the threshold determination shall be issued concurrently with the notice of the
administrator’s decision on the underlying project, as further set forth in JCC 18.40.320(3).
(c) For Type III projects, the notice of the threshold determination shall be issued concurrently with the notice
of public hearing on the underlying project before the hearing examiner.
(d) If the county indicates on the notice of application that a DNS or MDNS is likely, an agency with
jurisdiction may assume lead agency status during the comment period on the notice of application pursuant to
WAC 197-11-355(3) and 197-11-948.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 39/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(e) Type I projects that are not categorically exempt from SEPA shall be subject to notice of application and
comment period provisions of JCC 18.40.150 through 18.40.220, as well as the notice requirements of this
section.
(f) If a DS is made concurrent with the notice of application, the DS and scoping notice shall be combined with
the notice of application; provided, however, that the DS/scoping notice may be issued before the notice of
application (RCW 36.70B.110). If sufficient information is not available to make a threshold determination
when the notice of application is issued, the DS may be issued later in the review process (WAC 197-11-
310(6)). If the responsible official issues a DS under WAC 197-11-360(3), the responsible official shall state
the scoping procedure for the proposal in the DS, as required by WAC 197-11-408, by publishing notice in the
official county newspaper.
(2) If the county issues a DEIS under WAC 197-11-455(5), FEIS under WAC 197-11-560, or SEIS under WAC
197-11-620, notice of availability of the documents shall be given by publishing notice in the official county
newspaper; by notifying groups which have expressed interest in a certain proposal being considered; by notifying
the news media; by sending notice to agency mailing lists; and by other means deemed appropriate by the
responsible official.
(3) The applicant shall be responsible for all costs of the public notice requirements under this article.
(4) Comment periods begin with the publication of notice as provided in this section. Comments must be received
within:
(a) Fourteen calendar days for a DNS or MDNS;
(b) Twenty-one calendar days for a DS and scoping notice. Pursuant to WAC 197-11-408(2)(a)(iii), the date of
issuance for purposes of computing this comment period shall be the date the DS is sent to the Department of
Ecology and other agencies with jurisdiction and is made publicly available; and
(c) Thirty calendar days for a DEIS.
(5) The responsible official shall consider timely comments on the notice of application and either issue a DNS or
MDNS with no comment period using the procedures set forth in Article IV of this chapter and this article; issue a
DS; or require additional information or studies prior to making a threshold determination. A copy of the DNS or
mitigated DNS shall be sent to agencies with jurisdiction, the Department of Ecology, those who commented, and
anyone requesting a copy. A copy of the environmental checklist need not be recirculated.
(6) A DNS or MDNS becomes final at the end of the comment period unless the determination is modified or
withdrawn by the responsible official.
(a) When a DS is withdrawn and a DNS issued, a new notice must be published as provided in this section, and
a 14-calendar-day comment period provided on the new threshold determination.
(b) When a DNS is withdrawn and a DS issued, a new notice must be published as provided in this section, and
a 21-calendar-day comment period provided on the new threshold determination and scoping notice.
(c) If modified, the threshold determination becomes final upon publication of notice as provided in this section
by the responsible official. A new appeal period shall then commence.
(7) Notice for public hearings shall be given consistent with this section and JCC 18.40.230, and may be combined
with other notice(s). [Ord. 8-06 § 1]
18.40.790 Public hearings and meetings.
(1) If a public hearing on the proposal is held under some other requirement of law, the hearing shall be open to
consideration of the environmental impact of the proposal, together with any environmental document that is
available. This does not require extension of the comment periods for environmental documents.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 40/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(2) In all other cases a public hearing on the environmental impact of a proposal shall be held whenever one or more
of the following situations occur:
(a) The county determines that a public hearing would assist it in meeting its responsibility to implement the
purposes and policies of SEPA and its implementing rules;
(b) When 100 or more persons who reside within the county, or who would be adversely affected by the
environmental impact of the proposal, make written request to the lead agency within 30 calendar days of
issuance of the DEIS; or
(c) When two or more agencies with jurisdiction over a proposal make written request to the lead agency within
30 calendar days of the issuance of the DEIS.
(3) Whenever a public hearing is held under subsection (2) of this section, it shall occur no earlier than 15 calendar
days from the date the DEIS is issued, and not later than 50 calendar days from its issuance. Notice shall be given as
set forth in JCC 18.40.780(6).
(4) Whenever a public hearing is held under subsection (2) of this section, it shall be open to discussion of all
environmental documents and any written comments that have been received by the county prior to the hearing. A
copy of the environmental document shall be available at the public hearing.
(5) Comments at public hearings should be as specific as possible (see WAC 197-11-550).
(6) The county may hold informal public meetings or workshops. Such gatherings may be more flexible than public
hearings and are not subject to the above notice and similar requirements for public hearings.
(7) Public meetings held under Chapter 36.70B RCW may be used to meet SEPA public hearing requirements so
long as the requirements of this section are met. A public hearing under this section need not be an open record
hearing as defined in RCW 36.70B.020(3). [Ord. 8-06 § 1]
18.40.800 Environmentally sensitiveCritical areas.
(1) Actions identified as categorically exempt from SEPA under JCC 18.40.750(1) shall remain exempt under SEPA
even when located in one or more of the ESAs critical areas classified, designated and mapped under Article VI-D
of Chapter 18.1522 JCC. A threshold determination shall not be required for actions identified as categorically
exempt.
(2) Actions located in one or more ESAs critical areas that are categorically exempt from review under this article,
and which require issuance of a permit or approval under this code or any other applicable county ordinance or
regulation, shall be reviewed, and as necessary, conditioned or denied to assure consistency with the protection
standards contained in Article VI-D of Chapter 18.1522 JCC. [Ord. 8-06 § 1]
18.40.810 Appeals.
(1) Appeal of a Threshold Determination for a Type I Permit Decision. Threshold determinations on Type I permit
decisions may not be appealed administratively to the hearing examiner.
(2) Appeal of a Threshold Determination for Type II Permits – Open Record Hearing. The decision of the
responsible official on Type II permits making a threshold determination of a DNS or MDNS, approving a proposal
subject to conditions, or denying a proposal under SEPA’s substantive authority may be appealed to the hearing
examiner pursuant to JCC 18.40.280 for an open record appeal hearing. Any such appeal must be filed within the
time limits of JCC 18.40.330(2)(b), and must be consolidated with any appeal on the underlying Type II permit
decision. Any requests for reconsideration shall be governed by JCC 18.40.310.
(3) Appeal of a Threshold Determination for Type III Permits – Open Record Hearing. The decision of the
responsible official on Type III permits making a threshold determination of a DNS, approving a proposal subject to
conditions, or denying a project under SEPA’s substantive authority may be appealed to the hearing examiner
pursuant to JCC 18.40.280. The open record public hearing on the SEPA appeal shall be before the hearing
examiner, who shall consider the appeal together with the decision on the project application in a single,
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 41/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
consolidated hearing as further set forth in Article IV of this chapter. Any requests for reconsideration shall be
governed by JCC 18.40.310.
(4) Appeals of Threshold Determinations for Type V Actions. Threshold determinations of the responsible official
on Type V decisions (other than a DS) may not be appealed to the hearing examiner.
(5) Limitations on Appeals for All Types of Permits. When a threshold determination results in a DS it shall not be
appealable. In addition, issues relating to the adequacy of the EIS and other procedural issues may not be appealed
under this article.
(6) Who May Appeal. An applicant or other party of record, as defined in Chapter 18.10 JCC, may file a SEPA
appeal as provided in this article.
(7) Time to Appeal Administrative Decisions. A written statement appealing the threshold determination must be
filed within 14 calendar days after the notice of decision is issued. When the last calendar day (as defined in Chapter
18.10 JCC) of the appeal period is a Saturday, Sunday or legal holiday, the appeal period shall run to the next
business day.
(8) Form of Appeal. A person or group appealing the decision of the responsible official shall submit a written
appeal in the form and manner set forth in JCC 18.40.330(5). Notice of all appeals shall be mailed to all parties of
record not less than 10 calendar days prior to the date of the public hearing to consider the appeal.
(9) Scope of Review. The hearing examiner shall affirm, modify or reverse the responsible official’s decision, and
shall enter findings and/or conclusions into the record to support the decision. In making the decision, the hearing
examiner shall give deference to and afford substantial weight to the decision of the responsible official. Review
shall be on a de novo basis.
(10) Judicial Appeals. Pursuant to RCW 43.21C.075, if there is a time period for appealing the underlying permit
decision, appeals under this article shall be commenced within such time period. The county shall give official
notice stating the date and place for commencing an appeal.
(a) Optional Limitation Period. If there is no time period for appealing the underlying government action, the
county, applicant for or proponent of an action may use a notice of action pursuant to RCW 43.21C.075 and
43.21C.080. The notice shall describe the action and state time limitations for commencing a challenge to that
action, in a form substantially similar to that provided in WAC 197-11-990. The notice shall be published by
the department, applicant or proponent pursuant to RCW 43.21C.080, and any action to set aside, enjoin,
review or otherwise challenge any such governmental action shall be commenced within 21 days from the date
of the last newspaper publication of the notice of action, as further set forth in RCW 43.21C.080.
(b) Exemption. This article does not apply to decisions made pursuant to Chapter 90.58 RCW, the Shoreline
Management Act. Appeals of SEPA mitigation measures pertaining to projects subject to Chapter 90.58 RCW
shall be made to the shoreline hearings board along with the appeal of the county’s shoreline decision, as
further set forth in Chapter 90.58 RCW. In addition, as an alternative dispute resolution process, any SEPA
appeal, whether involving a shoreline issue or not, may be made to the shoreline hearings board upon the
consent of the parties to the action, as further set forth in RCW 43.21C.075(7).
(11) Violations and Penalties. The administrator is authorized to enforce the provisions of this article whenever he or
she determines that a condition exists in violation of this article or permit issued hereunder. All violations of any
provisions of this article, incorporated standard or permit issued pursuant to this article are made subject to the
provisions of Chapter 18.50 JCC, which provides for voluntary correction, notice and orders to correct the violation,
stop work and emergency orders, and assessment of civil penalties.
(12) Public Nuisance. All violations of this article are determined to be detrimental to the public health, safety and
welfare and are public nuisances, and may corrected by any reasonable and lawful means, as further set forth in
Chapter 18.50 JCC.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 42/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(13) Alternative Remedies. As an alternative to any other judicial or administrative remedy provided in this article
or by law or ordinance, any person who willfully or knowingly violates or fails to comply with any stop work order
or emergency order issued pursuant to Chapter 18.50 JCC is guilty of a misdemeanor and upon conviction shall be
punished as set forth in JCC 18.50.110. Each day such violation or failure to comply continues shall be considered
an additional misdemeanor offense. [Ord. 8-06 § 1]
Article XI. Development Agreements
18.40.820 Purpose.
This article establishes the mechanism under which Jefferson County may enter into development agreements as
authorized by RCW 36.70B.170. A decision to enter into a development agreement shall be made on a case-by-case
basis. A development agreement may be appropriate for large, complex or phased projects, or projects which were
not contemplated by existing development regulations or existing application procedures. [Ord. 8-06 § 1]
18.40.830 General requirements.
(1) Discretion to Enter Development Agreement. A development agreement is an optional device that may be used
at the sole discretion of the county, except a development agreement shall be required for applications for master
planned resorts in accordance with JCC 18.15.126 and major industrial developments in accordance with JCC
18.15.605.
(2) Who May Enter. The property owner(s) and the county shall be parties to a development agreement; provided,
that if a proposed development is within an adopted municipal UGA, the applicable town or city shall also be a party
to the agreement. The following may be considered for inclusion as additional parties in a development agreement:
contract purchasers, lenders, third-party beneficiaries and utility service providers.
(3) Content of Development Agreements. A development agreement shall be prepared by the applicant and shall set
forth the development standards and other conditions that shall apply to and govern the development, use and
mitigation of the property subject to the agreement.
(4) When Development Agreements May Be Approved. A development agreement may be entered into prior to,
concurrent with or following approval of project permits for development of the property.
(5) Consistency with Unified Development Code. The development standards and conditions set forth in a
development agreement shall be consistent with the applicable development regulations set forth in the Unified
Development Code, except in the case of a master planned resort (which requires a site-specific Comprehensive Plan
amendment), where adopted standards may be modified by the development standards contained in the agreement,
so long as all project impacts have been adequately mitigated. However, the minimum requirements related to the
protection of environmentally sensitivecritical areas in Article VI-D of Chapter 18.1522 JCC may not be varied by
adoption of any development agreement. [Ord. 8-06 § 1]
18.40.840 Development standards to be addressed.
(1) A development agreement shall include, but need not be limited to, one or more of any of the following types of
development controls and conditions:
(a) Project elements such as permitted uses, residential and nonresidential densities, scale and intensity of uses
and/or building sizes;
(b) Mitigation measures, development conditions and other requirements pursuant to environmental review
under Chapter 43.21C RCW;
(c) Design standards such as maximum heights, setbacks, drainage and water quality requirements, screening
and landscaping and other development features;
(d) Roads, water, sewer, storm drainage and other infrastructure requirements;
(e) Affordable housing;
(f) Recreational uses and open space preservation;
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 43/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(g) Phasing;
(h) Development review procedures, processes and standards for implementing decisions, including methods of
reimbursement to the county for review processes;
(i) Other appropriate development requirements or procedures.
(2) A development agreement may obligate a party to fund or provide services, infrastructure, or other facilities.
Project applicants and governmental entities may include provisions and agreements whereby applicants are
reimbursed over time for financing public facilities.
(3) Development agreements shall:
(a) Establish a process for amending the agreement;
(b) Specify a termination date upon which the agreement expires;
(c) Establish a vesting period for applicable standards; and
(d) Reserve authority to impose new or different regulations to the extent required by a serious threat to public
health and safety. [Ord. 8-06 § 1]
18.40.850 Procedures.
(1) A development agreement shall be initiated by a written request from the property owner to the administrator of
the department of community development. The request should describe the project and the specific reasons why the
project is suitable for a development agreement. The request should identify the development standards set forth in
JCC 18.40.840 that the applicant is requesting to be included in the development agreement and any other
reasonable information requested by the county.
(2) If the administrator determines in his or her discretion that a development agreement should be considered by the
county, the property owner shall be so informed, except that development agreements shall be required for the
approval of master planned resorts in accordance with JCC 18.15.126 and for the approval of major industrial
developments in accordance with JCC 18.15.605.
(3) When a development agreement is being considered prior to project permit approvals, the property owner shall
provide the county with the same information that would be required for a complete application for such project
permits in order for the county to determine the development standards and conditions to be included in the
development agreement.
(4) When a development agreement is being considered following approval of project permits, the development
standards and other conditions set forth in such project permits shall be used in the development agreement without
modification.
(5) The county shall only approve a development agreement by ordinance or resolution after a public hearing. The
board of county commissioners may, in its sole discretion, approve the development agreement (see Table 8-1
above). If the development agreement relates to a project permit application, the provisions of Chapter 36.70C RCW
shall apply to the appeal of the decision on the development agreement.
(6) An approved and fully executed development agreement shall be recorded with the county auditor. [Ord. 8-06 §
1]
18.40.860 Effect.
(1) A development agreement is binding on the parties and their successors, including a city that assumes
jurisdiction through incorporation or annexation of the area covering the property subject to the development
agreement.
(2) A development agreement shall be enforceable during its term by a party to the agreement.
Jefferson County Code
Chapter 18.40 PERMIT APPLICATION AND REVIEW
PROCEDURES/SEPA IMPLEMENTATION
Page 44/44
The Jefferson County Code is current through Ordinance 1-16, passed February 1, 2016.
(3) A development agreement shall govern during the term of the agreement all or that part of the development
specified in the agreement and may not, unless otherwise agreed to in the development agreement, be subject to an
amendment to a local government land use ordinance or development standard or regulation or a new local
government land use ordinance or development standard or regulation adopted after the effective date of the
agreement.
(4) Permits issued by the county after the execution of the development agreement shall be consistent with the
agreement.
(5) Nothing in RCW 36.70B.170 through 36.70B.200 and Section 501, Chapter 374, Laws of 1995, or this chapter is
intended to authorize the county to impose impact fees, inspection fees, or dedications or to require any other
financial contributions or mitigation measures except as expressly authorized by other applicable provisions of state
law. [Ord. 8-06 § 1]
1 Pursuant to RCW 36.70B.140(2), boundary line adjustments, building and other construction permits, or similar administrative
approvals categorically exempt from environmental review under SEPA (i.e., Chapter 43.21C RCW), or permits/approvals for
which environmental review has been completed in connection with other project permits, are excluded from the provisions of
RCW 36.70B.060, and 36.70B.110 through 36.70B.130.