HomeMy WebLinkAboutSchedule Type I with SEPAESTIMATED TIMELINE FOR TYPE I PERMIT PROCESS with SEPAFeb. 13, 2019Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11Week 12Week 13Week 14Week 15Week 16Week 17Date31421284111825411182518152229Elapsed Days310172431384552596673808794101108115Date of Intake1/9/201928-Day Determination of Complete AppliationIncomplete 24-JanPre-Application Conference PRE19-0000813-Feb14 days from Det. Of Completeness to PublicationSEPA DeterminationNotice of App. & SEPA Det. Publication Date (Wednesday)6-MarApplicant posts Notice Board14 Day Comment Periodto 19-MarStaff AnalysisFinal Threshold Determination14 Day No Action Period per 197-11-340 (2)(iii)Prepare Permits--Findings & Conditions Issue PermitsActivityCritical Path ActivityJoel Peterson, Associate PlannerElapsed TimeJefferson County Department of Community DevelopmentApplicant621 Sheridan StreetDCDPort Townsend, WA 98368(360) 379-4457JanuaryFebruary MarchApril