HomeMy WebLinkAbout090919_ca04To:
From:
Agenda Date:
Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
Board of Commissioners
Philip Morley, County Administrator
Monte Reinders, P.E., Public Works Director/County Engineer
September 9, 2019
Subject: Utility Relocation/Adjustment Agreement between Jefferson County
and CenturyLink for the Upper Hoh Road/Olympic National Park FLAP
Project, Project No. 18019410
Statement of Issue: The Federal Highway Administration has requested that Jefferson
County enter into an agreement with CenturyLink for the above referenced project.
Analysis/Strategic Goals/Pro's Et Con's: The Upper Hoh Road/Olympic National Park
FLAP project is being managed by the Federal Highway Administration Western Federal
Lands Division (WFL). The project will encompass three sites on Upper Hoh Road and
will require temporary and permanent utility relocations by CenturyLink. It is standard
practice for WFL to have project -specific agreements with affected utilities, and
therefore WFL has requested that Jefferson County, as the land owner, enter into this
agreement with CenturyLink for the term of the project.
Fiscal Impact/Cost Benefit Analysis: This a non -reimbursable agreement. There will be
no reimbursement to CenturyLink for utility relocation/adjustment as a result of this
agreement. The agreement commits Jefferson County to coordinating with CenturyLink
on the utility relocations/adjustments, and Jefferson County will incur staff
expenditures typical for utility coordination on construction projects.
Recommendation: The Chair of the Board is requested to sign all three originals of the
Agreement and return two originals to Public Works.
Department Contact: Mark Thurston, Project Manager, 385-9210.
Date
Non -Reimbursable
UTILITY RELOCATION/ADJUSTMENT AGREEMENT
Federal Highway Administration Project "WA JEFF 91420(1) Upper Hoh Road, Ph. 2"
RELOCATION AND/OR ADJUSTMENT OF FACILITIES
THIS AGREEMENT, by and between Jefferson County, Washington, hereinafter called
"County", and CenturyLink, hereinafter called "Company," is authorized by Title 23 CFR 645.
WHEREAS, the Department of Transportation, Federal Highway Administration
("Department"), in cooperation with the County, plans to reconstruct approximately 1.05 miles
of the Upper Hoh Road, also known as County Road 91420, at three locations: 1) Milepost 3.2-
4.0, install large fish passage culvert and bank stabilization, 2) Milepost 7.8-8.1, replace Tower
Creek Bridge, and bank stabilization, and 3) Milepost 10.1-10.4, construct Canyon Creek
Bridge, and bank stabilization.
WHEREAS, due to the construction of this project, it is necessary to relocate and/or adjust
underground phone cable facilities at all conflict locations within the County road right of way.
The Company and County agree to the temporary and permanent relocation and/or adjustment of
those phone facilities in conflict with the project, according to the Company's engineering and
relocation planning referenced as part of this agreement, and according to the Department's
construction plans and cross sections sheets.
WHEREAS, it is deemed to be in the best public interest that necessary relocation and/or
adjustment of said phone facilities shall be accomplished by the Company before the beginning
of planned road construction AND during road construction, and shall be performed under the
terms of this agreement and in accordance with and governed by the provisions of the
Government's Code of Federal Regulations 23 CFR 645.
PERFORMANCE OF WORK
NOW, THEREFORE, in consideration of the foregoing, IT IS MUTUALLY AGREED that:
The Company shall perform or cause to be performed the work herein described, furnishing all
materials and supplies necessary and incidental to the relocation and/or adjustment of its
facilities;
Preliminary relocation engineering activities will be performed by Company forces.
Relocation construction work will be performed by Company forces, to include, but not limited
to:
• Permanent relocation of phone line at road construction conflict areas identified by the
Company. The Company will determine how and where the permanent relocations will
occur, according to its relocation plan.
• Coordinate with the County on permanent locations, to ensure relocations occur within
existing County rights of way and newly -acquired permanent easement areas.
Page 1 of 4
• Temporary relocation of phone line at those locations, including culverts, identified by
the Company. The Company will determine how and where the temporary relocations
will occur, according to its relocation plan.
• Move temporarily -relocated phone line to permanent locations after road construction is
completed in those conflict areas. The Company MUST avoid damaging the new road
construction when moving its temporarily -relocated line to permanent locations.
• Measure and document the depths and locations at which the phone line and conduit have
been relocated, and provide this information to the County and Department prior to the
beginning of road construction.
• Contact the County and Department immediately, if, during relocation activities, that
other possible, unanticipated conflicts may occur during road construction.
• Coordinate with the County and Department on standards for installing conduit at Tower
Creek and Canyon Creek bridges, and at other areas, if needed.
Equipment and materials needed for the work will be furnished by Company forces.
The Company will complete all necessary temporary and/or permanent relocation work needed
to avoid the known road construction conflicts by February 5, 2021. The Company, after the
Department installs conduit at the locations noted in the construction plans, will permanently
relocate the phone cable in the conduit no more than 60 days after conduit is installed.
Costs
The Company's cost share will be 100% of all costs incurred to temporarily and permanently
relocate its underground phone facilities.
The County's cost share will be 0% of all costs incurred.
NOW, THEREFORE, in consideration of the foregoing, IT IS MUTUALLY AGREED that:
The County shall perform or cause to be performed the work herein described, necessary and
incidental to the coordination with the Company of planned relocations and of unforeseen
conflicts with phone facilities during relocation and during road construction;
• Review the Department's construction plans and the Company's relocation plan, and give
concurrence in writing, via email or letter, that the Company's proposed relocations are
sufficient to avoid conflicts with the project construction.
• Be available during relocation and road construction to help coordinate quick, efficient
mitigation of conflicts with the Company's facilities.
• Before road construction commences, concur with the Company that all needed
relocations have been completed, and notify the Department when all relocations have
been completed.
• Provide to the Department and its Highway Contractor the relocation depths and
locations from the Company, for inclusion into the project drawings.
Costs
The County's cost share will be 100% of all costs incurred for the above Performance of Work
tasks listed under "The County".
Page 2 of 4
The Company's cost share will be 0% of all costs incurred.
SCHEDULING AND COORDINATION
The County and the Company will coordinate before and during relocation construction to avoid
delays to the subject project schedule, and to avoid hindrance of other road work in the vicinity.
The Company will provide the County at least 14 days advance notice of when relocation
construction work will begin.
The Company will afford the County the opportunity to inspect the relocation work.
The points of contact for the County and Company will be:
Mark Thurston, P.E. Kelsie Watson, Engineer I
Jefferson County Public Works Century Link
623 Sheridan St. 4600 Neel Ct.
Port Townsend, WA. 98368 Gig Harbor, WA. 98335
(360) 385-9210 (206) 733-8723
MThurstongco.jefferson.wa.us kelsie.watsonkcenturylink.com
The point of contact for the Department will be:
Susan Ellis, Construction Operations Engineer
FHWA-Western Federal Lands
610 E. 5th St.
Vancouver, WA. 98661
(360) 619-7810
susan.elliskdot.gov
Authorization to Proceed
The Company is authorized to commence utility relocation and adjustment work on the date of
execution of this agreement.
Permits
The Company shall make application to appropriate authorities to obtain all necessary permits
and/or easements required to perform work herein described.
Page 3 of 4
IN WITNESS WHEREOF, the parties hereto have executed this Agreement
as of the date of signature of the Company.
CENTURY LINK
BY:
TITLE:
DATE:
JEFFERSON COUNTY
M
TITLE:
DATE:
Page 4 of 4