HomeMy WebLinkAboutNordland Construction NW, Inc., Change Order No. 1 re: Resurface and Restore Center Road - 100520 JEFFERSON COUNTY Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change 1 Date: 8/28/2020 CHANGE ORDER Order No. Ordered by County Engineer under terms of []Section 1-04.4 of the Standard Specifications and Contract No. 18020500 Change proposed byContractor To g P P Nordland Construction NW, Inc. __ Nordland Construction NW,Inc. 123 Ponderosa Place �^ .-- Nordland, WA 98358 ,,/ l,.,...,..,,�,••,,, actor Firm Name :V4 ,-bl Sii atuurre , Dat f// Z L5-,A' Y.,f� Title , Consent given by Surety:(when required) Project Title Center Road MP 14.61 - 15.01 Resurface and Restore By: Attorney-in-fact Date You are ordered to perform the following described work upon receipt of an approved copy of this change order: This change order will make the following changes to the contract: Adjust the contract amount to reflect actual bid item quantities used on the project,as shown on the attached spreadsheet. The total adjustment amount is an addition of $25,625.14.This amount includes underruns and overruns on several bid item quantities. All work materials and measurement to be in accordance with the provisions of the standard specifications and special provisions for the type of construction involved. ORIGINAL CURRENT 4,1 4 14 / CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL 7 AMOUNT AMOUNT THIS ORDER AFTER CHANGE ;, $498,513.95 $498,513.95 $25,625.14 $524,139.09 , ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT 4eff� 4 CONTRACT TIME CONTRACT TIME CHANGE(Add/Del) TIME ; g, N/A N/A-work completed 0 N/A -- i Y ` APPROVAL R M DED APP VA COMMENDED r Project Manager Date County Engineer Date A PROVAL RECQMMENDED APP I II V. l 1I2,S 1v II I r t/Sf202 Engineering er vic s Manager Date Chair,Jefferson Cou ty Commissioners Date o er co o 4W F W N 0 0 0 0 0 00 0 0 0 0 0 0 0 N F, O O p 00 O O M 01 O O O O V'1 O l� O O O CD �p 06 0 0 * V3 an 00 ,r1 _O O r,j O M O O M O O D In .-- o 00 p v'? N O M O co O O O O N ER j: I ci U N O N M M "1 in .zrkr) `^ N M asp (.n 0 C .� U M N t O M 00 O ,VD , . W Uo U O w 0 z 0 O O O co o o co co co Q 0 0 o co o 0 0 N o 0 co x v o 0 0 co 0 0 0 0 0 0 . o 0 0 . . o M 0 0 0 U o kn N oo O - 000 N O ,-- _ _ N O C O O N F P, 6R 69 EA 69 EA 69 69 6R 69 69 6R EA EA 69 69 EA 69 EA EA w F w .a ,JUH E- HHUX ,-,j ,-Sz .axxa ,.- .-aa F CA w CA cc o Q - x o > - 3 t E. i _a Q o b cA CO .n C7 5 0 v' a, O O C , a. 3 E- m U a. W U a� - w Q o OZ O W O N A b�D C N W = oxo a3i o U ;.., :x °v �o a WW U 4- ` t o d a C.- b CG C7�" z C tat) P. G Q Q a • . a O .a > o aoi = v) a. > C7 °� " PF-, O C.3 a A. `�" 'i, P. y = E °� crt a� W 44 U O ,� k w ¢ .1 a ' p G P, o _, W o •o U W o o P. x a A U w a) at' -o iiUw° yU3U c -a xU •c c ,oU �' P; P; c4 U an x Z U Q W U P. a P: F-1 i w F-• U Q W PL PG o p, N o cq O ° z N N C. 4, ON O N I I • a� 0O O •--- M 7r V') 00 O N vl N 00 —� M W I z ,— ^+ r•+ •--- N N N N N N N M M M M M 1 1 an Q I Department of Public Works O Consent Agenda Page 1 of 1 Jefferson County Board of Commissioners Agenda Request To: Board of Commissioners PhilipMorley, CountyAdministrator Y� From: Monte Reinders, Public Works Director/County Engineer Agenda Date: October 5, 2020 Subject: Change Order No. 1 Center Road MP 14.61 - 15.01 Resurface and Restore County Project No. 18020500 Statement of Issue: Change Order No. 1 with Nordland Construction NW, Inc. for Center Road MP 14.61 - 15.01 Resurface and Restore, Project No. 18020500, County Road No. 931507. Analysis/Strategic Goals/Pro's Et Con's: The objective of the project is to resurface and restore Center Road between the Little Quilcene River and US 101. The work has been completed and Change Order #1 is necessary to increase the total contract amount to reflect actual final quantities for each bid item in the contract and to add the cost of additional work items added in response to unanticipated conditions encountered during construction. Fiscal Impact/Cost Benefit Analysis: This change order will increase the total contract amount by $25,625.14 from $498,513.95 to $524,139.09. Construction of the road improvements portion of the project is funded 90% by Rural Arterial Program (RAP) grant funds administered by the County Roads Administration Board. Sidewalk improvements funded by $65,000 of Public Infrastructure Fund (PIF) funds are also part of the project. Recommendation: Public Works recommends that the Board execute all three (3) originals of Change Order No. 1 with Hanson Excavation, LLC and return two signed (2) originals to Public Works for further processing. Department Contact: Bruce D. Patterson, P.E., Project Manager, 385-9169. Reviewed By: Y Ptri[i Mori ount or Date