HomeMy WebLinkAboutBLD2021-00253 - 05 Approved Stormwater02-\-'h\
DEPARTMENT OF COMMUNITY DEI'ELOPMENT
621 Sheridan Strcct, Pon Townseod, WA 98368
Tel -160.379.4450 | Fax: 360.379.4451
Web: \r,ww.co.ie fferson.wa. us / communiwdevdoPment
F--mlL dcd@co.icfferson.wa.us Scan the QR
code to access
the digital form
STORMWATER CALCULATION WORKSHEET
,o"..,0 Q!8-I eaotecr/aerltc.lr,,tt tavt;a
DETERMTNTNG STORMWATER MANAGEMENT REqUIREMENTS; This stormwater calculation worksheet should be completed first to
classify the proposal as "small," "medium," or "large." The size determines whether a Stormwater Site Plan is required in
conjunction with a stand-alone stormwater management permit application, building permit application, or other land use approval
application that involves stormwater review. The basic information will also be helpful for completing a Stormwater Site Plan, if
req uired.
Lond-disturbing octivw is any activity that results in movement of earth, or a change in the existing soil cover (both vegetative and
non-vegetative) and/or the existing soiltopography. Land disturbing activities include, but are not limited to clearing, grading, filling,
excavation, and compaction associated with stabilization of structures and road construction.
Notive vegetation is vegetation comprised of plant species, other than noxious weeds, which reasonably could have been expected
to naturally occur on th€ site. Examples include species such as Douglas fir, western hemlock, western red cedar, alder, big-leaf
maple, and vlne maple; shrubs such as willow, elderberry, salmonberry, and salal; herbaceous plants such as sword fern, foam
flower, and fireweed,
ES,t#l:E;ri,Ffuffi
An acre contains 43,560 square feet. Multiply the acreage bythisfigure
PARCEL
Size of parcel in sq ,rr"t .t 11,lbh sq/ft
fl.E.. StTE)
size of parcel 0'{Li u"r".
lo15
l8D 0
qDD r/-Fi| 5A)% @utydl15 2 t?.Cut
Y
7
G
+
Constructio n site tor structures 3 Abq sq/ft
sq/ft
sq/ft
f, rr)
Other compacted surface, etc-
Does the project convert 2 % acres or more of
native vegetation to paslure
Drainfield, septic tank, etc.
Well, utilities, etc.
Temporary construction area
Total Land Disturbance
Driveway, parking, roads, etc
Lawn, landscaping, etc.
\360
35
Calculate the total area to be cleared, graded, fllled,
excavated, and/or compacted for proposed development
project. lnclude in this calculation the area to be cleared for:
sq/ft
sq/ft
sqift
sq/ft
lndicate Total Volumes of Proposed:
(lncludes BMP T5.13 Fill Volume)
Answer the following two questions related to
conversion of native vegetation:
Does the project convert % acres or more of
native vegetation to lawn or landscaped areas?
Circle: Yes
Circle: Yes
lJ tv L$ 15,
2021 iiAPR 22
stormwater calc worksheel QR code REV.5/31/2019 _t
LAND DISTURBING ACTIVITY. CONVERSION OF NATIVE VEGETATION. AND VOLUME OF CUT/FILL
@
lmperviout suiace is a hard surface that either prevents or slows the entry of water into the soil as under natural
conditions prior to development. A hard surface area which causes water to run off the surface in greater
quantities or at an increased rate of flow from the flow present under natural conditions prior to development.
Common impervious surfaces include, but are not limited to roof tops, walkways, patios, driveways, parking lots
or storage areas, concrete or asphalt paving, gravel roads, packed earthen materials, and oiled, macadam or other
surfaces which similarly impede the natural infiltration of stormwater'
)bt
qblp
Total ExistingTotal New
{-)
)
sq/ft
I
STORMWATE M
tft
tft
tfi
/ft
tft
sqfft
LATIONS - I JS SIIRFACFCALCU
sq/n
.sq/ft
D;iveway, parking, roads, etc
Other
EXISTING
Structures (all roof area)
Sidewalks
Patios
Solid Decks
(without infl ltration below)
Driveway, parking, roads, etc
Other
NEW
Structures (all roof area)
Sidewalks
Patios
Solid Decks
(without infiltration below)
Divide the total existinq
impervious surface above by the
size of the parcel and convert to
a percentage
Does the site have > 35% or more
existinq imDervious surface?
++no
+
yesF
The proposal is considered redevelopment Answer
questions in Figure 2.4,2. Flow chart for
Redevelopment to determine project size (next page),
The proposal is considered new development. Answer
questions in Figure 2.4.1 Flow Chart for New
Development to determine project size lnext page).
NT SIGNATURE By signing the stormwater Calculation Worksheet. I as the applicant/owner attest that the information Provided herein
knowledge. I also certify that this application is being made with the fult knowledge and consent of all owners
aDaA
(oArE)PESENT
d correct to the best of m
of affected proPertY
is tru
slotuter €lc wo.ksh6€l QR @de - REV. 5/31/2019
b
o
TOTAL NEW + TOTAL EXISTING' sq/ft 'This amount will be used lo check total lot coverage.
DEvELOPMENT v. REOEVELOPMENT
- Applicants for "small" projects must comply only with Minimum Requirement #2-Construction Stormwater Pollution Prevention.
please submit the Small Project Cenification (Worksheet "s). The proponent is responsible for employing the 12 Elements to control
erosion and prevent sediment and other pollutants from leaving the site during the construction phase of the proiect. Pick up the
Construction Stormwater Pollution Prevention (SWPPP) Best Management Practices (BMPs) Fact Sheet.
- Applicants for "medium" projects-those that must meet only Minimum Requirements #1 through #5 must submit Worksheet A1
and 81, a stormwater site plan and a construction stormwater pollution prevention site plan (See Reference A1A and B1A for
guidance).).
- "Large" projects-those that must meet all 9 Minimum Requirements- must submit Worksheet A1 and 81, a stormwater site plan
and a construction stormwater pollution prevention site plan (See Reference A1A and B1A for guidance). Large projects also may
require engineering. See Worksheet L to determine additional large project requirements.
WorkheetAl
Medium & Large Proiect Report
Minimum Requirement # 1 : Preparation of Stormwater Site Plan
Com the following:
Submit a site plan demonstrating the project. Refer to REFERENCE A1A for examples of Best Management
Practices (BMP's) thatyoucanuse. Rememberthatall site plans submitted forthe project must be consistent
and accurate.
Describe both existing and proposed site conditions for the following items as applicable in the space below each
bullet point. Attach additional pages if needed.
we
5
Minimum Requirement # 2 : Constru on Stormwater Po ution Prevention Plan SWPPP
A SWPPP is designed to be a stand-alone document that addresses !9!SUUEE!! stormwater management concerns. This
document is required to be kept by the contractor performinB the work at the jobsite for reference and update during
the life of the project. Construction BMP'S must be indicated on the stormwater site plan. REFERENCE B1A includes
diasra
d ms of common BMP's that may be used on the site plan.
My completed SWPPP (WORKSHEET 81 or equivalent) is included in this application packet!
Minimum Requirement # 3 : Source Control of Pollution (not construction related)
The intent of source control is to prevent stormwater from coming in contact with pollutants. Source control BMPs
can be operational or structural in nature. A roof over a material storage area is an example of a structural source
control BMP Washing your vehicle on the lawn rather than in the street is an operational BMP This requirement
is Benerally not applicable to Slngle Family Residences (SFRs); however, ways to minimize pollution from moving
downstream should be considered during the design phase of every project. Specifications on standard source control
BM ps that are applicable to various commercial and industrial-type facilities can be found ln Volume lV of the 2014
Stormwater Management Manual for Western Washington (SWMMWw) (continued on page 2).
{n ero
.ELEM
, vr- Colncr
74
page 1 of 6
{
May 21 2021
May 24 2021
BLD2021-00253
d
Minimum Requirement # 3 :source Control of Pollution (continued from page 1)
Check one of the following boxes that best represents your project with regards to fMR #3.
My project is not a StR and after reviewing Vol. lV of the SWMMWW I have determined that this MR is not
applicable because of the following reason:
My project is not a SFR and after reviewing Vol. lV of the SWMMWW I have determined that the following source
control BMPs are applicable to my project and shall be incorporated into the project design and operation.
My project is a Single Family Residence (SFR) and after considering operational and structural measures to prevent
stormwater from coming in contact with pollutants, I have,
tr determined this MR to not be applicable. ff made appropriate adjustments to my project.
page 2 of6
WorlsheetAl
Medium & Iarge Project Report
i
l_
\,
1I N L-;
WorkheetAl
Medium & Large Project Report
Minimum Requirement # 4 : Preservation of Natural Drainage Systems
Creating new drainage patterns results in more site disturbance and more potential for erosion and sedimentation during
and after construction, to the maximum extent possible, proponents must 1) maintain the natural on-site drainage
pattern and concentrated discharge location at the downstream property boundary and 2) prevent erosion at and
downstream of the discharge location.
NOTE: All outfalls require energy dissipation. See Table 4.5,1. in Vol. V of the SWMMWW for minimum design standards
for rock protection at outfalls,
Choose the option below that best describes your project:
The project site does not currently have any intermittent, seasonal, or continuous concentrated water
moving across any part of the property and the proposed improvements to the site will not create new
concentrated flow paths or not discharging to existing drainage systems.
The project site has existng concentrated flow drainage systems and outfalls. (NOTE: These items must
be graphically shown on the Site Plan or equivalent, to includei type, slope, dimensions, channel lining,
direction of flow, buffer, etc.) select below how it will be addressed.
This pro.iect will not alter the existinB drainage system in any way. lf the existing outfall(s) show
signs of erosion and scour, energy dissipation measures will be installed or improved upon.
Construction activity of any kind will not occur within at least 10 ft. of the edge of the channelized
flow. BMp C1O2: BUFFER ZONES will be implemented durinB the life of the project to include visible
flagging or other demarcation technique.
The existing concentrated drainage system traversing the property will be impacted as part
of this project, as described in the space below and shown on the site plans. Engineering
calculations are required that show the altered drainage design can accommodate the existing
flows and the added runoff contributed by the project.
page 3 of6
tr
tr
Minimum Requirement # 5 : On-site Stormwater Management
On-site stormwater management techniques shall be implemented where possible to accommodate the permanently
added stormwater runoff being generated by development. Some on-site stormwater management techniques provide
better stormwater detention and treatment than others; however, they are not always appropriate for use due to varying
individual site characteristics. Therefore, techniques are presented to applicants on the next pages in a hierarchical order
and shall be considered for use in the order listed. The first technique on the list that is determined to be possible shall
be implemented. See WoRKSHEET C to determine which techniques are feasible.
Runoff from developments occurring in drainage basins that drain directly or indirectly to a creek require a higher level
of stormwater management, thus, the techniques are presented in three lists below:
All properties will be in one of these three categories:d My project is located in a drainage subbasan that
drains to directly or indirectly to freshwater.
PROCEED to Page 5 to use LIST #1,
My Project will discharBe to a subasin draining to
salt water, Dosewallips River, or Hoh River.
PROCEED to Page 6 to use LIST #3.
My project is a large pro.iect. Refer to Worksheet [. lf full dispersion isn't feasible, use LtsT #1
(List g2 and List #1 are the same except raingardens are not permitted in List #2).
page 4 of 6
WorksheetAl
Medium & Large Proiect Report
tr
May 21 2021
N
|!1r)lIN
.,.Workheet 81
Construction Protection: Medium and Large Projects
(Slll/PPP: Stormwater Pollution P'revention Planl
Submit a site plan demonstrating the construction protective measures or best management practices that will
be used for the project during the construction phase.
Refer to REFERENCE B1A for exa m ples of Constructio n Best Management Practices (BMP's) that you can use. The
activities that take place during construction are the highest risk for stormwater problems such as erosion and
sediment control (you may need to provide an additional site plan with greater detail for stormwater features. lf so,
make sure it is consistent with the primary site plan. Remember that all site plans submitted for the project must
be consistent and accurate).
Element 1: Preserve Vegetation / Mark Clearing Limits
The goal of this element is to preserve native vegetation and to clearly show the limits of disturbance
Cho ony of the following that opply:
The perimeter of the area to be cleared shall be marked prior to clearing operation with visible flagging, orange
plastic barrier fencing and/or orange silt fencing as shown on the SWPPP site plan. Vehicles will only be allowed
in the a reas to be graded, so no compaction of the undeveloped areas will occur. lf this option is selected check
the BMPS you will use below:
C10I Preservine Natural
Vegetation
Cl02 Buffer
Zones
CI03 Hieh Visibilitv
Fence
existing site conditions, property
not covered by hard surface at the end of
Post-Construction Soil Quality and Depth.
Cl07 Construction
Road / Parkins Area
Stabilization
It is necessary to disturb the entire property during this project due to
constraints, and proposed design, I understand that all disturbed land
the project is subject to soil amendment requirements per BMP T5.13
The site was cleared as part of clearing activity that is subject to an enforcement action and will be re-vegetated
Restoration may be necessary to comply with Critical Area Regulations or stormwater requirements. Buffer Zones-
BMP C1O2 may apply if Critical Areas exist on-site and buffer zones shall be protected.
Element 2 : Construction Access
The goal of this element is to provide a stabilized construction entrance/exit to prevent or reduce or sediment
track out.
Choose one ol the following:
The driveway to the construction area already exists and will be used for construction access, All equipment and
vehicles will be restricted to staying on that existing impervious surface. lf sediment is tracked off site, the road-
way will be cleaned thoroughly at the end of each day.
A stabilized construction entrance will be installed prior to any vehicles entering the site, at the location
shown on the SWppP site plan. lf sediment is tracked off site, the roadway will be cleaned thoroughly at the end
of each d7y, lf this option is selected check the BIYIPS you will use below:
A Clo5Stabilized [[ ctoawh""l
Construction Entrance / Wash
Exit
page 1 of 6
r
d
)i
!'\
1I N
This ment does not opp ty to my proiect becouse (check ony thot apply):
Site is mildly sloped (<5%),
There are no individually sloped sections greater than 10%,
The bulk of the project is scheduled to occur during dry season (May 1-Sept 30)
Element 4: Sediment Control
The goal of this element is to construct sediment control BMPs that minimize sediment discharges from the
site.
Select one of the two statements dpplicable to the proiect.
The site has already been stabilized and re-vegetated,
Sediment control BMPs shall be placed at the locations shown on the SWPPP Site Plan. lf thls option is selected
check the BMPS you will use below:
Worksheet 81
Construction Protection: Medium and Large Projects
(SWPPP: Stormwater Pollution Prevention Plan)
d C233 Silt Fence I-l t1235 Watttes
C232 Gravel Filter trBerm SIEP
Element 5: Stabilize Soils
The goal of this element is to stabilize exposed and unworked soils by implementing erosion control BMPs.
Selegtd one of the three statements applicoble to the proiect.
My proiect will ensure the following:. Soiistockpiles will be located within the disturbed area shown on the SWPPP Site Plan.
. Soil excavated for the foundation will be backfilled against the foundation and graded to drain away from the
build ing.
. No soils shalt remain exposed and unworked for more than 7 days from May 1to September 30 or more than
2 days from October 1to April 30.
. Once the disturbed landscape areas are graded, the grass areas will be amended.
. All stockpiles will be covered with plastic or burlap if left unworked.
This element &qll-! opply to my proiect because:
My proiect must implement specific BMP's to ensure compliance. (Check BMP'S you will use on the next page),
Element 3: Control Flow Rates
The goal of this element is to construct retention or detention facilities when necessary to protect properties
and waterways downstream of development sites from erosion and turbid discharges.
C23l Brush Barrier
trd
tr
tr C234 Vegetated
tr
page 2 of 6
iC'lIN
Worksheet Bt
Construction Protection: Medium and large Projects
(SWPPP: Stormwater Pollution Prevention Planl
n crz2 Nets & Blankets f] crz+ soaaing !
tr Cl23 Plastic Coverins C125 Topsoil / E C140 Dust Control
Composting
Element 6: Protect Slopes
The goal of this element is to design and construct cut-and-fill slopes in a manner to minimize erosion.
Select one of the two statements opplicoble to the proiect.
No cut slopes over 4 feet high or slopes steeper than 2 feet horizontal to 1 foot vertical, and no fill slopes over
4 feet high will exceed 3 feet horizontal to l foot vertical. Therefore, there is no requirement for additional
engineered slope protection.
The above checkbox is not checked. My submittal is designed by a licensed geologist to protect slopes. Based on
the licensed professionals recommendation (please attach their evaluation), the following BMP's will be used:
Tc c C205 Subsurface f- c2o7 Check Damst__J
Cl20 Temoorarv &
Permanent Seeding
Seeding
C204 Pioe SIooe Drains
C13l Gradient
Terraces
Drains
C206 Level Spreader tr C208 Triangular Silt Dike
(Geotextile-Encased Check Dam)
Element 7: Protect Permanent Drain lnlets
The goal of this element is to protect storm drain inlets during construction to prevent stormwater runoff from
entering the conveyance system without being filtered or treated.
Select one of the three stotements opplicable to the proiect
tr The site has open ditches in the right-of-way or private road right-of-way.
There are no catch basins on or near the site
pa8e 3 of6
d
l-l ctzt Mulchine
I_l czrs wuttles
Catch basins on the site or immediately off site in the right-of-way are shown on the SWPPP Site Plan. Storm drain
inlet protection shall be installed. lf this option is selected check the BMPS you will use below:
[-l t::zo Srorm Drain Inlet Protection
tr
Element 8: Stabilize Channels and Outlets
The goal of this element is to design, construct, and stabilize on-site conveyance channels to prevent erosion
from entering existing stormwater outfalls and conveyance systems.
one oI the three stotements opplicoble to the proiect.
Construction will occur during the dry weather. No storm drainage channels or ditches shall be constructed either
temporary or permanent.
There are no existing or proposed stormwater conveyance channels on the project site.
A wattle shall be placed at the end of the swale to prevent erosion at the outlet of the swale. lf this option is
selected check the BMPS you will use below:
Select
d
l-l e :o: Chrnnel Linirrg l-l
Element 9: Control Pollutants
Workheet 81
Construction Protection: Medium and Large Projects
(SWPPP: Stormwater Pollution Prevention Planl
I-l czos outlet Protection [-l C235 WattlesC207 Check Dams
The goal of this element is to design, install, implement and maintain BMPS to minimize the discharge of
pollutants from material storage areas, fuel handling, equipment cleanrng, management of waste materials, etc.
fhis eiement dgg!!q! opply to my Woject becouse (circle ony thot dpply - lf any box is unchecked this element applies.
There will be no concrete work,
There will be no sawcutting work,
M
d
l-l lhere witt be no heavy equipment associated with this project,
El rn"r" will be no pressure washing, equipment maintenance or dewatering
lf one or more of the checkboxes above are unchecked. Any and all pollutants, chemicals, liquid products and other
materials that have the potentialto pose a threat to human health or the environment will be covered, contained, and
protected from vandalism. All such products shall be kept under cover in a secure location on-site. Concrete handling
shall follow BM P C151 C154. lf this option is selected check the BMPS you will use below:
C15 i Concrete Handling C 152 Sawcutting and Surfacing
nP
There will be no hazardous materials on-site,
There will be no fertilizer or pesticide application,
C153 Materi al Deliverv. Storase, and Containment C 154 Concrete Washout Area
page 4 of 6
tr
tr
Wor{sheet 81
Construction Protection: Medium and Large Projects
(SWPPP: Stormwater Pollution Prevemion Plan)
Element 10: Control De-watering
The goal of this element is to handle turbid or contaminated water from dewatering (removal of water)
separately f rom stormwater.
5e ne of the two stotements opplicoble to the proiect
No dewatering ofthe site is anticipated,
Dewatering ofthe site is anticipated. If this option is selected check the BMPS you
will use below:
C203 Watq ia$E C236 Vegetated Filtration ! Czoe Level Spreader
Element 11: Maintain Best Management Practices
The goal of this element is to maintain and repair all temporary and permanent erosion and sediment control
BMPs to assure continued performance.
Describe the steps you will take:
Best Management Practices or BMPs shall be inspected and maintained during construction and removed within
30 days after the County lnspector or determines that the site is stabilized, provided that they may be removed
when they are no longer needed.
Element 12: Manage the Project
The goal of this element is to ensure that the owner and those performing the site work comply with the
SWPPP and properly coordinate to ensure that all BMPs are deployed at the proper time to achieve full
compliance with county regulations throughout the project.
The SWppP will be implemented at all times, lf applicable to the project, erosion control BMP5 will be
implemented in the following sequence:
L. Mark clearing limits
2. lnstall stabilized construction entrance
3. lnstall protection for existing drainage systems and permanent drain inlets
4. Establish staging areas for storaBe and handling polluted material and BMPs
5. lnstall sediment control BMPS
6. Grade and install stabilization measures for disturbed areas
7. Maintain BMPs until site stabilization, at which time they may be removed
page 5 of 6
t
Element 13: Protect Low lmpact Development BMPs
The goal of this element is to protect permanent stormwater mana8ement BMPs from siltation and compaction
during construction. The permanent stormwater management BMPs used for runoff from roofs and other hard
surfaces include: full dispersion, roof downspout full infiltration or dispersion systems, perforated stubout
connections, rain gardens, bioreten6on systems, permeable pavement, sheetflow dispersion, and concentrated
flow d ispersion.
Metlods that will be used to protect permanent stormwater management BMPs include:
f?r Sequencing the construction in a fashion to install these permanent BM Ps at the latter part of theU construction gradingoperations,
n Excluding equipment from the BMPs and the associated areas,
5 Using the erosion and sedimentation control BMPs listed below to protect facilities such as drywells,
lJ raingardens, permeable pavement, or bioretention from accumulating sediment during construction and
before site restoration. lf this option is selected check the BMPS you will use below:
l-l c toz Buffer Zone
l-l cz3: silt r"n."
n czgt Brush Barrier
[-l ctor Hish visibilitv Fence
C234 Vegetated Strip
Othertr
Applicant or Representative Signature fuz*'
page 6 o[6
Worksheet 81
Consffuction Protection: Medium and Large Prcjects
(SWPPP: Stormwater Pollution Prwention Plan)