From: VMorrisCS@aol.com
Sent: Tuesday, December 21, 2010 12:22 PM
To: dwjohnson@co.jefferson.wa.us
Cc: ascalf@co jefferson.wa.us; shoskins@co.jefferson.wa.us; peckassoc@comcast.net
Subject: Fwd: Pleasant Harbor SEIS
Attachments: RE: Pleasant Harbor Priority Work Items Status Report: 11/24/10 (21.7 KB)
David
Is the County accepting Garth's 12/16/10 e-mail reply (forwarded below) as the final word re: the Pleasant Harbor MPR
construction start date (and thus the time available/required for the SEIS and land use approval process), or do you (or Al)
plan to follow up with him for final clarification?
Vicki
Vicki Morris Consulting Services
7732 18th Avenue NE
Seattle, WA 98115-4426
206.522.8057
FAX: 206.523.4648
Michelle Farfan
From:
Sent:
To:
Cc:
Subject:
M. Garth Mann
President & C.E.O
P: 403-256-4151
M:403-899-9222
F: 403-256-6100
7370 Sierra Morena Blvd. S.W.
Calgary, Alberta
T3H 4H9
www. statesmangroup.ca
Garth Mann <GarthM@statesmancorporation.com>
Thursday, December 16, 2010 7:43 PM
David W. Johnson
Al Scalf; Stacie Hoskins; peckassoc@comcast.net; VMorrisCS@aol.com;
Scott@benderllc.com
RE: Pleasant Harbor Priority Work Items Status Report: 11/24/10
-----Original Message -----
From: David W. Johnson [mailto:dwjohnson@co.jefferson.wa.us]
Sent: Thursday, December 16, 2010 10:43 AM
To: Garth Mann
Cc: Al Scalf; Stacie Hoskins; peckassoc@comcast.net; VMorrisCS@aol.com; scott@benderllc.com; David W.
Johnson
Subject: RE: Pleasant Harbor Priority Work Items Status Report: 11/24/10
Garth,
I'm concerned with your item #7 in which you state, "Because of the Water Rights negotiated by Tom McDonald
and Scott Bender, we need to start construction no later than June 2010." Do you mean 2011 i ypo...should read
that some progress in construction is important to commence by June of 2011 or 2012? As I tried to convey in my
letter of December 13, and illustrated with attached process graphics, no construction can occur before building
and development permits are approved and issued, and that can't happen without a completed SEIS and signed
Development Agreement. It is unrealistic to expect construction to start no later than June 2011, since it is
unlikely the SEIS will be finalized by then. 2012 is more realistic in terms of the scope of what needs to be
accomplished before construction can start. If your water rights are based upon construction by June 2011, 1
suggest you consider requesting an extension to those terms. I have discussed this with Scott Bender and he is
aware of this. The reports are close to completion. There should be a cohesive effort now to work towards the
summer of 2011 to start Pleasant Harbor Resort.
From: Garth Mann [ma iIto: Garth M@statesmancorporation.comI
Sent: Thursday, November 25, 2010 12:29 AM
To: VMorrisCS@aol.com; peckassoc@comcast.net; jcooke@perkinscoie.com; David W. Johnson
Cc: NProft-Carlson@gmharchitects.com; scott@benderllc.com; vjperrone@perroneconsulting.com;
hresvelt@earthlink.net; consultares@aol.com; mikeread@tenw.com; wwright@geoengineers.com;
jpurdy@geoengineers.com; bmerryman@msn.com; jim@blackrockllc.net; rsteffel@Environcorp.com; Milton
Kiehlbauch; mwong@susa.ca; tmcdonald@cascadialaw.com; don@pleasantharbormarina.com;
diane@pleasantharbormarina.com
Subject: RE: Pleasant Harbor Priority Work Items Status Report: 11/24/10
Regarding the Status reports:
Since the October status Reports, a number of issues have now been resolved pertaining to a completed status
for the following:\
1) The Marina Lands and the Adjoining Properties between the Marina and Black Point Road.
Natalie and Craig have simplified the layout from all aspects of the required Road Networks, the Building
Footprints to satisfy the SMP, the Fire Code Issues for access/egress and staging areas to fight a fire, as well as
the Long and Short Term Parking, the surface water issues and the stream culverts, and the resultant reduction
of the Building impervious areas for Alternative 3.
2) The MOU's have been completed except for Brinnon School, and thanks to Don and Diane Coleman these are
being forwarded to Vicki
3) The Ordinances should be Ready this week for inclusions by JT Cooke (see Natalie and Craigs information).
4) The Tribes have been surveyed and are very pleased with the results. We have asked that they deal with the
issue internally as to the Tribe most attributable to managing the Conservation Easement. The fencing issue
brought up by Pointe No Point Council cannot be constructed on highway 101 ... but could be placed on the north
property line of the Golf Course land areas to control only the Elk Herd.
Craig will show on his site plan the sound Attenuation fencing areas placed sporadically along the south side of
the 12 foot wide pedestrian access to the Marina.
The Habitat Corridor should be in collaboration with Craig Pecks recommendations.
5) Don Coleman is doing a collaborative investigation with ALL Owners those with Harbor Access to meet and to
set up a council for managing the Harbor Waters.
6) The Golf Course design is nearing completion with Craig and Garth contemplating the fairways and protecting
golfers and the wetland areas by retaining healthy trees between fairways. and adding a SPILL Stream between
the Reservoir and the Easterly Wet -Land.
7) The Reports are almost done now for the Waste Water Treatment Plant as well as the reservoir, as a self
managed utility including the electrical requirements. for the Resort. Because of the Water Rights negotiated by
Tom McDonald and Scott Bender, we need to start construction no later than June 2010.
8) Please expect a package of information from Natalie and Craig and Rick, others will now be able to complete
their report before next months Status Reports.\
G
From: VMorrisCS@aol.com [mailto:VMorrisCS@aol.com]
Sent: Wed 11/24/2010 8:28 PM
To: Garth Mann; peckassoc@comcast.net; jcooke@perkinscoie.com; dwjohnson@co.jefferson.wa.us
Cc: NProft-Carlson@gmharchitects.com; scoff@benderllc.com; vjperrone@perroneconsulting.com;
hresvelt@earthlink.net; consultares@aol.com; mikeread@tenw.com; wwright@geoengineers.com;
jpurdy@geoengineers.com; bmerryman@msn.com; jim@blackrockllc.net; rsteffel@Environcorp.com; Milton
Kiehlbauch; mwong@susa.ca; tmcdonald@cascadialaw.com; don@pleasantharbormarina.com;
diane@pleasantharbormarina.com
Subject: Pleasant Harbor Priority Work Items Status Report: 11/24/10
Garth et al.
Attached is the 11/24/10 status report for Priority Work items required in support of the Pleasant Harbor Master
Planned Resort Development Agreement, Zoning Ordinance, and SEIS. Several decisions were made since
the 10/25/10 status report was issued that have resulted in refinements to the Alternative 3 site plan. These
are nearing completion.
The 11/24/10 version of the status report now identifies the responsible team member for each task, and adds
tasks that were inadvertently not included in the original (1/13/10) list.
Please review the status of work products for which you are responsible, answer any Questions, respond to
Requests, and send me updates for inclusion in the next monthly status report (to be sent on or about December
23).
Thank you. Happy Thanksgiving to everyone (a belated greeting to those of you in Canada)!
Vicki
Vicki Morris Consulting Services
7732 18th Avenue NE
Seattle, WA 98115-4426
206.522.8057
FAX: 206.523.4648