Thank you, Karen for the draft and Garth for your thoughtful review and comments.
We've discussed the area of the SEIS, and it's clear that the development regulations (DRs)will apply to the Pleasant
Harbor Master Planned Resort in its entirety, although the marina area benefits from the existing binding site plan
(BSP). Willyou recommend the BSP be written into the DRs so that the uses and footprints are limited to those in the
BSP? I understand we aren't addressing the environmental impacts because the BSP is already approved, but the DRs
will need to address development in the entire MPR and there is interconnection between the areas. For example,
o Three of the streams in the BSP area are in the MPR, and what has been proposed is consistent with the
BSP. What if the developer proposes something in the future that is not on the BSP? Will we have DR's to go
by?
o The zip line is proposed to connect in the marina area.
Thanks!
Saza.4,, *o4/&4t
Planning Manager, Jefferson County Department of Community Development
521 Sheridan Street * Port Townsend, WA 98368
Phone 360-379-4453 * Fax 360-379-4451
shoskins @ co. iefferson.wa.us
Jefferson County DCD Mission: To preserve and enhance the quality of life in Jefferson County by
promoting a vibrant economy, sound communities and a healthy environment.
All e-mail sent to this address will be received by the Jefferson County e-mail system and may be subject to Public Disclosure under Chapter 42.56 RCW
L
5r'! SaVf PAPER - Pleose do nol print this e-moil unless obsolutely necessory
From: Garth Mann [mailto:GarthM@statesmancorporation.com]
Sent: Friday, March 29,201312:11 PM
To: 'Swenson, Karen'; David W. Johnson; Stacie Hoskins; don@pleasantharbormarina.com; peckassoc@comcast.net;
amackie@perkinscoie.com;'Natalie Proft-Carlson';'Michael Read'
Cc: Schipanski, Rich
Subject: RE: Pleasant Harbor SEIS Chapter 2 - Preliminary Draft for Internal Review
Happy Easter Karen
I think you have done well with your Chapter 2 lnternal Review:
Some suggestions
1) Corporate Name for the Applicant is not the Statesman Group of Companies
Please use: Pleasant Harbor Marina and Golf Resort LLP.
1
2) Typo (last line of first para of 2.1) ..was lssued on November 27th, 2007
3) Craig Peck will confirm the numbers for our 2007 FEIS approval
4) lnteresting that Scoping is Optional for the SEIS. What if the County were to receive a similar application as ours?
Would this application be required to pursue the same Optional Scoping expense?
5) Please read the report from Geo-Engineers where they describe 5 streams which are mainly inactive except the
very wet season. Two are outside of the SMP set-backs
6) Natalie provided to you the up-dated chart for the Alternatives including the break-down on the mix of product.
The largest Terrace Building has 191 suites that are short term 1 and 2 bedroom.
Terrace Building #2 has 90 suites
Terrace Building #3 has 53 suites
Terrace Building #4 has 53 suites
Natalie will confirm these numbers for you.
7) Natalie has designed the majority of the parking for Guests and Residents below grade. (Podium Style)
8) Stage 1: Phase 1: Add: Construct Wastewater Treatment Plant and The Reservoir (Kettle B)
Set up the Construction Camp, (East of WWTP and then we use the Staff Housing Building)
Phase 2: Add: Staff Housing and Maintenance Center
Start the clearing for the Golf Course and the creation of the Nursery
Stage 2: Phase 1:Add: Continue work on Golf Course
Phase 2: Add Golf Course Opens
9) 2.6 Separate Actions: Add: TREE-TOPPER Adventure with Zip Line; Euro-Bungy & Rock Climbing Wall
Family Fun Center located in the Maritime Building
10) Float Plane Dock: A substantial Shoreline Development Permit: Craig Peck to provide Permit details for the Float
Plane Dock
11) Benefits of Deferring Approval of the Proposed Actions:
**Michael Read: has worked with WDOT to mitigate the Transportation issues, and the road assignments and tratfic
calming.** NO external Views are impacted as a result of the Pleasant Harbor Resort...(Omit this clause since it is not
accurate)
"* NO lmpact on the Aquifer and Water Resources (See Reports and Permit where the Aquifer is not impacted at
all) (Zero-lmpact Bender Eng.)
Thank you for the quality report
M. Garth Mann
M. Garth Mann
President & C.E,O
P:403-256-4151
M:403-899-9222
F:403-256-6100
7370 Sierra Morena Blvd. S.W
2
Calgary, Alberta
T3H 4H9
www. statesmanqrou p. ca
From : Swen son, Karen [mailto : kswenson@eaest.com]
Sent: Tuesday, March 26,2013 11:18 AM
To: David W. Johnson; Stacie Hoskins; don@pleasantharbormarina.com; peckassoc@comcast.neU Garth Mann;
a mackie@ oerkinscoie.com
Cc: Schipanski, Rich
Subject: Pleasant Harbor SEIS Chapter 2 - Preliminary Draft for Internal Review
Dear Pleasant Harbor SEIS Team,
Here is a preliminary draft of Chapter 2 of the Pleasant Harbor Master Plan SEIS for internal review. A few comments are
in the margin, primarily regarding the WDFW access road realignment. lf the WDFW is included in the SEIS, additional
information will be added where noted, upon receipt from the applicant's team. lf the realignment is treated as a
separate action that will require separate environmental review, these notes will be deleted from the body of the
document and the WDFW access road will be addressed in the SEIS as shown in Section 2.6.
Please review the Word document and make any direct edits in Track Changes within the document. Also if you have
any specific comments regarding a sentence/paragraph, please insert those comments directly into the document as
well. Any other global comments or comments about the figures may be made via e-mail to me, with a cc to David
Johnson. Please also cc David Johnson when you send me your edits to the Word document.
Per the schedule, please complete your review in one week, by 10 am on April 2nd. At that point, we will consolidate all
the edits and comments and revise the document accordingly.
This fulfills Task 1 of Phase 2 of our contract. We are currently progressing through Task 2 and 3 of Phase 2 (Preliminary
Draft SEIS).
Thanks,