HomeMy WebLinkAbout053Michelle Farfan
From:
Sent:
To:
Cc:
Subject:
Attachments:
David W. J oh nson < djoh nson @co jefferson.wa.us >
Monday, October 21,20t3 2:08 PM
Barbara Moore-Lewis
David W. Johnson
RE: Monday 10/20
SEIS Deficiency Memo-CP-L0 21 13.pdf
Attached. Hopefulto have these items resolved by November L,2O!3
From : Barbara Moore-Lewis Ima ilto : mooreleb@gma il.com]
Sent: Monday, October 21,20L3 B:31 AM
To: David W. Johnson
Subject: Re: Monday 10/20
If you call me at 2, you'll have to call my cell 503 580 6430. Or you can call me at 3 at 360 796 0378
On Mon, Oct 21 ,2013 at7:45 AM, David W. Johnson <djohnson@cojefferson wrote
Yes.
From: Barbara Moore-Lewis [mailto:mooreleb@gmail.com]
Sent: Sunday, October 20,2073 9:14 PM
To: David W. Johnson
Subject: Monday 10/20
Call at2?
I understand that the marina office and deli is now being taken down. I'm also told they they plan to fill the
driveway between the building and the shore. Do they have permits to do this, particularly to change the grade
of the driveway? Does any of this depend on future changes to the binding site plan or the SEIS (or the SMA)?
1
Thanks. Barbara
XFINITY Connect
Page I of2
peckassoc@comcast.ne
I Font Size _
Outstanding items for Pleasant Harbor Draft SEIS
From : Karen Swenson <ks,venson@eaest.com>
Subject : Outstanding items for Pleasant Harbor Draft SEIS
To : Craig Peck (peckassoc@comcast.net) <peckassoc@comcast.net>
Cc : David W. Johnson (djohnson@co.jefferson.wa.us) <djohnson@co.jefferson,wa,us>, Rich
Schipanski <rschipanski@eaest.@m>, Kristy Hollinger <khollinger@eaest.com>, Karen
Swenson < kswenson@eaest.com>
Craig,
As requested during our conference call with Kitsap County yesterday, here is the list of outstanding items that will need be provided to EA to
complete the Draft SEIS for Pleasant Harbor:
1. Energy Demand Memo (short memo to accompanythe conceptual load spreadsheet previously provided by Hargis on 7-3-13)Hargis
Energy Supply Report/Memo from Scott Taylor at the PUD regarding transmission capacity and transformers on- and off-site PUD
Water Report Dwight
Technica I sewer report outlining the phasing of the WWTP including the onsite septic system for the
Maritime Village
Revised site plans to show the removal of the two 12-unit buildings in the Maritime Village area and any changes to Marina Access Drive
Revised impervious surface area calculations per the removal of the two 12-unit building in the Maritime Village area CP, Natalie
8. Any revisions to the Maritime Village building including commercial building square footage, height or building footprint (we understand
that the 24 units from the Harborview House and Reunion House will be shifted to the Maritime Village building but the overall unit
count for the project will remain the same)Natalie
9. Revised data tables from GMH Architects (Natalie) for Alternatives 1 and 2 indicatinB redistribution of parking (surface vs structured) in
the Maritime Village area due to the consolidation of buildings in this area Natalie
10, Map showing wellhead protection areas around the two existing wells and a list of restrictions in these areas (plus any correspondence
with DOH regarding written variances for paving and sanitary sewer forcemains)Dwight, CP
11. wtap showing revised SEIS site boundary to include 28-acre WDFW property (this map should indicate that this WDFW property is not
owned by the applicant)SEIS Boundary is new map - excludes BSP?
12. lmpactsofconstructionoftherealignedWDFWboatlaunchroad(includingoveralllength,conditionandgradeofexistingroadand
proposed road, and quantity of clearing and grading for proposed road)CP - thought covered in previous response
13, Revised phasing list (in Chapter 2 of the Preliminary Draft SElS) to indicate change in tlme of construction of the Maritime Village building
and the addition of the onsite septic system, as well as timing of the realigned boat launch road (Stage 1, Phase 1?)CP
14. Confirmation that Alternative 2 should be noted as the Preferred Alternative in the Draft SEIS (per Sandy Mackie's 5-23-13 memo).Karen?
15. EditstoSection3.land3.2fromCraigPeck(therestoftheeditsforthePreliminaryDE|SsectionswerealreadyprovidedbyCraigon6-6-
13).CP
16. Clarification/confirmation of what is allowed under the amended BSP (currently the SEIS lndlcates that redevelopment and renovation is
CP, David
2.
3,
4.
5.
6.
7.
Sewer Report
Tue, Oct 08, 2013 01:59 PM
Qt
hUMarvDw
within existing footprints only, but Craig added "or where shown on )
Page? of2
17. Clarification of compliance with the first part of BoCC 63(g) - "The developer shall commission a study of the number of jobs
expected to be created as a direct or indirect result of the MPR that earn 80% or less of the Brinnon area average median
income (AMl)." The 2012 Jobs Study, Summary of Pleasant Harbor lmpacts: Job Creation and Value Added to National
Economy, did not include salary levels of proposed jobs and/or comparison the the Brinnon AMl. Garth noted that "Aaron Goforth of
wright Johnson LLC would address the reports for accuracy and proposed salaries."
18. Revisions to the description of the proposal (Chapter 2) and the list of required permits due to the inclusion of the zipline, the removal of
the 2 structures in the Maritime Village area, and the inclusion of the realigned boat launch road in the proposal - the applicant can
revise Chapter 2 and the Fact Sheet of the Preliminary Draft SEIS accordingly, or EA can draft changes for applicant review
I believe this covers all the outstanding items that are needed to complete the Draft SEIS and to complete revisions due to changes to the
Please let me know if you have any questions.
Thanks,
Karen Swenson
EII
Karen Swenson, AICP
Senior Planner
2200 Sixth Avenue, Suite 707 | Seattle, WA 98121
206.452.5350 x 1716
kswenson@eaest,com
David
imageo02jpg
997 B
@
n