Due to the length of time completing technical reports, we've had to push the schedule for the Pleasant Harbor MPR
SEIS and Public Hearing further into the future. Please see the attached Timeline. Notice that the current proposed
releaseoftheSElswill betheWeekofJunegth,andthePlanningCommissionPublicHearingisnowscheduledforJuly
16th, which as it turns out, is when the Planning Commission is scheduled to be in Brinnon this year.
For those of you who are planning to attend the Public Hearing, please make a note of this new date
David Wayne Johnson - LEED Green Associate
Associate Planner - Port Ludlow Lead Planner
Department of Community Development
Jefferson County
360.379.4465
Mission: To preserve and enhance the quality of life in Jefferson County by promoting a vibrant economy,
sound communities and a healthy environment.
5r{ SOUE PAPER - Pleose do not print this e-moil unless obsolutely necessory
All e-mail may be consrdered subjed to the Public Records Ad and as such may be disclosed to a third-party requestor,
J*ff*rson County 0€f,6nment of Cornmunlty Developnrerrl
ffi5w UARH.'."....")',. 11,
B€ttcr gultdlflg Storts tlErr,
tIl 1t!4ri;r*rYr,I{:,{Id*ilfiif,l{4sf}r*lJ60rlrdax, ld*.:lc<.rr-iL,q.rw*rir
LEED
GREEN
ASSOCIATE
1
PLEASANT HARBOR SEIS PROCESS & TIMELINE (contingent upon accuracy of step l date)
PC = Planning Commission BoCC = Board of County Commissioners
20L4
* = Completed
revised April7th,2OL4
STEP WHO WHAT WHY WHEN
1.Applicant All Final Reports to Consultant For Production of Preliminary Draft SEIS April 14th
2 Consultant
Phase ll
Preliminary/Working Draft SEIS to County For County & Applicant Review and
comment April2l't
3 County Staff Review & comment due back to
Consultant
Ensure accuracy and readability May 5th
4 Consultant
Phase lll
Produce Final Draft lncorporate staff & applicant comments May 19th
*5 County PC meeting & BoCC Afternoon Briefing Opportunity to inform of upcoming
release, requirements, work schedule
and requirements
PC Meeting February L9th
BoCC - Monday Afternoons in
March 17th
6 County Notice of Availability, Press Release and
Notice of Public Hearing
To inform the public of availability Concurrent with Draft SEIS release
- Step 7
7 County &
Consultant
Publish Final Draft and release to public Public review for 45 day public
comment period
June 9th
9 County &
Consultant
Open House & PC Public Hearing
(Brinnon School Gym)- after release of
the Draft but before end of comment
period
Present Project, Staff Report & Take
Public Testimony and written comments
July 16th
10 County Staff Review of public & agency
comments
Compile comments to address in Final
SEIS
45 days after release of Draft SEIS
July 23'd
1L Consultant
Phase lV
Produce FinalSElS lncorporate staff, agency and public
comment - release to public - seven
days before BoCC action. 60 day notice
to Commerce - intent to amend UDC
prior to BoCC decision
Oct 13th
72 County PC Recommendation to BoCC Required per JCC 18.45.090
13 County BoCC deliberations to accept PC
recommendation or hold Public Hearing
Required per JCC 18.45.090 TBD
t4 County BoCC Public Hearing or instruct staffto
draft ordinance
Required per JCC 18.45.090 TBD
15 County BoCC decision to adopt Development
Agreement & regulations
Required per JCC 18.45.090 TBD
Prepared by Project Planner, David Wayne Johnson
TBD