5 February 2015
M Garth Mann sF,ntvia e-mall
Statesman Group of Companies
U.S. Head Office
9300 E. Raintree Drive, Suite 100
Scottsdale, AZ 852690
Corporate Head Offce
7370 Siena Morena Blvd,. SW
Calgary, Alberta, Canada T3H-4H9
Subject Pleasant Harbor FinalSE|S
EA Project Number 1501601
Dear Dr. Mann:
As indicated in our December 8, 2014 conespondence, "a Final EIS scope of work and budget
agreeable to Statesman, Jefferson County and EA will be processed following completion of the
Draft SEIS comment period on January 5,2014." The Draft SEIS comment period is complete
and EA has received the comments.
Accordingly, EA has prepared the following scope of work and budget proposalfor Phase 4 -
Complete and lssue the Pleasant Harbor FinalSupplemental ElS. EA is providing
environmental review services for the Pleasant Harbor Project in phases as follows: Phase 1 -
Projectlnitiation; Phase2 -Prcliminary DTafrSEIS;Phase3 -Complete andlssueDraftSE/S;
and, Phase 4 - Complete and lssue Frnal SE/S.
EA has completed Phases 1,2 and 3 of our SEPA environmental review services for the
Pleasant Harbor Prqect (Phase 3 concluded with issuance of the Draft SEIS on November 19,
20'14, and our ailendance of the Open House and Planning Commission meeting on December
3,2014).
67 individual comment letters were received on the Draft SEIS. A number of these comments
will require detailed responses in the Final SEIS, including input ftom the Pleasant Harbor team.
ln general, the primary environmental issues raised during the Draft SEIS comment period that
will require input from the Pleasant Harbor team include:
. aquifer recharge/drawdown - Bender Consuhing. kettleArvetlands/animals conditions - GeoEngineerso traffic volume and safety - TENWo tax revenue and public costs - Micfiael K Evans. stormwater/water quality/Hood Canal - Craig Peck, Bender Consulting and H.R. Esvelt
Eng.
The following provides our scope of work and budget estimate for Phase 4 - Complete and
lssue Final SEIS of the SEPA environmental review process for the Pleasant Harbor Project.
The Phase 4 scope is intended to cover services through the issuance of the Final SEIS. lf the
schedule is substantially delayed for reasons beyond EA's control, a budget adjustment could
be necessary.
Scooe of Work
Task 1: Review all letters and written comments received on the Draft SEIS; assign team
responsibilities for input to responses; and, distribute to the team to obtain technical responses.
Task 2: Review transcript from County Commissioners meeting; assign team responsibilities for
input to responses to comments, and distribute to the team to obtain technical responses. lt is
anticipated that many of the comments from the meeting can be addressed by referring to
responses to written comments.
Task 3: Coordinate with County regarding Sheriff and Fire Dept. impacts and status of MOU's.
Task 4: Coordinate with the County and the technical team regarding preparation of responses;
obtain, review and incorporate comment response input into the 1$ Preliminary Final SEIS.
Task 5: Directly prepare the balance of responses to comments.
Task 6: As wananted by the Draft SEIS @mments, revise sections of the Draft SEIS in
highlights or track-change to clearly indicate updates since publication of the Draft SEIS.
Task 7: Prepare a summary matrix of all comments per County guidelines.
Task 8: Produce 1$ Preliminary Final SEIS for submittalto Jefferson County for review and
comment (submit electronically in PDF and Word versions).
Task 9: Review the County's 1"t round of comments on the Preliminary Final SEISI
Task 10: Coordinate with Jefferson County and the technicalteam regarding preparation of
revisions based on comments received; obtain, review and incorporate changes into the 2M
Preliminary FinalSElS.
Task 11: Prepare the balance of revisions in a 2nd Preliminary Final SEIS.
Task 12: Produce 2nd Preliminary Final SEIS for review by Jefferson County.
Task 13: Coordinate with Jefferson County regarding final review of the document and obtain
any further comments.
Task 14: Make edits to the Final SEIS based on finalcomments from Jefferson County and
prepare the Final SEIS for issuance by Jefferson County.
' Assumes comments from Jefferson County are editorial in nafure and do not requirc new technical analysis or
SEIS Altematives.
Contnct Amendment
Pleasant Harbor SEIS
2
Task 15: Print and produce CDs of the Final SEIS for issuance by Jefferson County (it is
assumed that EA will print seven hard-copies of the document and will burn 50 CDs).
At the end of this phase, the Final SEIS will be issued by Jefferson County. This scope of work
and budget covers our service through issuance of the Final SEIS.
Should an appeal of the adequacy of the Pleasant Harbor SEIS be filed, EA staff is available to
assist the County at the appeal hearing. We will bill for our services on a time and materials
basis, at the hourly rates listed below.
Schedule
Based on our cunent scfredule, we assume that the 1d Preliminary Final SEIS would be
submitted to the County in mid- to lat+. March. This submittal is contingent upon receiving draft
technical responses from the technical team in early March, and upon receiving an updated
fiscal analysis by the end of February. The actual Final SEIS publication date will depend upon
Jefferson County's review schedule and the extent and nature of their comments on the
preliminary documents.
Budqet Estimate
We have prepared a not-to-exceed budget estmate for Phase 4 based on the assumptions and
scope of work outlined above. This budget covers costs for Phase 4 services provided by EA,
and is based on EA's 2015 Fee Schedule. This proposed amendment will utilize the terms and
conditions of the February 11,2013 contract.
PHASE 4. PREPARE AND ISSUE FINAL SEIS
EA BUDGET BREAKDOWN2
Other Rates
Auto mileage, per mile $0.565
ln-house photo copies, per page $0.15
Handling charge on subcontractors and expenses 1006
Rates are gmd hrough December 2015.
2 Budgct docs not include costs associated with other tearn membcrs.
Rich Schipanski $205 24 $4,920
$9s 176Kristy Hollinger $16,720
lGthryn Cemy-Chipman $70 12 $840
$22.480Total
Production Costs $400
$22,880
Confract Amendment
Pleg.sg,nt Harbor SEIS
3
Name Hourlv Rate TotalHours Total Budqet
Please don't hesitate to contact us should you have any questions.
Sincerely,
EA Engineering, Sclence, and Technology,lnc., PBC.
I
Rich Schipanski, Program Manager
CC: David Johnson, Jefferson County
{(/^"-, /kr*-
Kristy Hollinger, Project Manager
Authorization provided lhisT day of (ck*,T,201 5
Statesman Group of
Garth
Con/ract Amendment
Pleasant Harbor SEIS
J)r,r*;d*.
-Suby/ fr; z/tra,,u,irr1 frlt,t"aty 7 /ri /,trL
P,r* S l,'qans l,i f/wf /le po,:taa t ftucc/q/a
/orzdtku,rraT Turrrtra /tl azln,^tk./f ;
, ,./'f,rlrri^ fr4 fue, fr$d6:u(, [*n al,fiur"l
' '/ 'ltottoo' ':, /ui{tr(f< r( Ailu', (k
br+f J rts
-l . , - ) / n
^ ,;/ 1 ,tcsy'lrn a /,2. /raa,'t bitru.( ,
7* /r. f"*fru l, //tc ,'y.a r't/i'it<art ALun6nr- d,,c'{ o,
f ry,r/irt*"/
/"nqr.l'
67 dcfr,,4/ /,ttt k/,nr
4
oaa: frbilu;ri 7 //i