HomeMy WebLinkAbout056PLEASANT HARBOR PHASE 2 SEIS PROCESS & TIMELINE
PC = Planning Commission BoCC = Board of County Commissioners * = Completed
20L5
STEP WHO WHAT WHY WHEN
*1 Applicant All Final Reports to Consultant For Production of Preliminary Draft SEIS October 20th
*2 Consultant Preliminary/Working Draft SEIS to County For County & Applicant Review and
comment October 27th (L week)
*3 County Staff Review & comment due back to
Consultant
Ensure accuracy and readability November 10th
(2 week)
,k4 Consultant Produce Final Draft lncorporate staff & applicant comments November 17th
(l weeks)
,85 County PC meeting & BoCC Afternoon Briefing Opportunity to inform of upcoming
release, requirements, work schedule...Completed
*6 County Notice of Availability, Press Release and
Notice of Public Hearing
To inform the public of availability Concurrent with Draft SEIS release
- Step 7
,(7 County &
Consultant
Publish Final Draft and release to public Public review for 45 day public
comment period
November 19th
(1.5 weeks)
*g County &
Consultant
Open House (Brinnon School Gym) and
PC Public Meeting on Draft SEIS - after
release of the Draft but before end of
comment period
Present Project, Staff Report & Take
Public verbal and written comments December 3'd
*g County &
Consultant
Staff Review of public & agency
comments
Compile comments to address in Final
SEIS
45 davs after release of Draft SEIS
January 5th
County &
Consultant
Analyze staff, agency and public
comment from Draft - Produce Final SEIS
Release Final to public - seven days
before BoCC action. 60 day notice to
Commerce - intent to amend UDC prior
to BoCC decision
Approx. June 30th 2015
77 County PC holds Public Hearing, Deliberates &
makes Recommendation to BoCC
Required per JCC 18.45.090(3)August 5 or September 2,2015
1,2 County BoCC considers PC recommendation on
UDC Amendment & schedules Public
Hearing on Development Agreement
Required per JCC 18.45.090(4) &
18.40.8s0(s)
TBD
13 County BoCC holds Public Hearing on
Development Agreement
Required per JCC 18.40.850(5)TBD
L4 County BoCC decision to adopt Development
Agreement & regulations by resolution
Required per JCC 18.45.090(4) &
18.40.8s0(s)
TBD
Prepared by Project Planner, David Wayne Johnson revised May 5, 201,5
10
PLEASANT HARBOR PHASE 2 SEIS PROCESS & TIMELINE
PC = Planning Commission BoCC = Board of County Commissioners * = Completed
20L5
STEP WHO WHAT WHY WHEN
*1 Applicant All Final Reports to Consultant For Production of Preliminary Draft SEIS October 20th
*2 Consultant Preliminary/Working Draft SEIS to County For County & Applicant Review and
comment October 27th (l week)
,.3 County Staff Review & comment due back to
Consultant
Ensure accuracy and readability November 10th
(2 week)
*4 Consultant Produce Final Draft lncorporate staff & applicant comments November 17th
(l weeks)
*5 County PC meeting & BoCC Afternoon Briefing Opportunity to inform of upcoming
release, requirements, work schedule..Completed
,1,6 County Notice of Availability, Press Release and
Notice of Public Hearing
To inform the public of availability Concurrent with Draft SEIS release
- Step 7
,t7 County &
Consultant
Publish Final Draft and release to public Public review for 45 day public
comment period
November 19th
(1.5 weeks)
*g County &
Consulta nt
Open House (Brinnon SchoolGym) and
PC Public Meeting on Draft SEIS - after
release of the Draft but before end of
comment period
Present Project, Staff Report & Take
Public verbal and written comments December 3'd
xg County &
Consultant
Staff Review of public & agency
comments
Compile comments to address in Final
SEIS
45 davs after release of Draft SEIS
January 5th
10 County &
Consultant
Analyze staff, agency and public
comment from Draft - Produce Final SEIS
Release Final to public - seven days
before BoCC action. 60 day notice to
Commerce - intent to amend UDC prior
to BoCC decision
Approx. May 31't 2015
1.1.County PC holds Public Hearing, Deliberates &
makes Recommendation to BoCC
Required per JCC L8.45.090(3)July 1't or August 5, 2015
72 County BoCC considers PC recommendation on
UDC Amendment & schedules Public
Hearing on Development Agreement
Required per JCC 18.45.090(4) &
18.40.8s0(s)
TBD
13 County BoCC holds Public Hearing on
Development Agreement
Required per JCC 18.40.850(5)TBD
1.4 County BoCC decision to adopt Development
Agreement & regulations by resolution
Required per JCC 18.45.090(4) &
18.40.8s0(s)
TBD
Prepared by Project Planner, David Wayne Johnson revised April 9, 2015
PLEASANT HARBOR PHASE 2 SEIS PROCESS & TIMELINE
PC = Planning Commission BoCC = Board of County Commissioners * = Completed
20L5
STEP WHO WHAT WHY WHEN
*1 Applicant All Final Reports to Consultant For Production of Preliminary Draft SEIS October 20th
*2 Consultant Preliminary/Working Draft SEIS to County For County & Applicant Review and
comment October 27th (1. week)
*3 County Staff Review & comment due back to
Consultant
Ensure accuracy and readability November 10th
(2 week)
,k4 Consultant Produce Final Draft lncorporate staff & applicant comments November 17th
(l weeks)
*5 County PC meeting & BoCC Afternoon Briefing Opportunity to inform of upcoming
release, requirements, work schedule...Completed
{<6 County Notice of Availability, Press Release and
Notice of Public Hearing
To inform the public of availability Concurrent with Draft SEIS release
- SteP 7
*7 County &
Consultant
Publish Final Draft and release to public Public review for 45 day public
comment period
November 19th
(1.5 weeks)
*g County &
Consultant
Open House (Brinnon School Gym) and
PC Public Meeting on Draft SEIS - after
release of the Draft but before end of
comment period
Present Project, Staff Report & Take
Public verbal and written comments December 3'd
*r9 County &
Consultant
Staff Review of public & agency
comments
Compile comments to address in Final
SEIS
45 davs after release of Draft SEIS
January 5th
10 County &
Consultant
Analyze staff, agency and public
comment from Draft - Produce Final SEIS
Release Final to public - seven days
before BoCC action. 60 day notice to
Commerce - intent to amend UDC prior
to BoCC decision
Approx. April 30th 2015
7t County PC holds Public Hearing, Deliberates &
makes Recommendation to BoCC
Required per JCC 18.45.090(3)June 3'd or July 1st 2015
t2 County BoCC considers PC recommendation on
UDC Amendment & schedules Public
Hearing on Development Agreement
Required per JCC 18.45.090(4) &
18.40.8s0(s)
TBD
13 County BoCC holds Public Hearing on
Development Agreement
Required per JCC 18.40.850(5)TBD
74 County BoCC decision to adopt Development
Agreement & regulations by resolution
Required per JCC 18.45.090(4) &
18.40.8s0(s)
TBD
Prepared by Project Planner, David Wayne Johnson revised March 23,2OL5