HomeMy WebLinkAbout165Phase 1a consists of site clearing and grading for golf course, road network, building footprints,
and Kettle B. Commence road construction with services and begin implementation of the
vegetation management plan. Create construction materials processing location on golf course
site.
Phase 1b consists of construction of the LOSS drainfield (wastewater treatment plant back up
system), water storage tank with distribution piping at Tee 5, transit stop, construct sanitary
sewer pump stations, Sea View Villas (170 units), Golf Vistas (32 units) and utility district.
Phase 2a consists of completion of the golf course and Half-way house (adjacent to fairway 5),
develop the second well, Kettle C: supplementary replacement to Kettle B, construct
maintenance building and 52 units for staff quarters.
Phase 2b consists of construction of the Golf Terrace Recreation Center and Conference
center/spa (208 units).
Phase 3a consists of construction of the Maritime Village building consisting of 66 units and
21,000 square feet of commercial. Construct Highway 101 and Black Point Road intersection
improvements, reconstruct Black Point Road and construct new access road to WDFW boat
launch.
Phase 3b consists of construction of the Golf Terraces 2, 3, and 4 (330 units), construction of
Sea View Villas (14 units) and Golf Vistas (16 units). Complete utility district for the resort.