Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, Interim County Administrator
From: Monte Reinders, Public Works Director/County Engineer f .
Agenda Date: November 22, 2021
Subject: Supplement #2 - Contract with Tetra Tech, Inc.
Final Design - Port Hadlock Sewer
Statement of Issue: Supplement #2 extends the completion date for this design contract.
This contract with the County's sewer design team led by Tetra Tech, Inc. is for final design,
specifications, and cost estimates for the sewer treatment facility and pressurized sewer
collection system for the Port Hadlock "Core Area" as shown in the Port Hadlock Wastewater
System Value Engineering Review completed in May 2019.
Analysis/Strategic Goals/Pro's a Con's: The Port Hadlock Wastewater System Value
Engineering Review completed in May 2019 determined that significant initial costs savings
could be realized by using newly available small, pre-packaged membrane bioreactor (MBR)
equipment and a pressurized collection system. This will allow the sewer to start small in the
Port Hadlock "Core Area" and grow as demand dictates. Design work is underway, currently
at approximately 60% complete. Final completion is anticipated in summer 2022 with final
approval by the Department of Ecology in September 2022.
Fiscal Impact/Cost Benefit Analysis: $1,472,665. The Washington State Legislature has
provided $1,422,000 as a direct appropriation through the Department of Commerce to fund
this work.
Recommendation: Please sign three (3) originals of Supplement #2 and return two (2) fully
executed originals to Public Works.
Department Contact: Monte Reinders x242
Reviewed By:
%de
Mark McCauley erim County Administra o ate
Supplemental Agreement Number: #2
Organization, Address, and Phone:
Tetra Tech, Inc.
1420 Fifth Avenue, Suite 600
Agreement Number: N/A
Seattle, WA 98101
Project Number: 405 1693-5
Execution Date:
Completion Date:
4/20/2020
12/31/2022
Project Title: Port Hadlock Wastewater
New Maximum Amount Payable:
System — Final Design
$19472,665
Description of Work: Final design of the Port Hadlock Wastewater Treatment Plant and
Collection System for the Port Hadlock "Core Area".
SUPPLEMENTAL AGREEMENT
The Local Agency of Jefferson County hereby amends the agreement with Tetra Tech, Inc. ("the
Agreement"), executed on April 20. 2020.
All provisions in the Agreement remain in effect, except as expressly modified by this
Supplemental Agreement.
The changes to the Agreement are described as follows:
I.
Scope of Services is hereby changed to read: No Change
II.
Time for Performance is hereby changed to read: The Agreement shall terminate on December 31,
2022 unless amended in writing prior to this date.
Payment is hereby changed to read: No Change
Supplemental Agreement (to A & B) Contract C, Version 1, Risk Legal Review Date 04/30/2018 Page 1 of2
This Supplemental Agreement shall be effective upon execution by both parties. Work performed
consistent with the Agreement prior to execution of this Supplemental Agreement is hereby ratified.
In witness whereof, the parties hereto have executed this Supplemental Agreement #2 as shown
below.
(Consultant Firm Name)
COUNTY OF JEFFERSON
BOARD OF COMMISSIONERS
Tetra Tech, Inc.
Consultant's Name Kate Dean, District 1 Date
f ���57
•I/
Consultant's Signature Heidi Eisenhour, District 2 Date
November 16, 2021
Date
Approved as to form only:
PRE -APPROVED CONTRACT FORM
Philip C. Hu Date
Chief C' Deputy Prosecutt g Attorney
Monte ers, . .
Public Works Director/County Engineer