Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, Interim County Administrator
From: Monte Reinders, Public Works Director/County Engineer
Agenda Date: February 14, 2022
Subject: Supplement #3 - Contract with Tetra Tech, Inc.
Final Design - Port Hadlock Sewer
Statement of Issue: Supplement #3 adds scope and budget to the Final Design contract with
Tetra Tech, Inc. for the Port Hadlock Sewer project. Completion time remains unchanged.
Analysis/Strategic Goals/Pro's a Con's: The following scope and budget items are added to
the current contract:
• Old Alcohol Plant sewer extension scoping study. $37,477
This work will develop a concept level design to determine how the Old Alcohol Plant
and marina properties could be connected to the Port Hadlock Sewer in the future.
The Old Alcohol Plant is within the Urban Growth Area (UGA), and the Port Hadlock
sewer system would benefit by having the additional flow and customer base provided
by these properties. It is important to know how this area could be served by sewer so
that provisions for its future connection to the Hadlock Phase I sewer area can be
planned for now. Cost estimates for this extension/connection will be developed.
• Operations/Maintenance/Admin estimating and rate studies. $64,978
This work will update the estimates for operations, maintenance, and administration
costs for the Port Hadlock sewer. The O&M costs in the Sewer Facility Plan contained
many assumptions that can be refined as more information is developed though the
design phase. The Consultant will work with the County and the PUD to develop
detailed costs for the operation, maintenance, and administration of the sewer system
at key design milestones. This information will be used for rate setting and rate
structure creation in a sewer ordinance.
Fiscal Impact/Cost Benefit Analysis: $102,455. This additional work will be funded by the
County through the Tri Area Sewer fund. The County has directed American Rescue Plan Act
(ARPA) money into the Tri Area Sewer fund.
Recommendation: Please sign three (3) originals of Supplement #3 and return two (2) fully
executed originals to Public Works.
Department Contact: Monte Reinders x242
Department of Public Works
O Consent Agenda
Page 2 of 2
Reviewed By:
"41/0//c
Mark McCauley, I rim County Administrato Date
Supplemental Agreement Number: #3 Organization,Address, and Phone:
Tetra Tech, Inc.
1420 Fifth Avenue,Suite 600
Agreement Number: N/A Seattle,WA 98101
Project Number: 405 1693-5 Execution Date: Completion Date:
4/20/2020 12/31/2022
Project Title: Port Hadlock Wastewater New Maximum Amount Payable:
System—Final Design $1,575,120
Description of Work: Final design of the Port Hadlock Wastewater Treatment Plant and
Collection System for the Port Hadlock "Core Area".
SUPPLEMENTAL AGREEMENT
The Local Agency of Jefferson County hereby amends the agreement with Tetra Tech. Inc. ("the
Agreement"), executed on April 20. 2020.
All provisions in the Agreement remain in effect, except as expressly modified by this
Supplemental Agreement.
The changes to the Agreement are described as follows:
I.
Scope of Services is hereby changed to read: Additional work to perform a scoping study for future
extension of sewer service to the Old Alcohol Plant area. Additional work to develop
Operations/Maintenance/Administration cost estimates and perform rates studies at key milestone
points in the project. All as described in attached Exhibit A.
II.
Time for Performance is hereby changed to read: No Change
III.
Payment is hereby changed to read: Additional payment not to exceed$102,455 as described in
Exhibit B, attached.
Supplemental Agreement(to A&B) Contract C, Version 1, Risk Legal Review Date 04/30/2018 Page 1 of 2
This Supplemental Agreement shall be effective upon execution by both parties. Work performed
consistent with the Agreement prior to execution of this Supplemental Agreement is hereby ratified.
In witness whereof, the parties hereto have executed this Supplemental Agreement#3 as shown
below.
COUNTY OF JEFFERSON
(Consultant Firm Name) BOARD OF COMMISSIONERS
Tetra Tech,Inc.
Consultant's Name Kate Dean, District 1 Date
10:944/7/
Consultant's S ature Heidi Eisenhour,District 2 Date
ca • 5 •
Date Greg Brotherton, District 3 Date
Approved as to forin only:
a. e February 4, 2022
Philip C. Hunsucker Date
Chief Civil Deputy Prosecuting Attorney
Monte Reinders ;„ uyr.r ..w.
Monte Reinders,P.E. Date
Public Works Director/County Engineer
Supplemental Agreement(to A&B) Contract C, Version 1, Risk Legal Review Date 04/30/2018 Page 2 of 2
EXHIBIT A-1
SCOPE OF WORK
JEFFERSON COUNTY DEPARTMENT OF PUBLIC WORKS
PORT HADLOCK WASTEWATER SYSTEM DESIGN UPDATE
SERVICES
AMENDMENT NO. 1
FINANCIAL PLAN UPDATE AND OLD ALCOHOL PLANT
PUMP STATION SCOPING STUDY
GENERAL
The scope of services in this amendment provides services for updating wastewater utility financial plan
and provide a scoping study for the Old Alcohol Plant Pump Station.
The Old Alcohol Plant scoping study will better develop and define the pump station to an approximate
15% Design level. This pump station will provide wastewater service for the catchment area focused on
the former Alcohol Plant located on Hadlock Bay Road.The purpose of this scoping study is to determine
the preferred location and size/configuration of a pump station serving the Old Alcohol Plant sub-area
and to develop a Class 3 cost estimate so Jefferson County and property owner can acquire funding to
complete design and construction.
Key work items and outcome of the Old Alcohol Plant pump station study will be as follows:
• Provide adequate information to confirm that a pump station and force main serving the Old
Alcohol Plant subarea can be tied directly in to the Core Area pressure sewer
• Review of septic system records to identify location of septic system equipment, drainfield, and
building drains.
• Review of water use records and development of flow criteria to size the pump station.
• Determine preferred location of Pump Station.
• Determine pump station type, size and configuration at the Old Alcohol Plant area.
• Determine how the pump station force main will be tied in to the Core Area pressure sewer
system in the vicinity of Scott Rd and Curtis Street—determine equipment type,size, and
configuration.
• Coordination with WSDOT on the installation of the force main and variance request for open
cut installation.
• Develop an estimated construction cost.
The services for updating the financial plan will provide better clarity on operation and maintenance
costs and anticipated monthly O&M costs per customer and anticipated wastewater service rates.
Key work items and outcomes of the financial plan update services will be as follows:
• Update the operation and maintenance cost estimate for the Pt. Hadlock Treatment Plant&
Collection System.
• Develop a rate study recommended rate structure to help clarify how rates will be charged.
SCOPE OF WORK
TASK 100 — PROJECT MANAGEMENT
This task includes supplemental budget to track, monitor, plan,and manage the work within the scope
of this amendment.
Work in this task is described as follows:
• Health and Safety Plan- It is assumed there will be no field work on this project and the project-
specific Health &Safety Plan (HASP)for the Core Area Design Project will largely apply for the
work within this amendment. A review of the HASP and updates to the Health and Safety
Checklist reflecting the work tasks of this amendment will be conducted.
• Progress Updates-Progress updates will be held by telephone approximately once a month, as
needed,with the County to coordinate work activities and keep the County informed of
progress to date. It is assumed this project will be accomplished within 3 months of notice to
proceed and there will be up to 2 progress updates during that period between the County and
the Consultant Project Manager.
• Progress Reports and Billings-Tt will include brief monthly progress reports along with monthly
invoices. Progress reports will contain information on major activities, anticipated actions, and
outstanding issues to be resolved.
Work Products:
• Updates/revision to project HASP.
• Summary of Action Items and follow up.
• Monthly progress reports and invoices
TASK 2000 — OLD ALCOHOL PLANT SCOPING STUDY
Subtask 2000.1 - Information Review & Criteria Development
The purpose of this task to review existing information, confirm site conditions, and confirm flow
conditions. This information will inform the location and elevation of the Alcohol Plant Pump Station,
pump type and size,wetwell geometry and size, and force main diameter.
Work activities to be completed in this task are as follows:
• Investigate the available septic system plans at the Alcohol Plant and marina.
• Site visit coordinated with County staff and property owners to confirm location of existing
septic systems, building drains, possible pump station locations and other key site features.
• Determine the location of existing building drains and connections to the existing septic
system(s).
• Identify a location for the pump station and configuration of connection building drains.
• Review flow analysis conducted during the Core Area design. Confirm estimates of average flow
and develop anticipated peak instantaneous flows from the Old Alcohol Plant water records.
Develop peaking factor to account for commercial use and hotel events.
• Review any water use data from the marina. Confirm average and anticipated peak
instantaneous flows.
• Review Facility Plan information and estimate future flows for the sub-area for infill
development.
• Identify pump size and force main diameter based upon existing and future flows.
• Identify wet well size and configuration
Work Product:
Technical memorandum documenting existing site conditions, existing water use,and design flows(both
existing and future)for the Old Alcohol Plant Pump Station.The technical memorandum will identify the
recommended pump type,size (identify one or more models) and force main diameter. A draft
technical memorandum will be submitted to the County. Comments will be reviewed and incorporated
in to a final technical memorandum. It is assumed there will be no field visits by the Consultant. Any
field work will be conducted by County staff in coordination with the Consultant Team.
Subtask 2000.2 - Schematic Plans
The purpose of this task to develop a schematic design of the Old Alcohol Plant Pump Station,force
main, and the Grinder Pump Transfer Station to approximately the 15%design level.
Work activities to be completed in this task are as follows:
• Locate and layout Old Alcohol Plant Pump Station based upon the information and conclusions
developed in Task 2000.1.
• Locate and layout the Grinder Pump Transfer Station in the vicinity of Scott Rd and Curtis Street
based upon the information and conclusions developed in Task 2000.1.
• No survey will be included in this task. County GIS maps including available LiDAR contours and
aerial backgrounds will be used as a base map.
• Plan & Profile Drawings of the force main alignment along Hadlock Bay Rd and Oak Bay Rd that
were developed during the 60%Core Area Design will be reused for this work product. The
alignment will be adjusted to be within the travel lane,will be double-cased, and installed with
open-cut construction. The drawings will be developed to the 15% Design Level and will be used
to advance the discussions and negotiations with WSDOT in Task 2000.3.
Work Product:
• Schematic design plans and pipeline profiles for the Old Alcohol Plant Pump Station,the Grinder
Pump Transfer Station and Force Main.
• These plans will be developed to approximately 15% Design level.
Subtask 2000.3 - Coordination with WSDOT
The purpose of this task to confirm the installation method and requirements for the force main along
the Oak Bay Road section of SR 116 between the intersection with Hadlock Bay Road, past the
intersection with Lower Hadlock Road,and West to Kively Center. Confirmation of the allowable
installation method and WSDOT requirements is an important element of the cost estimate.
Work activities to completed in this task are as follows:
• Meet with WSDOT and discuss installation details and methods of construction of the Old
Alcohol Plant force main in WSDOT right-of-way.
• Work with WSDOT to get confirmation assurances as to whether installation using open cut
trenching is acceptable and will be allowed for installation of the force main.
Work Products:
• Meeting summaries.
• If possible, permissions(even if tentative) in writing from WSDOT for force main installation
using open cut trenching along Oak Bay Rd.
• Summary of any requirements and next steps to get a variance from WSDOT.
Subtask 2000.4 - Cost Estimation
The purpose of this task is to provide a planning level cost estimate for the Old Alcohol Plant Pump
Station,force main, and Grinder Pump Transfer Station based upon the schematic drawings developed
in Task 2000.2 and project information documented in the Task 2000.1 Technical Memorandum.
Work activities to be completed in this task are as follows:
• Develop a draft AACE Class 3 cost estimate for the Old Alcohol Plant Pump Station,force main,
and Grinder Pump Transfer Station.
• Identify any cost related risks or uncertainties such as market conditions, changes in assumed
installation methods,geotechnical or excavation unknowns, etc.
• Review draft with the County.
• Incorporate any comments from the draft cost estimate.
• Submit final cost estimate.
Work Products:
• Draft Class 3 Cost Estimate.
• Meet to review draft.
• Final Class 3 Cost Estimate.
TASK 3000 — FINANCIAL UPDATE AND RATE STUDY
Subtask 3000.1 — Financial Update
This task includes the following work elements:
• Update financial model with 60%design cost estimates
• Update O&M Model with 60%design cost estimates
• Refine Financial and O&M Models with 90%cost estimates
• Refine Financial and O&M Models with 100%cost estimates
• Support management.
Subtask 3000.2 - Rate Study with Rates and Structure
This task includes the following work elements:
• Use cost estimates(Task 500)for revenue requirements
• Review local structures, including PUD
• Define customer classes for sewer utility
• Determine best rate structure for initial &future customers
• Develop rate alternatives for review
• Develop summary memo with rate recommendations
• Support management.
Schedule
Consultant shall complete Tasks 2000.1 through 2000.4 in 3 months from Notice to Proceed.
Consultant shall complete Task 3000.1 through 3000.2 within 9 months of Notice to Proceed.
CI Price Proposal Revision Date: Labor Plan Price Summary/Totals
Jan 31,2022 9 Resource Task Pricing Totals 96,755
Port Hadlock-Treatment Plant&Collection System .11 Pate 2a7.33 123.21 196a 12632 0762 11996 101.27 12671 9930 15.00%CP Fee(applied to Labor) 5,701
Technology Use Fee
Am#1-Financial Plan Update&Old Alcohol Plant PS Scoping Study Proo Area> Total Price 102,455
Submitted to:Jefferson Lounty(Attn:Monte Reinders) Unit Rate Qty s
E E
E E o 7 s Items>F.whide. Pricing by Resource
m_
3 0 :9 uUnitPa:e> $0.55
Contract Type:Cost Plus t: E r 5 i.E .1_
a Total 1 o p E t' x? Unit> ma �w Task Pricing
o ss E 2;
Schedule 8 2 Labor Hrs e a 3= a 3.2 3 3 a a N „_ .7. 3, charged to. Mae Pate Esc. Labor Subs Travel_Mat'Is&Equip o0Cs Totals
Project Phases/Tasks From rnru Months 3 0 ; 235 37 27 59 92 - z 1a - 2 Quantities> 110 0.001s 38,004 58,487 204 61 - 96,755
100 Project Management _ - - - .1 - -7 4 1 2 1,lM 1,3811
HASP Update 01/20/22 12/31/22 11.1 25 222 1 1 - - 197 197
Progress Reporting 01/20/22 12/31/22 11.1 25 222 3 2 - - 1 596 596
Billing and Status Reports 01/20/22 12/31/22 11.1 25 222 3 2 - - 1 596 596
2000 OW Aire of Plant PS Soaping Study 182 14 - 30 02 - 2 1e - -I 23o 28,416 3,436 72 61 - 54,004
2000.1 Information Review&Criteria Development 01/20/22 12/31/22 11.1 25 222 56 4 20 32 - - 110 8.973 72 61 9,105
2000.2Schematic Plans 01/20/22 12/31/22 11.1 25 222 76 18 40 - 2 16 - 10,498 10,496
2000.9 Coordination with MOOT 01/20/22 12/31/22 11.1 25 222 40 8 16 16 - - 7,156 7,156
2003.4 Cast Estimation 01/20/22 12/31/22 11.1 25 222 10 2 0 4 - - 1,789 5.456 7,245
3000 Financial Update a Rate Study 46 10 27 - _ - - . . -1 - 8,200 53,081 132 - - 61,60
30m.1 Financial Update 01/20/22 12/31/22 11.1 25 222 28 8 20 - 4,568 27,225 66 31,659
3000.2 Rata Study with Rates and Structures 01/20/22 12/31/22 11.1 25 222 18 11 7 - - 3,632 25,806 66 29.500
Totals 92 -01/20/22 12/31/i2 SLi 235 3) 27 59 2 14 2 1 Duam0ies> 110 0.0059 38,004 58,487 204 61 96,755