Loading...
HomeMy WebLinkAbout22- ITEM LOGPOMONA WOODS PROJECT CHECKLIST AND ITEM MATRIX MLA2021-00066 – ZON2021-00040 # ACTION ITEM/CONDITION COMPLETION - DATE ADDITIONAL INFORMATION Prepared by Assistant Planner, Amanda Hunt Dated: 3/2/2022 1 Pre-Application Conference held 05/04/2021 See “Exhibit K” for pre-application conference outline PDF 2 Conditional Use Permit Application received 06/23/2021 See “Exhibit T” for email 3 Application Fees paid 06/28/2021 See “Exhibit T” for email 4 Geotechnical Report received 07/14/2021 - 5 Incomplete Application Letter sent 07/23/2021 Requested information for parking plan, landscaping plan, sign plan, and stream verification, See “Exhibit I” pg. 1 for PDF 6 Revised Site Plan received 07/26/2021 Received revised site plan, and information explaining sign plan and absence of stream 7 Road Approach Permit Application received 07/28/2021 RAP2021-00068, See “Exhibit T” for email 8 Public Works Stormwater Guidance email 08/03/2021 See “Exhibit T” for email 9 SEPA Exemption Interpretation Assistance email 08/05/2021 See “Exhibit T” for email 10 Stormwater Site Plan & Large Stormwater Packet received 08/09/2021 - 11 Site Visit 08/12/2021 Assistant Planner & Staff Biologist confirmed no streams or wetlands present 12 Request for Public Works Review sent 08/13/2021 Email request sent to Public Works, See “Exhibit T” for PDF 13 Additional Information Request Email sent 08/18/2021 Requested SEPA Checklist, See “Exhibit T” for PDF 14 Soils Report received 08/19/2021 See “Exhibit D” for PDF 15 SEPA Checklist received 08/19/2021 See “Exhibit T” for email 16 Parking Plan received 08/19/2021 See “Exhibit T” for email 17 Revised Stormwater Plan received 08/19/2021 See “Exhibit T” for email 18 SEPA Invoice Sent 08/19/2021 See “Exhibit T” for email 19 Substantially Complete Application Letter sent 09/1/2021 See “Exhibit I” pg. 5 for PDF *Exhibit U* POMONA WOODS PROJECT CHECKLIST AND ITEM MATRIX MLA2021-00066 – ZON2021-00040 # ACTION ITEM/CONDITION COMPLETION - DATE ADDITIONAL INFORMATION Prepared by Assistant Planner, Amanda Hunt Dated: 3/2/2022 20 Notice of Application issued 09/15/2021 SEPA uploaded to SAW account, Comment periods ends 9/30/2021, See “Exhibit J” for PDF and “Exhibit T” for emails 21 Public and Agency Comments received 09/15/2021 – 09/30/2021 See “Exhibit O” and “Exhibit P” for PDFs 22 DRD Reviewer Letter sent to EH 10/15/2021 EH Comments due 10/29/2021, See “Exhibit I” pg. 6 for PDF 23 Revised Site Plan received 10/28/2021 - 24 Public Water Connection Feasibility Emails 10/29/2021 – 11/23/2021 See “Exhibit T” for email(s) 25 SEPA Checklist reviewed and annotated 11/04/2021 - 26 Project Review Status Update Email(s) 11/04/2021 See “Exhibit T” for email 27 Revised Stormwater Site Plan received 11/10/2021 - 28 Revised Large Stormwater Packet received 11/10/2021 See “Exhibit E” for PDF 29 Additional Information Request Letter sent 11/10/2021 Requested information for revised SEPA Checklist, Public Works review of revised site plan, FPA update, public water connection update, public comment response in application, See “Exhibit I” pg.7 for PDF 30 DPW Review Fee sent 11/10/2021 Paid 11/22/2021, See “Exhibit I”, pg. 9 for PDF 31 Revised Stormwater Site Plan 11/17/2021 See “Exhibit E” for PDF 32 Revised SEPA Checklist received 11/17/2021 - 33 DCD Phone Conference 11/18/2021 Follow Up Email sent on 11/19/2021, See “Exhibit T” for email 34 Revised SEPA Checklist received 11/22/2021 See “Exhibit C” for PDF 35 Revised Site Plan received 11/22/2021 See “Exhibit G” for PDF 36 Revised Geotech Report received 11/22/2021 See “Exhibit H* for PDF 37 Rain Garden Calculations received 11/22/2021 See “Exhibit E” for PDF POMONA WOODS PROJECT CHECKLIST AND ITEM MATRIX MLA2021-00066 – ZON2021-00040 # ACTION ITEM/CONDITION COMPLETION - DATE ADDITIONAL INFORMATION Prepared by Assistant Planner, Amanda Hunt Dated: 3/2/2022 38 Road Right of Way Email 11/28/2021 See “Exhibit T” for email 39 EH Septic Review Check In Email 12/09/2021 See “Exhibit T” for email 40 Road Right of Way Site Visit 12/15/2021 - 41 Requested Fire Department Review 01/06/2022 See “Exhibit T” for email 42 Public Works Stormwater Check In Email 01/10/2022 See “Exhibit T” for email 43 DCD Fire Department Review Letter received 01/10/2022 See “Exhibit P” for PDF 44 Additional Information Request Email sent 01/11/2022 Requested written verification from JPUD, EH, and DCD Fire Inspector that water connection, septic system, and emergency access/utilities are feasible, See “Exhibit T” for email 45 EH Septic Review Check In Email 01/26/2022 See “Exhibit T” for email 46 Certification of Water Supply Utility Service received 01/31/2022 See “Exhibit L” for PDF 47 Fire Rescue Review Letter received 02/03/2022 See “Exhibit M” for PDF 48 Check In Phone Call w/ Applicant 02/07/2022 Received additional information (FAQ Sheet) on 2/9/2022 in follow up email, See “Exhibit I” for PDF 49 EH Potable Water Sign Off Emails 02/25/2022 – 02/28/2022 See “Exhibit T” for email 50 Notice of Public Hearing issued 03/02/2022 See “Exhibit J” for PDF 51 SEPA DNS Issued 03/02/2022 See “Exhibit S” for PDF 52 Application/Staff Report issued 03/02/2022 See “Exhibit R” for PDF 53 Public Hearing 03/17/2022 -