PRISM Project #18-2561 (In Progress)
Jefferson Co Sportsmen's Club Noise-Safety Improv
Project Details
Jefferson Co Sportsmen's Assn; Jefferson Co Sportsmen's Club
Noise-Safety Improv (#18-2561) Attachment #378064, Visual of
100 yard Rifle Range
Project Status: Active since 10/23/2019
Planned Completion: 12/31/2021
This project is in progress. Project
scope, activities, and dollars may
change.
Project Type: Development
Project Sponsor: Jefferson County Sportsmen's
Association
Funding Board: Recreation and Conservation Funding
Board
Funding
Firearms & Archery Range Rec.:$150,000
Total RCO Grant:$150,000 (64%)
Sponsor Match:$86,000 (36%)
Total Agreement:$236,000(100%)
RCO Grant Status
Total RCO Grant:$150,000.00
Paid To Date:$0.00 (0%)
Grant Balance:$150,000.00(100%)
Links
Original Project Agreement
Attachments: 30 files
Project Description
The Jefferson County Sportsmen Association located near Port Townsend will use this grant to control noise and provide safer shooting on their 100 yard range. The scope
of this project is to install noise abatement and projectile control stalls with appropriate electrical work and site preparation. The primary recreational opportunity provided by
this grant is recreational shooting.
Project Contacts
Project Sponsor:Jefferson County Sportsmen's
Association
Project
Contact:
Don McNees
pt9baja@gmail.com
(360) 774-2991
Funding Agency:Recreation and Conservation Office
Project
Manager:
Rory Calhoun
rory.calhoun@rco.wa.gov
(360) 867-8328
Project Location
County: Jefferson
Legislative Districts 2012: 24
Congressional Districts 2012: 06
Sections: 08
Township: T30NR01W
Coordinates: 48.10214039
-122.82326543
Worksites
Worksite Name Scope of Work
Proposed Development
Cost
Jefferson County Sportmen's
Assn 100 yd (#1)
Architectural & Engineering (A&E), Cultural resources,
General site preparation, Install power utilities, Install
safety/noise abatement items, Install stormwater system,
Obtain permits
$236,000
Total $236,000
Amounts may not be complete
Properties
Worksite Name Property Name
Landowner
Type
Jefferson County Sportmen's
Assn 100 yd (#1) Property 1 - Jefferson County
Sportmen's Assn Range
Local
Government
Total
Amounts may not be complete
Project Metrics (Outcomes, Benefits)
Category / Work Type / Metric Proposed
Restoration Metrics (rolled up from Worksite level)
Permits
Obtain permits
Number of permits required for implementation of project 3
Archery and Firearms Range Elements
Install safety/noise abatement items
Linear feet of containment walls 100
Site Preparation
General site preparation
Acres of site preparation 0.04
Project Permits
Permit Type
Applied
Date
Received
Date
Expiration
Date Permit Number
Building Permit
Other Required Permits
Project Milestones
Milestone Name Target Date Description
Project Start 08/01/2019
Design Initiated 08/01/2019
Progress Report Due 01/31/2020
Submit Self-Cert Design 02/29/2020
Cultural Resources Complete 04/30/2020 Survey required, see special condition #1
60% Plans to RCO 06/30/2020
Annual Project Billing Due 07/31/2020
Progress Report Due 07/31/2020
Applied for Permits 08/01/2020
All Bid Docs/Plans to RCO 09/30/2020
Bid Awarded/Contractor Hired 10/31/2020
Progress Report Due 01/31/2021
Construction Started 02/28/2021
50% Construction Complete 05/31/2021
RCO Interim Inspection 05/31/2021
Progress Report Due 07/31/2021
Annual Project Billing Due 07/31/2021
90% Construction Complete 08/31/2021
Funding Acknowl Sign Posted 08/31/2021
Construction Complete 09/30/2021
RCO Final Inspection 10/31/2021
Submit Self-Cert Completed 10/31/2021
Final Billing Due 10/31/2021
Final Report Due 11/30/2021
Agreement End Date 12/31/2021
NOTE: This data is subject to change.
Project Attachments
Attachment Type Attachment Title Attach Date
Agreement - State 18-2561 Agreement.pdf.pdf 10/23/2019
Applicant
Resolution/Authorizations
JCSA Resolution 2019 01 14.pdf.pdf 01/14/2019
Application Review Report Application Review Report, 18-2561D(compl 01/25/19 14:45:32).pdf 01/25/2019
Application Review Report Application Review Report, 18-2561D(rtnd 11/29/18 13:46:48).pdf 11/29/2018
Certification of Applicant
Match
JCSA Certification of Match.pdf.pdf 04/24/2019
Control & Tenure
Documentation
JCSA License Agreement.pdf.pdf 11/04/2018
Correspondence Map parcel undefined .docx.docx 01/14/2019
Evaluation: Project
presentation - Final
FARR Grant 18-2561 - JCSA Noise Abatement and Safety Stalls.pptx 02/14/2019
Evaluation: Project
presentation - Tech Review
Mtg
18_2561_JeffCo_Sportsmans_NoiseAbatement_and Safety
Stalls.p.pptx
11/09/2018
FARR Application Maps and
Visuals
Visual of 100 yard Rifle Range.jpg 02/01/2019
FARR Application Maps and
Visuals
2nd Visual of 100 yard Rifle Range.jpg 02/01/2019
FARR Application Maps and
Visuals
Looking down 50 yard range firing line.jpg 02/01/2019
FARR Application Maps and
Visuals
Warming shed looking down to 100 yard Rifle range.jpg 02/01/2019
FARR Application Maps and
Visuals
50 yard range firing line.jpg 02/01/2019
FARR Application Maps and
Visuals
Downrange of 50 yard Rifle/pistol range.jpg 02/01/2019
FARR Application Maps and
Visuals
Overhang on firing line of 40 yard pistol range.jpg 02/01/2019
FARR Application Maps and
Visuals
Firing line on 40 yard pistol range.jpg 02/01/2019
FARR Application Maps and
Visuals
100 yard range from up hill toward the back berm.jpg 02/01/2019
FARR Application Maps and
Visuals
AppMapsandVisualsAttachment-Dev_JCSA_NoiseAbatmnt.pptx.pptx 01/14/2019
Map: Boundary map – Draft Boundary Map.docx.docx 11/05/2018
Map: Boundary map – Final Aerial Overview JCSA.docx.docx 11/04/2018
Milestones JCSA Development-FARR_06_03_2019.pdf.pdf 06/03/2019
Photo 2 JCSAYouthFirearmsTraining.jpg.jpg 11/04/2018
Photo 1 JCSA100yardRifleRange.jpg.jpg 11/04/2018
Progress report Progress Report, 18-2561 (accepted 01/25/20 14:18:34).pdf 01/25/2020
Project Application Report Application Report, 18-2561D (submitted 01/14/19 15:10:30).pdf 01/14/2019
Project Application Report Application Report, 18-2561D (submitted 11/07/18 16:29:45).pdf 11/07/2018
Site Plan: Conceptual Site
Plan
Plans Safetyand NoiseAbatement Modules.pdf.pdf 11/04/2018
Site Plan: Conceptual Site
Plan
1 SafetyandNoiseAbatementModule_Plan.pdf.pdf 11/04/2018
Site Plan: Development site
plan
1 FARR_JCSA Proposed Work SIte.docx.docx 11/04/2018
Date of last change: 01/31/2020