Loading...
HomeMy WebLinkAbout042522ca04 Department of Public Works O Consent Agenda Page 1 of 1 Jefferson County Board of Commissioners Agenda Request To: Board of Commissioners Mark McCauley, County Administrator From: Monte Reinders, P.E., Public Works Director/County Engineer/k. Agenda Date: April 25, 2022 Subject: Change Orders No. 2, 3, and 4, for SR 116 and Cedar Avenue Pedestrian - Bike Improvements Project, Project No. 1802057, County Road No. 637109, WSDOT Project No. HLP-SR19(006) Statement of Issue: Change Orders No. 2, 3, and 4 with Interwest Construction, Inc. of Burlington, Washington. Analysis/Strategic Goals/Pro's £t Con's: These change orders consist of: Change Order No. 2: Substitution of Crushed Surfacing Top Course for all occurrences of Crushed Surfacing Base Course in order to improve the constructability methods for this project. Change Order No. 3: Changed condition for constructing concrete sidewalk adjacent to the installed Pedestrian Light Poles along Cedar Avenue. Change Order No. 4: Removal of 2 utility poles that conflict with the proposed concrete sidewalk. Fiscal Impact/Cost Benefit Analysis: Change Order No. 2 adds no ($0.00) additional cost or Working Days. Change Order No. 3 adds $6,266.40 and 2 Working Days. Change Order No. 4 adds $1,075.02 and 'h Working Day. The total cost increase for all 3 change orders is $7,341.42. This project is funded at 100% by a WSDOT Safe Route to School Program (State) grant. Recommendation: Public Works recommends that the Board authorize Change Orders No. 2, 3, and 4 with Interwest Construction, Inc., and return two originals of each to Public Works for further processing. Department Contact: John Wayand, Project Manager, 385-9377. Revie By: ire Le 'IA/AZ-- Mark McCa:14, County Administrator Date I of 2 4/6/2022 ❑O(dered by County Engineer under terms of Section I - 04.4 of the Standard Speci mentions � Clmtrgc proposed by Contractor Endorsed by: Interwest Construction, Inc. r� / Contractor Flrar Nante 1l lgnarrn'e re are ?Y6hAA-4- Title Consent given by Surely: (whe)t required) By: Date JEFFERSON COUNTY DEPARTMENT OF PUBLIC WORKS CHANGE ORDER Contract No. .1.0: No. Interwest Construction, Inc. 609 North Hill Blvd. ! Burlington, WA.98233 i Project Title SR 116 and Cedar Ave. Ped: Blke Improvements Project No. 1802057 You are ordered to perform the following described work upon receipt of an approved copy of this change order: Item 13 Crushpd.19yrfarinsr Base Course This change order reduces the quantity of Bid Item 13, Crushed Surfacing Base Course (CSBC). to 0 CY. Item 14 Crushed Surfacing Ton Course This change order corrects the Unit type for Bid Item 14, Crushed Surfacing Top Course (CSTC) from CY (cubic yards) to T (tons), and revises the Quantity from 105 CY to 605 T. This change in material type Is being made at the Contractor's request in order to improve the constructibility of the materials to be placed around and under the concrete curb, gutter, sidewalk, and multi -use path by substituting CSTCfor CSBC, The Contractor and the Agency have negotiated a new unit price of $53.215 per Ton for Bid Item 14, Crushed Surfacing Top Course. Estimated cost is $0 Change in Contract Time: 0 additional Working Days Total Change Order 2 Summary -$26,000.00 Item 13 Crushed Surfacing Base Course Estimated Net Cost Decrease $26,000.00 Item 14 Crushed Surfacing Top Course Estimated Net Cost Increase $0.00 Total Estimated Net Cost Change All work materials and measurement to be in accordance with the provisions of the standard specifications and special provisions for (lie pe of construction involved. F) ORIGINAL CURRENT ESTIMATED ESTIMATED CONTRACT CONTRACT NETCHANGE CONTRACTTOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $573,723.61 $576,331.82 $0.00 $576,331.82 ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT CONTRACT TIME CONTRACT TIME CHANGE (Add/Del) TIME:. F 75 Working Days 77 Working Days 0 Working Days 77 Working days s. APPROVAL RECOMMENDED APPRO L t?d &ENDED -e- , mwe t 40411 r Date Corrrrty 4s41rr6 Date APPRO At, ECOMMIiNDED APPROVED Trrgttrrerireg Se ices Manager Date Chair, de17erson County Commissioners Date W O 0 0 O 0 0 0 z c7 �o �) o N 0 N rn o 0 00 m v� c p v . O o �O � M c � N N d4 M 69 M 69 O o d OO z O O M H H � E06 E<3 69 6R3 69 69 u► z H x U F N N N CDO pp r- kn O Ey Z O N M 110 W d z A w 3 v o 0 0 W N z a Ln kn� M M M [� 69 � � G W z w z O 0 o O 0 0 b o � O U U. z o 0 0 0 ] 0 rn o o o a vi ON all o,n o 6A 69 &S 69 Gq zap' 00 O I` O O O XH C N N W a W O O O U O 0 0 �i cV 6�A Go!� Goq 669 Goll 669 U z a zz Up. W �D a O OO O O 0 az0 �a o Q a 4N 421 U W ° 0 0 U z U U U U U U U F- ON N O ct 0 O zM w � N H w Sheet I of 2 DEPARTMENT OF PUBLIC WORKS Change Datc: 4/18/2022 CHANGE ORDER Order No. Ordered by County Engineer under onns of Section I -04, 4 orthe Standard Specifications FIClumge by Contract No, proposed Contractor To; Interwest Construction, Inc. r dor by; InterwestConsirtletion, Inc, 609 North Hill Blvd. Caruaclorl7rrn Name Burlington, WA, 98233 minafrrr Dale ,(6 t Ir'fLAL� Project Title 77de Consent given by Surely: (whert required) SR 116 and Cedar Ave. Pcd.-Bike Improvements By; Project No. 1802057 Rlrorrrey-Irr jiaer Dale You are ordered to perform the following described work upon receipt or an approved copy of this change order: item 52 Mitigation for pedestrian Light Pole installation This change order adds one new item "Item 52 Mitigation for Pedestrian Light Pole installation, per Each" and per Standard Specification 1-04.7. The Contractor has claimed that different site conditions have been created by the installation by the PUD of the Pedestrian Light Poles along Cedar Avenue, which will cause additional work and ' delays for the Contracor. The Contractor has agreed that the resulting additional work and delay only applies to the 14 Pedestrian Light Poles along Cedar Ave. Estimated cost is: $6,266.40 Change in Contract Time: 2 additional Working Days Total Change Order 3 Summary $6,266.40 Item 52 Mitigation for premature Pedestrian Light Installation by the PUD $6,266.40 Total Estimated Net Cost Change All work materials and measurement to be in accordance with the provisions of the standard specifications and s ccial provisions for the tYve of construction involved, ORIGINAL CURRENT tis•rIMA•ml) ESTIMATED CONTRACT CONTRACT NFTCIIANOE CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $573,723.61 $576,331.82 $6,266,40 $582,598.22 ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT CONTRACT TIME CONTRACT'TIME CHANGE(Add/Del) TIME 75 Working Days 77 Working Days 2 .Working Days 79 Working days APPROVAL RECOMMENDED APPW AL itECO -NIN L7 Prnfa Marmger Dale Coanly Engineer Date 'PROM . ItCCUMMRNDED APPROVED Crrghreerhrg So.rvict M—ager Date Chair, Jefferma County Commissioners Date \ \ \ $ f $ $ 7 G / / k ! Q f) \ _ t = 0 7 _ � z � 3 z -- - � @ e 2 ? S ® \ \ s z _ re I \ j \ j §�\ f y f 2 \ \ , of w V�\ \ = o c \ ± j 2 o� @ o g 0 g \/ \ GO,) $ a \ ZU. 4 2 / / / 4 q j 2 § ( § .2 / \ f \ \ ./ ¥ ~ \ LU�� LQ I of 2 DEPARTMENT OF PUBLIC WORKS 'Imnej, 4/18/2022 Ordered by County Engineer under tenns of ,,,Svood r I - 04. 4 of the Standard Specifications Change proposed by Contractor I ndorscd by: Interwest Construction, Inc. Contractor) -,inn Nanre Signerinre are rat " ti % Tille Consent given hy.Surery: (when regnirecl} By: Dcrte CHANGE ORDER No. Contract No. To: Interwest Construction, Inc. 609 North Hill Blvd, Burlington, WA, 98233 Project Title SR 116 and Cedar Ave. Ped.-pilce Improvements Project No, 1802057 You are ordered to perform the following described work upon receipt of an approved copy of this change order: Item 3 Removal of Structures and Obstructions This change order adds additional work to the existing item "Item 53 Removal of Structures and Obstructions" per Standard Specification 1-04.4. This change order provides for removing two existing utility poles that conflict with the proposed concrete sidewalk location. The poles are located on the west side of Cedar Ave, at the 1st street intersection and at the 2nd street Intersection. Estimated cost is: $1,075.02 Change In Contract Time: 0.5 additional Working Days Total Change Order 4 Summary $1,075.02 Item 53 Removal of Structures and Obstructions $1,075.02 Total Estimated Net Cost Change All work materials and measurement to be in accordance with the provisions of the standard specifications and special provisions -for the tylic of construction involved. ORIGINAL CURRENT ESTIMATED ESTIMATED CONTRACT CONTRACT NETCIIANGE CONTRACTTOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $573,723.61 I $592,598,22 J $1,075.02 I $583,673.24 ORIGINAL CONTRACT TIME 75 Working Days APPROVAL RECOMMENDED ED , If e �r M 8ngineeringSe►�irpr Manager CURRENT CONTRACT TIME NEW CONTRACT CONTRACTTIME CIIANGE(Add/Del) TIME 79 Working Days 0.5 Working Days 79.5 Working days A�VAI. R[iCUMM]? D� Dale County Gngineer Aml,di'l, APPROVED D Chair, Jefferson Coumy Comad.5sionerr L Date Date 69I 69 69 z F a 0 W kn N �o 0000 3 a H o � o U zFz z 0 r CY of o A W E� U �y vi 0000 116 GS vi v-i 0000 0000 6s sus fs1 z U U O C7 a F z O o O 0 O 0 C O o� ,-• o k W ri 69 (V b9 vi b9 F Z kli 7 k b ¢ O O a o O 0 0 i �:n U W O O CD O CDR O W i a, 00 09 m W U a W vi ¢ a a s Lu wD W U o < 0 4 � to >.� >V3 ° v° _ N N O p O W cv E O N O � � N - -"w T cr